
Ted Williams Tunnel |
Approximately 7 kilometers (4.3 miles) of Central Artery/ Tunnel
(CA/T) slurry walls will ultimately become the permanent walls of
the tunnel structure. In the majority of the alignment, vertical
loading as opposed to lateral stability governs wall depths. Costly
excavation of rock will be necessary to reach the required depths,
which commonly exceed 36.6 m (120 feet).
The selection of appropriate values for end bearing and side resistance
is critical to keeping project costs within budget, given the considerable
volume of wall construction, because these values dictate the depths
to which the walls must be embedded into bedrock. The Massachusetts
Highway Department authorized the B/PB team to determine these values
ultimately (as opposed to the Area Geotechnical Consultant or Section
Design Consultant) because similar slurry construction is common
to multiple design sections and B/PB is responsible for maintaining
design consistency.
We found that developing these design parameters highlighted several
challenges that are frequently encountered in geotechnical engineering:
- Establishing design parameters in highly variable ground conditions
- Contending with dissimilar classifications (by different consultants)
of the same core samples
- Assessing the risk of various “failure mechanisms”
of a given structure to establish a corresponding level of conservatism
in the selection of geotechnical design values
- Maintaining a design that falls within budgetary constraints.
Earlier Design Recommendations
Several years before the detailed design of the slurry walls was
underway, the Area Geotechnical Consultant (AGC) for the CA/T Central
Area—the region where slurry walls must resist vertical loads—developed
the recommended parameters for design of the slurry walls. The recommendations
included values for allowable end bearing and side resistance for
glacial soils and various classifications of bedrock. Of the two
sets of design values for allowable
end bearing-settlement controlled and strength controlled-settlement
controlled values were recommended.
Settlement Controlled Values. The settlement controlled
values were derived from an assumed tolerable settlement
of the slurry walls of 25 mm (1 inch), which applies to the condition
where the slurry walls are acting as underpinning elements that
support the existing elevated highway structure. The tolerable total
and differential settlements that the elevated structure could withstand
were represented as typical values for building construction. Allowable
end bearing pressures of the B2 and B3 rock (severely to moderately
weathered Argillite and moderately to slightly weathered Argillite,
respectively) were back-calculated using elastic parameters and
an assumed 25.4 mm of compression of the rock mass. To derive the
corresponding value for B1 rock (completely to severely weathered
Argillite), the AGC assumed the rock had similar engineering properties
to those of a hard clay. A one-dimensional consolidation analysis
was performed, assuming a recompression ratio of 0.02 and 25.4 mm
of settlement to back calculate an end bearing pressure.
Strength Controlled Values. Strength controlled
values for allowable end bearing were derived typically from results
of unconfined compression tests of core samples. Allowable end bearing
pressures were calculated primarily by classical methods of determining
bearing capacity. The shear strength of the rock for these calculations
was assumed to be one-half the unconfined compressive strength.
The AGC’s recommended design values appeared reasonable at
the time they were made. As final design progressed, however, they
led to calculated wall embedments that seemed excessive.
CLTP Used to Verify Design Parameters
We took advantage of a caisson load test program (CLTP) that was
slated for another CA/T design area (with similar geologic features
to those of the Central Area) to verify the slurry wall design parameters.
The CLTP consisted of the installation of a series of drilled shafts
that were then tested with Osterberg load cells. A test boring performed
at each shaft location was logged by the SDC for the design section
targeted by the CLTP. Pressuremeter tests (PMT) were performed in
each boring. Shafts were socketed in zones representative of the
full range of weathering and quality of the Cambridge Argillite,
the bedrock formation that underlies the entire project alignment.
The PMT results were then compared to the boring logs.
The comparison of logs was the source of complications. As mentioned,
the AGC had used a modified rock description system and divided
the bedrock into the classifications of B1, B2, and B3., but the
SDC used the standard project-wide classification system and did
not subdivide the bedrock. To correlate the CLTP results to the
slurry walls, the boring logs needed to be “translated”
and the Central Area AGC was requested to log the CLTP borings.
In our comparison of the two sets of logs, inconsistencies in descriptions
of weathering, which resulted in shifts in the bedrock classifications,
were noted-not surprisingly. We knew we had to examine the core
samples and reconcile the differences in classifications.
Once the rock was classified on a consistent basis, CLTP results
were transferable to the Central Area. It was not
possible to correlate the PMT data to rock classification (and corresponding
design values), however. The PMT is sensitive to borehole conditions
and instrument placement and the data obtained exhibited wide variations
in similar strata.
