 |
Baltimore Metro - Section C
Location: Baltimore, Maryland
Owner: Maryland Mass Transit Administration
Role: PB was retained, in joint venture, to provide
final design and construction related services during the Baltimore
Metro - Section C project.
PM: Colin Lewis
Date: Scheduled for completion in 1996.
SPTC walls with reinforcing between soldier piles were selected
for the permanent walls of the 186-m- (610-foot-) long Shot Tower
Station. An approximately 12-meter (40-foot) section of the main
station was constructed using a jet-grouted cutoff wall in order
to accommodate and not disturb existing electrical lines. (see "Constructing
Slurry Walls For Baltimore’s Shot Tower Station")
Panchiao Extension Project
Location: Taipei, Taiwan
Client: Taipei Railway Underground Project Office
Role: PB was involved in all phases of the Panchiao
Extension Project, served as general consultant and provided detailed
design review and construction advisory services for a segment of
the railway undergrounding program.
PM: Norman Crook
Date: Completed in 1996.
Project site is characterized by a high groundwater table and relatively
poor soil; some adjacent building foundations are less than 1 meter
(3 feet) from the excavation. Braced slurry walls were used for
most of the temporary support where deep excavations were required.
Slurry walls with eight levels of bracing were required near the
Hsintien River, where the excavation depth exceeds 24 meters (78
feet).
 |
63rd Street Tunnel Connection
Location: New York, New York
Client: MTA NYC Transit
Role: PB, in joint venture, is providing final
design services including design support during construction and
contract close-out.
PM: Lou Silano
Date: Revenue service expected to begin in 2001.
More than 900 m (3,000 feet) of slurry walls are proposed in a portion
of the project where new track sections will cross under the existing
Queens Boulevard Line tracks prior to merging with them. The walls
will control groundwater, providing a relatively watertight enclosure
in an area where external dewatering could not be used because of
the potential impact of drawdowns on nearby contaminant plumes and
consolidation of peat deposits below nearby structures. (see "Using
Slurry Walls to Control Groundwater During Subway Construction")
 |
Beth Israel Hospital Clinical Center
Location: Boston, Massachusetts
Owner: Beth Israel Hospital
Role: PB, as a subconsultant to an architectural
firm, provided design management and construction services for the
underground portions of the clinical center.
PM: Eldon Abbott
Date: Completed in 1996.
Project included the construction of a five-level underground garage
that provided foundation support for a 20-story medical facility.
Construction included slurry walls to reduce impacts to adjacent
buildings. The slurry wall was designed for two future openings—
a service tunnel and a connection to a future adjacent garage.
Rio Salado Town Lake Project
Location: Tempe, Arizona
Client: Engineering Division, City of Tempe
Role: PB will provide full construction administration
services.
PM: Ollie Park
Date: Scheduled for completion in February 1998.
Plan calls for converting a section of the Salt River channel into
a recreational lake. Approximately 1.6-kilometer- (1-mile-) long
slurry bentonite cut-off walls will be constructed in the channel
invert paralleling the lake boundary. The walls will be up to 15
m (50 feet) deep and will minimize seepage from the downstream half
of the lake area.
North-South Toll Road Construction Inspection
Location: Chicago, Illinois
Client: Illinois State Toll Highway Authority
Role: PB provided construction inspection services.
PM: James Gunraj
Date: Completed in 1989.
Project included 600 m (2,000 feet) of slurry wall construction.
Harvard Square Station
Location: Cambridge, Massachusetts
Client: Skidmore Owings & Merrill
PM: Morris Levy
Date: Completed in mid 1980s.
First slurry wall to be used for both permanent and temporary conditions
for rapid transit tunnel in the U.S. Project included approximately
300 meters (1,000 feet) of tied back slurry wall for excavation
depths of 17 m (55 feet). Excavation was as close as 2.1 m (7 feet)
to historic Harvard University structure founded on shallow spread
footings. Deformations were typically maintained at less than 6
mm (1/4 inch) horizontal and vertical.
Post Office Square Park and Garage
Location: Boston, Massachusetts
Client: Friends of Post Office Square, Inc.
Role: PB was retained as the lead firm to provide
design services for a seven-level parking garage in the middle of
Boston’s financial district.
PM: Eldon Abbott
Date: Completed in 1990.
Project included excavating the deepest excavation to date in the
Boston area, approximately 25 m (80 feet), with adjacent buildings
typically located on shallow foundations. Most adjacent structures
were within 15 m (50 feet) of the excavation. Construction used
the top down method, soil profile included deep, soft clay deposit,
approximately 335 m (1,100 feet) of slurry wall, permanent underdrain
system, no reported damage to adjacent structures.
Boston Crossing Project
Location: Boston, Massachusetts
Client: Campeau Massachusetts Inc.
Role: PB was retained to provide a range of planning,
design and permitting services.
PM: Andrew Boyd
Date: Completed in 1989.
Project included a slurry wall location study.
 |
 |
Central Artery/Tunnel
Location: Boston, Massachusetts
Owner: Massachusetts Highway Department
Role: PB, as part of the Bechtel/ PB joint venture,
is serving as management counsultant.
