
Construction of NYC's 63rd St. Subway Line |

Figure 1: Project Alignment and Contract Boundaries |
The second segment of New York City’s 63rd Street Subway
Line will provide a two-track connection between the Line’s
current terminus in Queens and the existing local and express tracks
of the Queens Boulevard Line. The connecting track sections will
cross under the existing Queens Boulevard Line tracks prior to merging
with them. Excavation will be done by tunneling so that service
on the Queens Boulevard line will be maintained during construction.
The project alignment and boundaries of the project’s three
construction contracts are illustrated on Figure 1.
The high groundwater table at the site makes dewatering necessary,
but conventional dewatering could not be used because of the potential
impact of drawdowns on nearby chemical contaminant plumes and consolidation
of peat deposits below nearby structures. Instead of conventional
dewatering, slurry cutoff walls will be used to provide a relatively
watertight enclosure that will limit groundwater drawdowns outside
of the wall. Necessary dewatering will take place inside the cutoff
walls.
More than 914 m (3,000 feet) of slurry walls are proposed for the
two most northern contracts (Contracts 2 and 3) and nearly 230 m
(750 feet) of jet grouted walls where access problems prevent the
slurry wall construction technique from being used.
Project Geology and Hydrogeologic Conditions
Bedrock consists mainly of slightly weathered, medium to very strong,
closely to widely fractured gneisses and schists with pegmatite
sills and dikes scattered throughout the mass. Zones of lesser quality
rock occur occasionally due to variations in weathering, fracturing
patterns, rock composition, and structural features such as foliation
and shear zones.
The bedrock is overlain by mixed glacial deposits, glacial till,
outwash and other reworked till deposits. Stratification is complex,
and significant variations in the thickness and location of the
different types of deposits are common. The glacial deposits are
overlain by a layer of miscellaneous fill material. There are also
local deposits of peat and organic silt that were formed by post-glacial
streams and creeks in marshy areas.
Groundwater flows south to southeast, with moderate gradients that
range from 4.6 m to 12.2 m per kilometer (15 feet to 40 feet per
mile). The outwash soils are estimated to have medium permeability
(5x10-2 cm/sec) due to their poor grading and low void ratio. The
majority of the soils classified as SM or GM within the glacial
till deposits are estimated to have a low to very low permeability
(5x10-4 to 5x10-7 cm/sec.) Rock mass permeability varies considerably
(<10-7 cm/sec to 10-3 cm/sec) depending on joint spacing, orientation
and degree of infilling.
Additional hydrogeologic characterization of the site, which was
obtained from two pump tests and a jet grouting test shaft, is as
follows:
- The soil profile does not act as a uniform aquifer and drawdown
is dependent on the vertical flow component.
- The zone of influence of drawdown is limited and less than
152 m (500 feet).
- The shallow groundwater table is perched on the glacial till,
suggesting that the till is semi-pervious, thereby allowing some
limited vertical leakage.
Keying the Wall to Control Drawdown
Because of the ground conditions, the cutoff walls will minimize
but not completely eliminate groundwater drawdowns. Slurry wall
toe elevations were optimized to provide an effective cutoff for
sufficient drawdown control while minimizing the amount of difficult
excavation. Keying the toes of the wall sections into low permeability
soils at higher elevations rather than into rock at depth was desirable
from a cost and constructibility point of view, provided that the
objective of limiting drawdown was met. Toeing the walls into these
soils, however, was contingent upon the soils having sufficient
thickness and continuity, and a significant percentage of fines.
We found the conditions varied between the southern two-thirds of
the connecting track segment and the northern third.
Southern portion. The internal dewatering requirements
were the most demanding in this area. Wall toe sections were designed
to be keyed into bedrock because sufficient drawdown control would
not be provided if the walls were keyed into the less permeable
soils. Some of the rock in this area has appreciable fracture permeability,
however, so drawdowns outside the cutoff walls would be excessive
and some type of additional cutoff treatment was therefore necessary.
