
JFK International Airport |
The Port Authority of New York and New Jersey has planned an automated
light rail transit (LRT) service to link John F. Kennedy (JFK) International
and La Guardia Airports with each other and the New York City Transit
subway to midtown Manhattan. At JFK, the project would include a
cut-and-cover tunnel and a pump station. Construction excavation
would be as much as 10 m (35 feet) below the groundwater table.
Tunnel Construction
The cut-and-cover tunnel and associated retained earth sections,
totaling about 610 m (2,000 feet), would include both a twin LRT
alignment and a barrier-separated, restricted service road that
breaks away from the LRT at approximately the tunnel’s midpoint.
The tunnel would pass underneath two taxiways at a maximum depth
of about 10 m (35 feet). The retained earth sections would connect
to at-grade sections running to the Central Terminal Area and along
the Van Wyck Expressway (VWE).
Tunnel construction can proceed by either the bottom-up or top-down
method. Both types have advantages and disadvantages, but a critical
restriction on both for this project is construction duration. Only
one taxiway can be taken out of service at a time, and only in a
narrow time slot at a given time of the off-season travel period.
- Bottom up. Either a permanent slurry wall
or a temporary soil-cement mix wall with a separate reinforced
concrete box is permitted. The latter has scheduling advantages
over the former.
- Top down: Construction would proceed with
a slurry wall as both temporary and permanent support walls.
This article focuses on the geotechnical design considerations
of the project, if it were to be built.
Geotechnical and Site Considerations
The relevant geotechnical conditions in sequence below the ground
surface are as follows:
- Loose to medium dense hydraulic fill with thickness varying
between 3 m to 6 m (10 feet to 20 feet)
- An extensive but not continuous layer of soft to firm, slightly
over consolidated, clay/peat deposit from 0.6 m to 3 m (2 feet
to 10 feet) thick
- A medium-dense to dense glacial sand layer with thickness varying
between 21 m to 30 m (70 feet to 100 feet)
- An impervious silty clay stratum at about a 38-m (125-foot)
depth.
Where present, the low-permeability clay/peat layer creates a perched
water table in the fill. The clay/peat layer is absent in scattered
areas inside and outside the tunnel perimeter, thus permitting hydraulic
connection between the perched water table and the glacial aquifer.
The perched water table in the fill is generally 1.5 m to 2.4 m
(5 feet to 8 feet) below the existing grade. The potentiometric
head in the glacial aquifer is about 0.3 m to 1.2 m (1 foot to 4
feet) lower.
The permeabilities of the fill, clay/peat and glacial sand were
estimated to be about 1x10-2, 1x10-5, and 5x10-2 cm/sec, respectively.
The fill and glacial sand are relatively homogeneous and isotropic,
while the clay/peat vertical permeability was estimated to be about
one to two orders of magnitude smaller than its horizontal permeability.
The site is constrained by many utilities and is within 30 m (100
feet) of the VWE, which passes underneath the taxiways. Three large
groundwater contamination plumes known to be adjacent to the site
consist mostly of hydrocarbons (including gasoline and jet fuel)
and glycol.
Geotechnical Design Considerations
Regardless of whether the construction proceeds as top-down or bottom-up,
construction using a conventional external dewatering system was
eliminated and the need to control groundwater drawdowns to a range
of a few feet was instituted. Cutoff walls, either as slurry walls
or soil-cement mix walls are required. Any cutoff wall would need
to extend relatively deep, in the range of 38 m to 41 m (125 feet
to 135 feet), to reach an impermeable stratum and therefore be effective.
We determined that it would be more cost effective and faster to
minimize the wall depth by using a horizontal
cutoff spanning between support walls. A horizontal cutoff would
be located below the excavation invert and would consist of either
soil-cement mixing, jet grouting or chemical grouting. Thickness
of this cutoff varies from about 1.5 m to 3.7 m (5 feet to 12 feet)
depending on excavation invert depth. Despite having both vertical
and horizontal cutoffs, some drawdown is still expected due to a
small but measurable permeability of the cutoffs.
Groundwater Flow Analyses
Groundwater analyses indicated that the most important factor for
drawdown control is the permeability and thickness of the horizontal
cutoff. Various thicknesses and material characteristics of the
horizontal cutoffs were assessed for drawdowns by using two-dimensional
groundwater flow analyses in vertical cross sections based on the
finite element method. The thicknesses were later verified by three-dimensional
finite difference based groundwater flow analyses (Figure 1). Case
histories of similar applications were also reviewed for drawdown
performance and plausibility of our approach.

Figure 1: Cross-sections through fill and peat/clay layers
in N-S direction (left) and E-W direction (right). Shown also
is a trace of water table in fill along model boundaries (right).
|

Figure 2: Contours of drawdown in feet in upper glacial
aquifer in the vicinity of cut & cover tunnel. |

Figure 3: Capture zone for construction period (15-month).
|
Both vertical and areal distributions of groundwater drawdowns
are very important. We had to look at settlements in specific areas
as a result of groundwater drawdowns in compressible soils. Also,
the nearby contamination plumes needed to be assessed as to whether
construction would influence contamination movement and dispersion.
Furthermore, during construction, drawdowns would be controlled
by an observation program that includes a network of multilevel
piezometers.
Maximum allowable drawdowns are assigned to each piezometer of the
network and enforced by the specifications. A three-dimensional
groundwater model was developed for the project site to simulate
general groundwater flow, to
estimate distributions of drawdowns, and to examine contaminant
transport. The U.S. Geological Survey’s Groundwater Simulation
Model, MODFLOW, was used to simulate groundwater flow in three dimensions
in steady-state modes.
The MODFLOW model was calibrated for an average annual distribution
of hydraulic head in the fill layer with a uniform areal recharge
of 0.15 m (6 inches) per year. The vertical cutoff wall and the
horizontal invert cutoff were both modeled as horizontal and vertical
flow barriers, respectively, with specified thicknesses and permeability.
Figure 2 shows the distribution of drawdowns in the glacial aquifer
with the cutoffs in-place and the excavation advanced to maximum
limits both areally and vertically for the entire length of the
tunnel. The drawdowns predicted by both the two-dimensional and
three-dimensional analyses were within 20 percent of each other,
considered good agreement.
Transport Analyses
PATH3D, a MODFLOW companion model, was used to find contaminant
migration pathways and related travel times, and to evaluate the
capture zones for the excavation. The travel times estimated for
contaminants are generally much longer than the estimated construction
period (15 months) for all contamination locations, except the contamination
near Terminal 3. The perimeter of the capture zone for the construction
period includes or passes near the contamination centers near Terminal
3 (Figure 3 on page 22), indicating that the contaminant could enter
into the excavation during construction.
Also important is that this contamination plume would be moved offsite,
making future cleanup more difficult. Hence, by utilizing our 3-dimensional
groundwater model, we looked at a series of options for maintaining
the plume in place. Our model indicated that a low volume ground-water
recharge system is a practical solution. Our client also requested
that we have a system that will not create drawdowns near another
nearby contamination site, which is undergoing limited cleanup operations.
An observational approach to managing the drawdowns and adjacent
contamination plumes is contained in the project specifications.
Each of the multilevel piezometers in the monitoring network has
specific drawdown limitations. The contractor will be required to
develop a recharge system to prevent drawdown in the areas closest
to the contamination plumes.
Conclusion
The interaction of cutoff walls with the soil and groundwater conditions
can be difficult to determine. The groundwater models we used for
this complex site provided a valuable insight into the interaction
in addition to serving as a decision and design tool aid. |