
Construction Site for the Central Artery/Tunnel |
The I-93 portion of the Central Artery/Tunnel project includes
approximately 7 km (23,000 linear feet) of slurry walls (Figure
1), most of which will be Soldier Pile Tremie Concrete (SPTC) walls.
Steel wide-flange soldier piles, forming the primary support system
for the wall, are installed at 1.2 m to 1.8 m (4 feet to 6 feet)
spacings. In most locations, the concrete is designed to act as
lagging spanning between the structural steel members. The concrete
base slab is rigidly connected to the SPTC walls and the composite
roof is pin connected to the walls to form the tunnel.
Groundwater Conditions
The groundwater level along the Central Artery is typically 2.4
to 3.1 meters (8 to 10 feet) below ground surface. Temporary or
permanent lowering or raising of the groundwater table has been
shown to affect buildings, streets and underground utilities adversely.
Potential problems include deterioration of wood piles, ground subsidence
and negative friction on piles.
To prevent the groundwater levels from fluctuating outside allowable
ranges, a low permeability retaining wall system such as slurry
walls is required for lateral support of the excavation. The walls
are designed to extend into bedrock to reduce lateral movements
during excavation and groundwater inflow, and to support vertical
bearing loads. (See also “Slurry
Wall Design Parameters” by Dave Druss.)

Figure 1: Location of tunnels using slurry walls |

Figure 2: Typical subsurface soil and rock profile |
Key Design Considerations
Several requirements that impacted the design of SPTC walls for
the I-93 cut-and-cover tunnels fell into two categories-geotechnical
and other.
Geotechnical. The geotechnical considerations (Figure
2) were that:
- Permeability in the glacial till and bedrock is relatively
high compared to the clay and glaciomarine soils.
- Depressurization in the glacial till and bedrock outside the
excavation had to be controlled to limit consolidation of the
compressible clay on which numerous structures are supported.
- The bedrock profile and quality rock are erratic, and localized
areas of high groundwater infiltration could be expected.
- Cobbles and boulders encountered in the glacial till could
impact the installation of earth support systems.
Other. The following right-of-way, construction
and alignment concerns had to be considered:
- Many existing buildings abut the tunnel alignment. These include
sensitive older structures, many of historic value, and also large,
40-story skyscrapers.
- The presence of existing buildings leads to a tight lateral
clearance in which to fit the tunnel. The design required stiff
walls that needed to fit in a narrow corridor.
- Underpinning of the existing Central Artery viaduct during
the construction of new cut-and-cover tunnel required an excavation
support wall system that would bear large vertical loads.
Having taken these key design constraints into consideration together
with the cost, schedule, constructibility and environmental impact,
we concluded that the optimal tunnel wall system for the Central
Artery alignment was SPTC walls that would be included as part of
the final tunnel structure. SPTC walls were chosen instead of conventional
reinforced concrete slurry walls because SPTC walls are stiffer,
more suitable for low headroom construction beneath the existing
artery viaduct, and stronger in bending than a concrete wall of
the same thickness.
For the CA/T downtown alignment, cross-lot bracing was designed
to support the excavation. Tiebacks were not considered for the
lateral support system due to right-of-way constraints and concerns
that the tieback penetrations might result in leakage in the permanent
tunnel wall.
Method of Analysis
It was necessary to consider the construction staging load along
with the permanent load condition for the stress and deformation
analysis because the SPTC walls are used both as part of support
of excavation and as permanent final structure. Construction stages
include sequential excavation and strutting with cross lot braces,
installation of base slab, sequential removal of struts, installation
of roof, and backfilling.
An interesting aspect of the SPTC wall design is that the maximum
lateral deformation occurs at a stage when the total lateral load
is relatively small compared with its maximum magnitude. This is
true because the excavation induced lateral movement will reduce
the lateral soil pressure from in-situ at rest value to some magnitude
equal to or greater than the active soil pressure, depending on
deflection of wall. In the final condition, the soil pressure will
increase over time to at-rest pressure. This requires the structural
design of the SPTC wall to first consider deformation control at
the construction stage when the load is relatively small, and then
the strength of the wall for the final permanent condition. For
this purpose, the CA/T project adopted a design approach to use
an allowable stress design method together with additional stringent
deformation control requirements for design of the SPTC wall during
temporary construction stage, and the load factor resistance design
method for its final permanent condition.
Structural Modeling of SPTC Wall
The structural model of the SPTC wall during the construction phase
is a nonlinear and stress-history-dependent soil structural interaction
analysis. Prior to tunnel excavation, the SPTC wall is in a state
of equilibrium with the surrounding soil. The first stage excavation
on one side of the SPTC wall creates different ground elevations
on two sides of the wall and mobilizes soil pressure on the retained
side to push laterally against the wall. The soil below the bottom
of excavation acts as support to maintain the stability of the wall.
A strut is placed at elevation about 0.6 meter (2 feet) above the
bottom of excavation and braced against SPTC walls on both sides
of excavation. In order to minimize the ground movement, the strut
is pre-compressed between the two SPTC walls. The strut acts as
a prestressed spring support to the wall with spring constant equal
to the axial stiffness of the strut. Preloading of the strut pushes
the SPTC wall against the retained soil and generates additional
soil reaction on the wall.
For each subsequent excavation stage, the excavation support structure
experiences following changes sequentially:
- Excavation removes the support of subgrade soil to the SPTC
wall and lowers the wall’s soil support down to the bottom
of the excavation stage.
- Excavation releases the subgrade soil reaction of the previous
stage and causes stress redistribution between the SPTC wall and
soil below the bottom of the excavation.
- Excavation results in additional lateral soil pressure on the
SPTC wall.
- Installation of a support strut adds a support, which is modeled
as a linear spring in the analysis.
- Precompression of the strut may generate additional soil reactions
on the SPTC wall by pushing the wall back into the soil.
The final stresses in the SPTC wall are accumulated in increments
from one excavation stage to the next. As excavation proceeds, the
load on the SPTC wall increases while the structural configuration
of the wall/support system as well as its boundary conditions change.
The final stresses in the wall are not linearly related to the displacements
of the structure, preventing use of the principle of superposition
and requiring an incremental nonlinear analysis.
Our structural model assumes for each excavation stage that all
loads mobilized by excavation will be applied to the SPTC wall at
once. The excavation and installation of struts to support the SPTC
wall is a staged process, so lateral wall movement occurs prior
to the installation of strut. To model this staged deformation mechanism,
the deflection of the SPTC wall at strut level prior to its installation
is accounted by introducing a fictitious concentrated load at end
of strut to short the strut by same amount. The effects of construction
staging are cumulative. As excavation proceeds, the wall tends to
move inward. Moments are generated in the wall, which become “locked
in” to the structure in the permanent condition.
The wall bending stresses and strut reactions from the incremental
analysis are examined at each phase of the excavation to check the
capacity of the soldier pile and struts under construction conditions
using allowable stress design method. In addition, the final “locked-in”
bending stresses are applied with appropriate design factors and
combined with results from a final net tunnel model using the additional
long-term loadings not included in the incremental analysis. These
results are then compared to a final tunnel model using all the
loading cases to obtain the maximum design stresses along the wall.

