|
Major construction has been under way for more than two years on
the downtown I-93 portion of Boston’s Central Artery/Tunnel
(CA/T) project. This section includes approximately 7 km (23,000
linear feet) of Soldier Pile Tremie Concrete (SPTC) slurry wall
with soldier piles used to reinforce the slurry walls spaced at
1.2 m to 1.8 m (4 feet to 6 feet). The slurry walls will form the
walls of the highway tunnels, which will be excavated beneath the
6-lane I-93 viaduct as it remains in use (Figure 1). The viaduct
will be underpinned by grade beams and needle beams supported by
the slurry walls.
About a third of the length of the slurry walls must be constructed
under low head room beneath the expressway viaduct. The vertical
constraint for low head room construction can be as tight as 1.2
m (4 feet) from the bottom of the I-93 viaduct to top of grade.
Walls as deep as 36.6 m (120 feet) must be built under this confined
space.
Work Zones Prepared

Figure 1: Plan (top) and Elevation (bottom) |

Figure 2: Elevation - Soldier Pile no Splice Zones (not
to scale) |

Figure 3: Method of Installation of the Soldier Piles in
the Middle SPTC Wall (not to scale) |

Figure 4: Stage 1 (top) and Stage 2 (bottom) |
Contractors prepare work zones by pre-excavating to a depth of
1.2 m to 1.8 m (4 feet to 6 feet) below grade to increase the vertical
working dimension. SPTC guide walls are then constructed at the
lower elevation. The depth of pre-excavation is limited for two
reasons:
- The site, adjacent to Boston Harbor, has a high water table-only
1.8 m to 2.4 m (6 feet to 8 feet) below grade.
- The guide walls must be constructed above the water table because
the slurry in the trench typically requires the hydrostatic head
above the in-situ water table to provide for a stable trench during
excavation.
Soldier Piles Spliced
Sections of the long steel soldier piles must be spliced in order
to be installed beneath the viaduct. Bolted connections were designed
instead of welded connections because there was concern that welded
splices could not be installed fast enough, considering the time
constraint of keeping the slurry trench open. Specifications typically
allow a maximum of 72 hours from completion of trench excavation
to completion of reinforcement and tremie concreting. The longer
the slurry trench remains open before tremie concreting, the greater
the risk of debris falling into the trench or the trench sides caving
in.
The splice design features full moment transfer using high strength
A490 bolts. Bolts were designed in bearing, double shear, and installed
to a “snug tight” condition. Soldier pile splices were
positioned vertically along the pile to avoid conflicts with later
structural connections to the tunnel roof and base slabs. The design
called for a “no splice zone,” where the contractor
was not permitted to detail splices. (Figure 2 on the following
page). The layout for this was carefully calculated and checked
during the design phase.
Two Splicing Methods Used Successfully
To date, the two contractors performing low head room construction
have used different methods to install the splices.
One Method. One contractor designed equipment to
lower two segments of soldier pile into position at a time (Figure
3). The segments are suspended from the guide walls, and their position
is determined by using a custom-designed frame. The splicing process
is as follows:
- Two segments are lowered into position beneath the I-93 Artery,
the A490 bolts are installed, then the vise clamps on the side
of the frame, which temporarily held the segments in position,
are released.
- At this point the soldier pile assemblage is supported by a
crane, which slowly lowers the piles into the slurry trench down
to the next splice point.
- The vise clamps are resecured, the crane hook is released,
and the next two segments are brought over for splicing.
The other method. The second contractor has also chosen to install
SPTC soldier pile segments two at a time. Instead of suspending
the installed segments from a crane and vises on the guide walls,
however, the contractor has erected a frame with two winches (Figure
4). Cables from the winches are attached to the bottoms of the soldier
pile segments. The winches are used to lower (and occasionally raise)
segments as the spliced soldier piles are installed.
Both Methods are Successful
The splicing operation has proceeded without difficulty using both
methods. The second contractor’s operation has the advantage
of requiring less equipment, and it appears to be more flexible.
On the other hand, in some cases the position of the winches and
frame have made it more difficult to clean the bottom of trench
prior to tremie concreting. |
PB, as part of the Bechtel/PB joint venture,
is serving as management consultant of the Massachusetts Highway
Department’s CA/T project. Other CA/T articles in this issue
are by Druss (p. 26), Das et al. (p. 28), and Brenner and Gelfer
(p. 34).
|