 |
Baltimore Metro’s Shot Tower Station was constructed under
a major roadway intersection near the heart of Baltimore. It supports
the triple-cell Jones Falls conduit, which carries a river that
was formerly a surface water feature, some large, storm drain conduits
and four 115 kV electrical lines on its roof structure (Figures
1 and 2).
Excavation for Shot Tower Station extended 21 meters (70 feet) underground.
The station is 186 m (610 feet) long, 20 m (65 feet) wide and 13.7
m (45 feet) high. The two tunnels that enter the station are 5.8
m (19 feet) in diameter, spaced 11.3 m (37 feet) apart horizontally
to provide a 8-meter- (26-foot-) wide column-free space for a center
platform.
Selecting a Construction Method
The Shot Tower Station site is characterized by a high groundwater
table and a limited excavation area. PB performed design services
as part of a joint venture, called DKP, with Daniel, Mann, Johnson
and Mendenhall (DMJM) and Kaiser Engineers. We investigated many
subway stations across the country with similar environmental and
soil conditions before deciding on the most suitable type of structure
and excavation support wall. The options we considered and our decisions
are as follows:
- Precast concrete panel slurry walls. This
excavation support wall type was rejected because of the difficulty
in transporting large panels and in making the joints between
the panels watertight.
- Cast-in-situ reinforced concrete slurry walls.
Although reasonably watertight, this method was rejected also
because it requires a larger than usual wall thickness, typically
1.2 m to 1.5 m (4 feet to 5 feet), to transmit high bending moments
and shear forces imposed by the soil and full hydrostatic pressures.
Also, moment connections using reinforcing bar bends, field bending
and field welding presented major structural problems.
- Cast-in-situ concrete walls with soldier piles. We
decided that the walls of the station would be constructed using
Soldier Pile Tremie Concrete (SPTC) with reinforcing between the
soldier piles. This type of wall is relatively watertight and
it provides significant strength in the vertical direction, greater
flexibility in moment connections and relatively easy connections
for temporary cross lot bracing.

Figure 1: Shot Tower Station Plan |

Figure 2: Shot Tower Station Profile |
SPTC Wall Construction
The soldier piles were designed for each construction stage as well
as for the final design condition. Pipe struts and wide-flange walers
were used to brace and frame each stage of the excavation. The pipe
struts were preloaded to about 35 percent of their anticipated load
to assure that each one would engage the bracing system.
Several of the pipe struts and walers were monitored during construction
with strain gauges to observe the stress levels.
In one instance, one of the monitored pipe struts near invert slab
level reached 150 percent of its design load. This problem was quickly
remedied by placing a second strut adjacent to the first strut to
relieve some of the stress.
The exact placement of a soldier pile is not yet a precise science,
especially when the pile has to go down about 21 m (70 feet). In
some instances, the soldier piles for the Shot Tower Station were
off from the theoretical location by as much as 0.3 m (1 foot).
The specified tolerance was 0.15 m (6 inches), but very little could
be done after the SPTC had been constructed except to accommodate
it by reworking structural and architectural details.
The SPTC wall was structurally connected to the base slab and used
as part of the final structure. The weight of the SPTC wall helped
resist high buoyancy forces at this site adjacent to the Baltimore
Harbor. The bulkheads and invert slabs at the ends of the station
had to be designed to accommodate the openings for the tunnels and
for any construction loads such as the bracing frame for the tunnel
shield and the waler and strut loads from the braced excavation.
Approximately 12 m (40 feet) of the main station was constructed
using a jet grouted cutoff wall in order to accommodate, but not
disturb, four existing 115 kV lines that would eventually rest on
the roof slab.
Supporting the Utilities
Some major utility structures had to span the width of the station
(between the clear distance of the SPTC walls) using the roof slab
for support:
- A 5.3-meter- (17.25-foot-) wide elliptical, double-box storm
drain
- The 20.7-meter- (68-foot-) wide triple-cell Jones Falls Conduit,
which provides drainage for areas within and north of Baltimore
- Existing conduits for four 115 kV power lines
- Existing and relocated 0.7-meter- (24-inch-) wide sanitary
lines
- A relocated 0.9-meter- (30-inch-) wide sanitary line.
Embedded steel plate girders in deep concrete beams had to be
designed for some of the larger utilities in order to minimize the
thickness and provide adequate clearance between the mezzanine and
the roof slabs.
Reconstruction of the triple-cell Jones Falls Conduit across the
top of Shot Tower Station required removing one cell at a time by
diverting the flow into the two other cells. The empty cell was
then removed so that SPTC wall panels on the north and south sides
of the station box could be constructed. The permanent station roof
was constructed and supported on the SPTC wall panels. The removed
cell was reconstructed upon completion of the station roof structure.
Staging the SPTC wall construction beneath the conduit required
careful coordination with the demolition and reconstruction work.
Brick and mastic waterproofing was used between the base of the
conduit cells and the station roof slab. High density polyethylene
(HDPE) membrane sheets were installed at the outside faces of conduit
and at the junction of the SPTC wall with the conduit cells. (See
also “Groundwater
Considerations for SPTC Walls at Shot Tower Station” by
Ray Castelli.)
Resolving Connection Problems
We used steel beams to support the mezzanine slab and steel plate
girders was to support the roof. The beams and girders sat on wide
flanged steel stubs that were welded to each soldier pile underneath
the mezzanine and roof levels. There was major concern about the
weld between the bracket and the soldier pile and how it would be
constructed and inspected. Welding experts were consulted about
the feasibility, constructibility and inspectibilty of the welds.
All welds were eventually tested and found to be acceptable.
Due to the location, slope and rotation of each soldier pile, each
mezzanine beam and roof girder would have a slightly different length
and, therefore, be custom made. A complex spreadsheet was developed
to calculate each mezzanine beam, roof girder length and associated
miscellaneous stationing, offsets, and eccentricities needed to
check shop drawings.
The brackets were welded perpendicular to the soldier pile flange
and beveled shim plates were used in the connection between the
beams and stub brackets. The brackets had to be designed not only
for the vertical dead and live loads, but also for any eccentricities
due to the location and orientation of the soldier piles.
Communication was Key to Success
As with any major engineering project, communication played an important
role in executing the design and
construction. On the Shot Tower Station project:
- Technical committees met on a regular basis to monitor and
advise on the progress of the design and construction.
- Quality assurance and value engineering evaluations were done
prior to every major submittal.
- Weekly construction progress meetings were held to resolve
any major issues that were encountered.
Overall, continuous contact was maintained with the client and
the contractors in order to discuss, accommodate and execute decisions |