Figure 3: Invert slab to SPTC wall connection |
The thickness of the SPTC slurry wall varies between three to four
feet thick. The soldier piles are spaced between 1.2 to 1.8 meters
(4 to 6 feet). The structural steel soldier piles are designed as
primary load carrying members and the concrete between the soldier
piles is considered as lagging between the piles. The flexural stress
in the concrete is very small, so no steel bar reinforcement is
needed. In some locations where the surcharge loading from adjacent
building foundations is high, however, reinforcement needed to be
provided. In most cases, W36 x 393 wide flange sections with 3.45
x 105 kPa (50 ksi) yield strength are used as soldier piles. The
minimum 28 days strength of the tremie concrete is 2.76 x 104 kPa
(4000 psi) with a slump between 180 to 255 mm (7 to 10 inches).
The concrete base slab, with thickness that varies between 2.4 to
4.5 meters (8 to 15 feet), is rigidly connected with the steel soldier
piles as shown in Figure 3. The roof structures are simply supported
by the soldier piles. The roof structures are composite structural
steel plate girders with a concrete roof top slab. Waterproofing
material is provided under the base slab and on the top of the roof
slab.
Conclusion
The downtown Central Artery tunnels used SPTC slurry walls that
were designed to serve as support of excavation, water cutoffs,
underpinning support for the existing artery viaduct, part of the
final tunnel structure and to handle a variety of challenging soil
and construction conditions. |