Development of Project Design Parameters
The design parameters developed subsequently by B/PB apply only
to the Central Area slurry walls. Load transfer mechanisms in the
sockets of the slurry walls may vary from those of drilled piers
as a result of differing geometries, installation methods, and the
consequences of exceeding theoretical load carrying capacity, which
is discussed below in greater detail. Additionally, drilled pier
capacities need to be assessed more critically because structural
loads are resisted by discrete elements that often act essentially
independently. The slurry wall has the ability to transfer loads
longitudinally from zones of lower bearing capacity to zones of
greater vertical bearing capacity.
Modeling of Tunnel Behavior. A key step in determining
foundation design parameters for a given structure is to identify
the potential modes of failure. Once these are established, appropriate
parameters and design values
for soil and rock capacity can be specified. The following discussion
applies only to the case where the tunnel invert bears on the marine
clay stratum.
The maximum loading condition of the Soldier Pile Tremie Concrete
(SPTC) walls occurs when the tunnel structure is completed and backfilled.
At this stage the SPTC walls are integrated with the tunnel structure
through continuous structural connections to both the invert and
roof slabs. In such a configuration, deflection of the wall becomes
a function of the stiffness of the combined wall/roof/invert section.
The resultant flexural stiffness in the longitudinal direction will
enable the structure to safely span considerable distances. Detrimental
settlement of the tunnel structure should not be anticipated unless
rock quality is considerably more adverse than assumed in design,
on a continuous basis, for a longitudinal distance of 30 m (100
feet) or more. The probability of all variations in rock properties
and stratification between existing borings becoming significantly
worse than presently shown on the subsurface profiles is remote.
A closer look at the mode of “failure” or deformation
of the tunnel provides further evidence of the unlikelihood of detrimental
settlement. If the actual bearing capacity of the bearing stratum
of the slurry wall is exceeded along the length of the wall, the
walls will begin to settle. As the walls move downward, the invert
will be drawn down as well, and contact pressures between the invert
slab and subgrade will increase, resulting in a simultaneous decrease
in wall loads. The
proportion of load that is transferred to the invert is a function
of subgrade modulus. Additionally, if the slurry wall settles, side
resistance along the entire height of the wall is mobilized. The
side resistance of only the strata located below tunnel invert are
taken into account in calculating wall depths.
In terms of the present structural model, as the bearing capacity
is approached and exceeded, the stiffness of the wall support will
considerably decrease. considerably. The vertical pressure thus
becomes more uniformly distributed among the wall and invert. Note
that a “stable” design can be achieved if the tunnel
bears entirely on the clay. However, because the slurry walls are
installed to act as underpinning elements and because it was elected
to implement an integrated design, the walls bear in the rock and
thus attract loads in the completed tunnel configuration.
Regardless, the fact remains that the SPTC walls will attract much
higher vertical pressures in service conditions as a result of the
variation of stiffness between the rock and marine clay. The SPTC
walls need to extend to appropriate depths in the rock to resist
these loads. Thus, allowable bearing pressures should be based on
strength, or bearing capacity, as opposed to control of deformations.
Basis for selection of design values. Design values
for slurry walls in the Central Area (Table 1 on page 45) were derived
from results of the CLTP, analysis of data obtained by the AGC,
and data and design parameters associated with other projects in
the Boston area. The CLTP results could not be used as the sole
source of design values because the entire range of rock properties
identified in the Central Area were not tested. Additionally, three
of the CLTP borings were located at a distance greater than 20 feet
from the test location, and thus the stratification in the core
samples may not correspond to those of the test sockets.
The revised values, particularly those associated with end bearing,
exceed those recommended several years earlier.
As stated, the original recommendations represent settlement controlled
values relating to underpinning of the existing highway structure.
Underpinning does not govern wall design, however, because the most
extreme loading occurs in the completed tunnel condition when settlement
becomes a secondary design consideration and, therefore, strength
controlled values were used in determining the revised values.
The CLTP results indicate that allowable end bearing values greater
than those shown above could have been selected, particularly in
the cases of B2 and B3 rock. The selection of lesser values was
deemed prudent, however, because the stratification along the slurry
walls will not be verified on a continuous basis.
Design values for the till were derived from CLTP results, the geotechnical
reports, and previous projects. There exists considerable design
and performance experience in the till in the Boston area. To develop
values for the B1 rock, its measured engineering properties were
compared to those of the till. It was concluded that the slurry
wall design values for the till and B1 rock should be similar. Note
that these values are typical of those used in foundation design
for similar rock quality in the Boston area. Values for B2 and B3
rock were derived primarily from CLTP results.
Conclusion
Implementation of the revised design values resulted in decreases
in the quantity of costly slurry wall excavation in rock. The action
taken by B/PB represented one example of the fulfillment of our
obligation to control project costs while maintaining quality in
the constructed product. |