Examination of the rock core and other related data indicated that
it would not always be possible or practical to continue the wall
through the permeable rock layers to the impermeable rock layers.
Instead, some sections will require toes that terminate above the
permeable rock layers. This condition required cutoff treatment
in the rock by a grout curtain, similar to that used by dams founded
on rock. Our assessment of the rock cores and field geohydrological
tests indicated that the upper 4.6 m (15 feet) of rock will require
grouting.
We established the following criteria for the construction contractor
to follow in order to evaluate the cutoff wall
toe elevations in rock during construction and make any necessary
adjustments:
- Drill exploration holes beneath every panel, with a maximum
exploration hole spacing of 3.0 m (10 feet).
- Conduct packer pressure tests in every exploration hole (because
the quality and permeability of the rock is not consistent). When
the packer test permeability exceeds the allowable limit, the
rock is pressure grouted.
Northern portion. Here, the glacial till stratum
thickens considerably. There are a number of boulders, the rock
becomes deeper and the excavation dewatering requirements are less
demanding. Keying the walls into rock in this area would:
- Extend the time required for excavation
- Impact the overall construction schedule
- Prolong traffic control requirements
- Increase the risk of problems with the wall construction
- Provide diminishing returns at significantly greater costs.
The upper layers of the glacial till are known to contain lenses
of clean permeable sands. The wall toes were extended below these
lenses. All wall toe elevations are being adjusted in the field,
however, based on soil characteristics immediately below the planned
wall toe elevations. Soil drilling, sampling and laboratory testing
are specified below every panel. When the soil immediately below
a panel is “clean” or has a low percentage of fines
based on grain size distribution, the wall toe is being extended
deeper.
Drawdown Outside the Slurry Walls
The cutoff walls were expected to result in small drawdowns outside
the walls due to underseepage since the walls could not be toed
into an ideal, continuous impermeable material. PB began the cutoff
wall design, with respect to groundwater control, by establishing
the pattern and magnitude of drawdowns based on estimates from case
histories, analytical studies and observations made during the pump
tests and the jet ground test shaft.
Settlement by the estimated drawdowns and their patterns could be
computed at different locations from the cutoff walls. For areas
near contamination plumes, we also evaluated contaminant transport
and dispersion from induced changes in groundwater flow directions
and gradients. Based on a combined assessment of the potential settlement
and contaminant transport, we computed maximum allowable drawdowns
at various locations around the site, then established the required
cutoff wall thickness, permeability and toe depth.
We used 2-dimensional finite element analyses of flow in vertical
cross-sections using the dual formulation for hydraulic potential
and stream function for the analytic studies. Fixed groundwater
heads on either side of the cutoff wall were applied at appropriate
locations, soil and rock permeability assigned and the resulting
drawdowns computed. The wall geometry was altered until the computed
drawdowns approximated the target maximum allowable. These analyses
included the effects of rock mass permeability and the grout curtain
below the wall toe.
The construction contractor is required to maintain groundwater
elevations outside the walls. Compliance is checked using strategically
placed piezometers outside the walls with specified limits on drawdowns
at each monitoring location. The allowable drawdowns are small,
generally 0.6 m (2 feet) maximum.
Internal dewatering is essential for constructibility of the required
excavations, and maintaining groundwater levels outside the cutoff
walls is extremely important. Therefore, the contractor is required
to conduct deep well pump testing inside the enclosed walls at critical
areas before excavating and to demonstrate that internal piezometric
levels can be achieved and that they do not induce excessive drawdowns
or wall leakage. The contractor is also required to remediate the
cutoff walls when the observed external drawdowns exceed the allowable
limits.
Construction is Under Way
All three construction contracts are underway with cutoff wall construction.
The most difficult problem is, as predicted, excavating the walls
through or into glacial till, a dense sand with boulders. Rock coring
beneath every panel has confirmed the expected variations in rock
quality and permeability. Production grouting of the rock beneath
the wall toes is commencing in sections where the walls terminate
at a rock surface. |