PM: Tony Lancellotti
Date: Scheduled for completion in 2004.
Downtown portion of the project includes approximately 7 km (23,000
feet) of SPTC slurry wall. The slurry walls will form the permanent
walls of the highway tunnels, being excavated beneath the 6-lane
I-93 viaduct as it remains in use. About a third of the length of
slurry walls will be constructed under low head room. (see "Constructing
Slurry Walls Under Low Head Room," "Slurry
Wall Design Parameters," "Using
SPTC Walls as Permanent Tunnel Walls," "Should
Slurry Walls Be Part Of the Final Structure?")
MBTA Tunnel Ventilation Shafts
Location: Boston, Massachusetts
Client: Massachusetts Bay Transportation Authority
Role: PB provided planning, design, architectural/engineering,
and construction-phase services.
PM: Bill McMenimen
Date: Completion date scheduled for 1996.
Thirty ventilation shafts and/or emergency exits at 30 locations
along three existing transit lines. Slurry walls designed at some
sites to minimize ground movement and avoid potential damage to
the subway tunnel and nearby historic structures.
 |
Long Wharf Vent Shaft
Location: Boston, Massachusetts
Client: Massachusetts Bay Transportation Authority
Role: Geotechnical study as part of investigation
of condition of wharf and condition of granite sea walls for eventual
rehabilitation of pier end into a public park.
PM: Eldon Abbott
Date: Completed mid 1980s.
Project included slurry wall construction on the Boston water front
for an approximately 23-m- (75-foot-) deep excavation immediately
adjacent to the existing MBTA Blue Line Tunnel. Construction included
use of permanent soldier piles to accommodate cross-lot bracing
that served as both temporary bracing and the permanent floor levels
for the vent structure. It was necessary to buttress the Blue Line
Tunnel with the slurry wall to maintain water control and the structural
stability of the tunnel. This necessitated excavating and casting
the slurry wall in contact with the existing unreinforced concrete
tunnel.
 |
 |
North Station Parking Garage
Location: Boston, Massachusetts
Client: Massachusetts Bay Transportation Authority
Role: Lead designer
PM: Rich O’Brien
Date: Completed in 1993.
Approximately 520 m (1,700 feet) of slurry wall construction employing
top down scheme and permanent underdrain. Excavation was approximately
18 m (60 feet) deep through primarily organic soils and located
1.2 m (4 feet) off the existing Boston Garden Arena. Excavation
extended 9 m (30 feet) below the foundation of the existing Garden,
which maintained operations throughout the construction. (see "Tips
for Slurry Wall Structural Design")
North Station Super Station
Location: Boston, Massachusetts
Client: Massachusetts Bay Transportation Authority
Role: Lead designers and providing construction
phase support services in joint venture with STV Inc.
Project Manager: Rich O’Brien
Date: Completion scheduled 1999.
Project includes the construction of a new underground Green Line
Station immediately adjacent to the existing Orange Line Station.
Approximately 530 m (1,900) feet of slurry wall is under construction.
Greater Cairo Metro - Line 2/Phase 1
Location: Cairo, Egypt
Owner: National Authority for Tunnels (NAT)
Role: Greater Cairo Metro Consultants, a joint
venture of PB, Electrowatt Engineering Services and Sabbour Associates,
is providing design review and construction management services.
PM: Bob McDonald
Date: Phase 1A in scheduled for completion in October
1996 and Phase1B is scheduled for completion in September 1997.
Unreinforced cement/bentonite slurry perimeter wall box with an
impermeable chemical grouted hard gel base plug beneath the jet
grout treatment was used as supplemental ground water control in
critical areas. (see "Cairo
Metro Slurry Walls")
Santa Cruz Freshwater Bypass
Location: Santa Cruz, California
Client: City of Santa Cruz
Role: Landfill freshwater by-pass system feasibility
study. Also PS&E and design services during construction.
PM: Lee Abramson
Date: 1996
Soil-cement-bentonite slurry cutoff walls were constructed to prevent
subsurface migration of fresh water into the landfill. The walls
are part of the solution to regulations that required fresh water
to be intercepted above the landfill, conducted around it and discharged
downstream of the landfill, back into the creek bed that the landfill
occupies. (see "Slurry
Wall Cutoff at Santa Cruz Landfill")
 |
Los Angeles Metro Red Line
Location: Los Angeles, California
Owner: Los Angeles County Metropolitan Transportation
Authority
Role: PB was a member of the Metro Rail Transit
Consultants (MRTC) joint venture, which provided general engineering
consulting services for the development of the Red Line.
PM: Krishniah Murthy
Date: All segments scheduled for completion by
late 2001.
At the time of construction (1989) the slurry wall for the Metro
Rail Union Station was probably a record breaker for depth in difficult
ground—greater than 30 m (100 feet). The final wall contained
174 panels enclosing the 442-m- (1,450-foot-) long station. It was
designed to provide complete water cutoff. Construction sequence
called for skipping around so that nearby track yard activities
were not interrupted. Extra finishing on interior faces was required
for installation of an HDPE tunnel lining. (see "A
Case History: Using Slurry Walls to Control Groundwater") |