| The City of Santa Cruz, California owns and operates a Class
III landfill that was constructed in canyons close to the Pacific
Ocean. For several years, the landfill acted as a barrier to fresh
storm water drainage in these canyons. Surface runoff ended up flowing
into the landfill and becoming polluted by landfill contaminants.
The State of California Regional Water Quality Control Board imposed
a Cease and Desist Order on the landfill until the city constructed
a system to intercept fresh water flow above the landfill, conduct
it around the landfill and discharge it downstream of the landfill
back into the creek bed that the landfill occupies.
The solution that PB provided for the city included:
- Two 0.7-m to 0.9-m (26-inch to 36-inch) -diameter microtunnels
to convey the fresh water around the
landfill
- Soil-cement-bentonite slurry cutoff walls to prevent subsurface
migration of fresh water into the landfill.
Project History
Preliminary studies for a tunnel solution were first prepared by
others in 1988. Geologic conditions along two tunnel alignments
were evaluated and geotechnical considerations for tunnel construction,
potential geologic hazards and tunnel design characteristics were
addressed. At that time, two 305-m- (1,000-foot-) long, 2.1-m- (7-foot-)
wide, horseshoe-shaped bypass tunnels were recommended to be excavated
using drill-and-blast methods through ridges upstream and west of
the landfill.
A 1990 environmental impact report (EIR) addressed the environmental
aspects of two possible solutions for a freshwater bypass:
- A system of bypass tunnels as proposed in 1988
- A permanent pipeline and pumping system along the east and
west canyon ridges.
After approval of the EIR, prepared by others, PB made further
studies to review available data, prepare hydrologic and hydraulic
calculations, evaluate fresh water bypass alternatives using pipelines
and tunnels, and recommend a preferred alternative for further study—two
small-diameter bored tunnels (microtunnels) constructed within landfill
property. These microtunnels would provide the benefits of the larger
tunnels proposed in 1988, but with fewer of the environmental and
permitting consequences associated with constructing tunnels on
state park land next to the landfill.

Figure 1: Geologic Cross Section of the Slurry Cut-off Walls |

Figure 2: Soil Fines Content Effect On Slurry Wall Permeability |

Figure 3: Schematic Section of Slurry Cutoff Wall Construction |

Figure 4:Constricted Construction Site |
Several Issues to Consider
Once the option of a tunnel from the east canyon to the west canyon
and a second tunnel from the west canyon to a creek under the middle
of the landfill was selected, the task was how to install tunnels
under the landfill cost-effectively and prevent flow of fresh storm
water into the landfill. The issues considered when designing the
tunnels included:
- Locating where the rock-landfill interfaces occurred
- Evaluating how to mine through the landfill materials, if encountered
- Determining how to handle contaminated groundwater from the
landfill, if encountered,
- Evaluating whether there would be methane gas present and at
what concentrations.
In addition to the tunnel studies, PB’s design considered
ways to prevent subsurface groundwater flow from entering into the
landfill and direct it into the freshwater bypass tunnel system.
The geotechnical exploration program undertaken to resolve these
issues included geologic mapping, soil borings through refuse, rock
core borings, laboratory testing, and geophysical testing. Because
the site was contaminated, personnel had to be trained in health
and safety and all of the requirements for a contaminated site had
to be followed, including physical examinations of all personnel,
appropriate health and safety equipment, training, and monitoring.
PB developed contract documents for the exploration and actual execution
of the work including operation of monitoring equipment and groundwater
sampling. Figure 1 on the following page indicates the in situ character
and extent of subsurface conditions at the slurry wall locations.
Slurry Wall Cutoff Design and Construction
Several alternatives were evaluated for cutting off subsurface groundwater
flow through the valley alluvium overlying bedrock upstream of the
tunnels. Steel sheet pile cutoffs, concrete wall cutoffs, clay blankets,
and soil-cement-bentonite slurry walls were considered. After an
exhaustive alternatives analysis, a slurry wall cutoff solution
was selected based on cost. On August 21, 1995, construction of
the tunnels and walls began.
The project design included the requirement for a mixture of soil,
cement, and bentonite in accordance with the contractor’s
approved mix design. The specified requirements for the slurry cutoff
walls included criteria for strength and permeability as indicated
in Table 1. These criteria were based on published literature and
case histories.
The contractor who constructed the slurry cutoff walls first drilled
additional borings at the wall sites to obtain soil samples that
would be incorporated into the mix design trials. Fines content
of the soils has a dominant effect on the in situ permeability of
the cutoff walls as indicated in Figure 2. The cement content has
a dominant effect on the in situ strength of the cutoff walls.
The method of construction of soil-cement-bentonite cutoff walls
(Figure 3) consists of:
- Excavating a trench with addition of bentonite-water slurry
to maintain stability of the trench
- Keying the trench into bedrock
- Backfilling the trench with soil-cement-bentonite slurry mixed
on-site, which displaces the bentonite-water slurry
- Capping the slurry cutoff wall.
The trenches were excavated in stages because the valley walls
constricted the site (Figure 4). The backhoe straddled each wall
and excavated one half at a time. Once one half of the wall was
completed, the backhoe would turn around and construct the other
half.
Table 1: Criteria for Strength and Permeability
 |
As indicated in Table 1, the mix designs were achieved in the field
and they met the specified criteria. It should be noted that quality
control in the field required intense scrutiny of field operations
and follow-through on laboratory testing of field samples.
Conclusions
Valley landfills are common on the West Coast. Changing regulations
have had a drastic impact on how landfill operators deal with storm
water in and around their facilities. In the case of the Santa Cruz
Landfill, where a pump and pipeline system was installed as a temporary
solution, the City determined that drainage tunnels would be more
cost effective over the life of the facility (100 years) because
of the high operations and maintenance costs of the pumps. Subsurface
cutoff of groundwater flow with soil-cement-bentonite slurry walls
was an important feature of this project.
This project used the best of PB’s full-service resources.
Some of our environmental specialists provided unique services related
to landfill contamination and our water resource specialists provided
instrumental guidance during design. These specialists were in addition
to other PB professionals who provided their construction and civil
engineering expertise. With four PB entities involved, we can say
that we had a PB “Grand Slam” on this small, but very
important project along the coast of northern California.
|