
Cairo Metro Construction |
Construction of Africa’s first metro is under way in the
shadows of the ancient pyramids of the Giza Plateau in Cairo.
This portion of the Greater Cairo Metro system, called Line 2/Phase
1, includes considerable underground work:
- 1.4 km (0.87 mile) of cut-and-cover tunnel
- 5.8 km (3.0 miles) of single bored tunnel with an excavated
diameter of 9.5 m (31.2 feet)
- 7 cut-and-cover stations.
Tunneling Made Difficult by Centuries
of Flooding
Cairo is at the apex of the Nile delta where, until completion of
the High Aswan Dam in the 1960s, seasonal flooding of the Nile created
thick alluvial flood deposits of clays and fine sands, materials
that are increasingly coarse and pervious with depth. Tunneling
in this area is particularly challenging because of the presence
of the upper alluvial clays and fine sands in combination with a
high groundwater level.
These conditions presented difficult construction conditions for
tunneling in general, but particularly for the two most sensitive
construction aspects of the project:
- Tunnel boring machine (TBM) station break-ins/outs
- Special hand-mined gallery connections between the bored tunnel
and tunnel annex structures (deep shafts located about midpoint
between stations along the bored tunnel route that provide for
tunnel ventilation, dewatering, and the system power supply).
Jet Grout Treatment Selected
The treatment zones at these critical locations extended through
both the upper clays and fine sands, and the lower more pervious
sand aquifer. Effective permeation of the finer soil types of the
upper alluvium is not normally possible with chemical or mineral
grouts. The design-construct contractor, therefore, envisioned the
ground treatment to be performed using the jet grout method only.
Jet grouting, applicable for all soil types, was expected to provide
both the required soil consolidation and ground water control to
safely complete these works (Figure 1). The required depth of the
treatment at these locations, however-30 m to 40 m (100 feet to
130 feet)—was considered to be near the limits of the current
jet grout technology, particularly when it is intended to be a watertight
treatment.

Figure 1: Early TBM Break-in/out and Tunnel Annex Connection |
Erosion Problems Surface
It became clear during the execution of the early break-ins/outs
that the jet grout treatment would provide the required soil consolidation,
but could not be relied upon for ground water control. Small discontinuities
of untreated soil were occasionally encountered between the jet
columns at depths of about 15 m or 20 m (50 feet to 65 feet).
The clean and uniform lower sand deposits have no natural cohesion
so they are particularly susceptible to erosion when subjected to
a hydraulic gradient. These discontinuities were exposed during
the demolition of the station end wall for the early TBM break-outs,
causing rapid and progressive failure by forcing soil and water
under pressure through the discontinuities and into the station.
This ultimately required the flooding of two stations for stabilization,
causing significant construction delays. Similar leakage through
the jet grout columns was observed during execution of the first
two tunnel annex connections, again causing construction delays.
As a result of the early problems at these areas, we had the contractor
review the ground treatment design for subsequent break-ins/outs
and annex connections.

Figure 2: Revised TBM Break-in/out and Tunnel Annex Connection |
Slurry Wall is the Solution
After some trial and error, the final solution adopted was an unreinforced
cement/bentonite slurry perimeter wall box with an impermeable chemical
grouted hard gel base plug beneath the jet grout treatment (Figure
2). Using the slurry wall as a supplemental ground water control
concept proved to be the solution to completing the construction
of these critical areas, despite the difficult ground conditions
within the Nile valley. In addition, it allowed for:
- Using an internal pumping test to confirm the watertightness
of the closed box before the demolition of the concrete diaphragm
wall began
- Lowering of the groundwater level inside the box, thus reducing
the water pressure and increasing the safety
factor.
It was clear that this more conservative design approach to the
ground treatment of these critical areas effectively reduced the
risk and minimized further construction delays. |