Parsons Brinckerhoff
Worldwide LocationsContact PBLegal NoticeSite MapHome
PB Websites search Advanced Search
MarketsServicesAbout UsPeople and CareersNews and EventsResearch LibraryProjects
PB Network Email This Page
Go To Other Issues | Contact PB Network | Print This Article 
<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Geographic Information Systems (GIS) Also: Web-Based Project Management Tools
September 2001 • Issue No. 50 • Volume XVI • Number 2
Application/Advantages of Alternative Project Delivery Systems
Alternate Project Delivery Methods for Brier Creek Parkway Project
By Robby McDonald, Sumter, South Carolina 1-803-938-9530, mcdonaldr@pbworld.com, and Jim Ruddell, Herndon, Virginia 1-703-742-5742, ruddell@pbworld.com
The value of construction input for the design, bid and award processes increases significantly with early involvement by the construction team. An excellent example of successful collaboration between our design and construction professionals is the Brier Creek Parkway project.

Funding and scope are pivotal factors that can alter the construction start date of a project. When PB’s design and construction professionals collaborated to provide services for the Brier Creek Parkway Project in Raleigh, North Carolina, the developer and North Carolina Department of Transportation (NCDOT) had not yet agreed on either funding or scope for the construction contract. Extended negotiations delayed the project by several months, but the developer wanted to retain the original completion date of December 1998 as long as acceleration cost proved acceptable. Our goal was to identify a bid approach that both compressed the original schedule and quantified the cost of acceleration.

Finding the Best Solution

We developed a 2-step solution to meet the owner’s objectives:
  • Alter the quadruple 3-m x 2-m x 46-m (9-foot x 6-foot x 151-foot) box culvert from a cast-in-place structure to an owner-furnished precast structure
  • Insert an alternate bid item for the cost of an early construction completion date (see Table 1, which summarizes the construction contract bids for the base bid and for the alternate bid to complete early).
The cast-in-place concrete box culvert was the major project element affecting the schedule. The contractor could not optimize mass earthwork operations until he could haul over the box, and could not complete water line installation before backfilling the box because the new water line went into the backfill.


Figure 1: Brier Creek Parkway Fragnet Schedule - Comparison of Box Culvert Delivery Methods
After reviewing several options for acceleration, we concluded that the most cost-effective solution was an owner-furnished precast box culvert. Our analysis centered on the three fragnet1 construction schedules that compared the costs of an owner-furnished precast box, a contractor-furnished precast box and a conventional cast-in-place box (Figure 1). With the benefit of hindsight, PB’s recommendations proved quite accurate, as shown in Table 1.

We presented the three schedules and reviewed the cost implications of each with the developer, who accepted our recommendation to purchase the pre-cast box and furnish it to the contractor as an “install only” bid item. At the developer’s request, we then solicited bids from potential suppliers. We narrowed the field to two suppliers based on the following criteria:
  • Ability of the precaster to prepare shop drawings for NCDOT review
  • Product quality
  • Product cost
  • Ability to meet schedule
Table 1: Brier Creek Parkway Schedule- Actual vs. Planned Completion Dates
Table 2: Comparison of Bids
We discussed project requirements in detail and solicited a written schedule and cost proposal from both suppliers. After reviewing the two proposals, we recommended Gifford-Hill Concrete Products of Chesapeake, Virginia. On March 13, 1998, the owner issued notice-to-proceed to Gifford-Hill for shop drawings, precast concrete elements and delivery to the project site.

The Cost of Acceleration

Although our recommendation for an owner-furnished, pre-cast box culvert cut nearly three months off the construction schedule, we still considered the schedule ambitious. We worked with the owner to provide an alternate bid item in the contract for completion by December 15, 1998, which enabled us to quantify the cost of acceleration. A comparison of the four lowest bids is shown in Table 2.

The developer awarded the construction contract to Rifenburg Construction Inc. Construction was proceeding on schedule when the owner added surface asphalt to the contract scope in November 1998. Owing to inclement weather, the owner granted the contractor an extension. As of March 1999, the project is complete, pending final acceptance into the NCDOT roadway system.

By tailoring two contractual elements to meet the owner’s needs, PB delivered bid documents that compressed the original construction schedule by five months and quantified the cost of acceleration as a bid alternate.

Robby McDonald is the construction engineer for the Brier Creek Parkway project. His experience includes wastewater treatment plants, water distribution systems and highway construction. In 1998, Robby was named a finalist for Construction Services company’s Inspector of the Year.

Jim Ruddell is operations manager for the Construction Services company’s Mid-Atlantic region, a senior project manager and professional associate in construction management.

<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Go To Other Issues | Contact PB Network | Print This Article 
Markets  |  Services  |  About Us  |  People + Careers  |  News + Events  |  Research Library  |  Projects
Worldwide Locations  |  Contact PB  |  Legal Notice  |  Site Map  |  Home
© Parsons Brinckerhoff