| The answer to whether or not slurry walls should be designed
as part of the final structure seems obvious at first. If you are
building slurry walls for an excavation then, clearly, they should
be used as part of the tunnel or underground building structure.
After all, such a design avoids the need for additional, cast-in-place
walls inside the slurry walls, the excavation can usually be narrower
because double sets of walls are not needed and, therefore, the
overall cost of the structure would be reduced.
In practice, however, the answer is not that obvious. We must first
look at analytical and design considerations,
construction challenges, and determine whether or not a slurry wall
is even necessary.
Analysis and Design Considerations
In recent times, we have harnessed the great capabilities of computers
to learn things about slurry wall analysis that we never knew before.
For example, when slurry walls are to be connected to the tunnel
or building structure, it is now standard practice to do a staged
construction analysis—the slurry walls are modeled for construction
stages, where excavation proceeds to a certain depth, then tiebacks
or cross lot braces are installed. The staged excavation is non-linear
in that each stage adds moments and forces to subsequent stages.
Staged construction analysis is very different and more complex
than the traditional excavation support analysis, which consisted
basically of a final loading condition, an assumed soil and water
pressure, and strut/tieback support points. Staged construction
analysis also leads to the following problems:
- The moments and forces predicted by the model often
can be much greater than the traditional final condition model.
There is limited verification in the literature, however,
that these critical temporary conditions actually occur during
the wall construction. The result can be a conservative design
that adds to the cost of the slurry wall.
- The design is dependent upon assumed construction staging
sequences. In typical design/bid/build contracts, it
is necessary for the designer to design the slurry walls because
they are part of the final structure. The wall cannot be simply
specified, then designed by the contractor. If, during construction,
the contractor needs to adjust the strut or tieback arrangement
or sequence, the wall needs to be redesigned and the client ends
up paying for two wall designs.
Construction Considerations
Slurry wall construction must deal with some additional challenges,
particularly when the wall will be used as part of the final structure.
For example, slurry walls may be difficult to build in areas where
there are many underground obstructions. These can be natural obstacles,
such as glacial boulders, or man-made objects, such as buried foundations
from old buildings. In cast-in-place construction, the obstructions
are still there, but they are easier to see and remove. Slurry wall
construction is more prone to delay and claims than cast-in-place
construction.
Another construction challenge is that the field connections of
slabs to slurry walls are more difficult than cast-in-place construction.
Problems include:
- Crushed blockouts
- Rebars in the wrong place in the wall
- Bars that are difficult to bend
- Leakage because the blind side of the wall (next to the soil)
can not be waterproofed or because imperfections in slurry wall
concrete (pervious zones) permit groundwater seepage through the
wall.
A third challenge is that the construction tolerance for a slurry
wall is greater than for cast-in-place construction. Although slurry
walls can be built close to where they are supposed to be, it is
impossible to get the walls perfectly in position—there will
always be a few panels that are out of alignment. In some extreme
cases, panels may be installed so far out of alignment that the
contractor will be responsible to design special work around connection
details. The concerns are magnified when dealing with the tolerance
of the reinforcement because rebar inserts can end up in the wrong
place and soldier piles in SPTC walls can be out of line and twisted.
Do You Really Need a Slurry Wall?
If there is an obvious benefit to using slurry walls as part of
the structure, then it can become tempting to design slurry walls
in cases where they may not be needed. Slurry walls offer design
and construction benefits, but at a price. The construction is specialized
and usually much more expensive than other excavation support walls
or a sloped excavation if you can get away with it. Slurry wall
construction also requires more space for the slurry plant and reinforcement
staging, and it is messier.
Consider two examples from the CA/T project:
- I-93 mainline cut-and-cover tunnels, where slurry walls are
part of the permanent structure
- Leverett Circle ramp cut-and-cover tunnels, where slurry walls,
where used, are not part of the permanent
structure.
I-93. It was decided to also use the slurry walls
as part of the permanent tunnel walls because, in part, the width
of the excavation would be 3 m to 4.6 m (10 feet to 15 feet) narrower
than if separate, cast-in-place walls were used. The excavation
width was a key design consideration because adding just a few more
feet would directly
impact existing building foundations. (See “Using SPTC Walls
as Permanent Tunnel Walls” by Das et al.)
Leverett Circle. The connecting ramps feature
tunnels that are not as wide or deep as the mainline I-93 tunnels
and that will be built, for the most part, relatively far from existing
buildings. Slurry walls are designed in some limited locations,
however, such as beneath existing railroad tracks. The reasoning
for not using the walls as part of the permanent structure was that
the Leverett Circle ramps are designed to “float” on
a mat foundation. Connecting to slurry walls at one location would
introduce a hard point, which meant that either:
- A joint would be needed between the floating mat section and
the section connected to slurry wall.
- The entire tunnel alignment would have to be built on deep
foundations.
Using slurry walls as part of the final structure can make sense
in many cases, but it should not be an automatic
decision. The designer should first consider slurry walls where
needed, then weigh other factors, as described above, before incorporating
the walls in the final structure. |