
Figure 1: Pile-driving rig near active runway. |
Detroit Metropolitan Airport’s South Access Road-Midfield
Segment is a four-lane roadway with ramps that will connect it to
the proposed World Travel Center. Due to poor soil conditions, the
retaining walls adjacent to the access road construction site were
designed with pile footings. Consequently, the contractor would
have to mobilize a pile-driving rig only 160 feet (50 meters) from
the centerline of an active taxiway (Figure 1).
FAA Approves Construction Plan
At the onset of the project, Wayne County officials sought approval
from the Federal Aviation Administration (FAA) to allow equipment
heights to penetrate the restricted airspace during construction
of the road. FAA regulations generally prohibit tall equipment from
operating in areas near active runways and taxiways or require lowering
such equipment at the time of take-offs or landings.
The FAA approved the County’s construction safety plan and
allowed equipment heights 65 feet (20 meters) over the seven horizontal
to one vertical (7:1) slope of the “imaginary surface”
defined by Federal Aviation Regulation Part 77: Objects,
with continued use of the runways and taxiways for airport operations.
This approval was for an 18-month construction schedule. As an added
level of safety, specifications were written to require the contractor
to lower the booms at the end of each workday, during marginal weather
conditions, and within a half hour after specific notification from
the air traffic control tower. FAA also required that cranes and
backhoes penetrating the 7:1 slope be equipped with red flags.
 |
Cost of Lowering the Boom
What wasn’t known until construction time neared was that
lowering the boom on a pile driving rig is not simple. One must
dismantle the hammer and rigging, a task that requires several hours
of down time to the contractor. The cost of such an operation would
be tremendous. In this case, pile-driving was an item on the contractor’s
critical path schedule. Forcing the contractor to adhere to the
letter of the specification could have delayed the project as much
as 85 calendar days.
Upright Boom Approved
Wayne County officials submitted a plan to the FAA requesting that
the contractor be allowed to leave the boom in the upright position
during pile driving operations. The FAA required the contractor
to place a red flashing beacon on the top of the boom to alert incoming
planes and the tower of its location and issued a NOTAM (notification
to airmen) to alert the pilots of the construction situation at
the Detroit Metropolitan Airport.
Thus far, the contractor, airport operators and Wayne County Field
personnel are pleased with the operation. The contractor is in daily
contact with the tower, the project is on schedule and the solution
works for all involved. |