Parsons Brinckerhoff
Worldwide LocationsContact PBLegal NoticeSite MapHome
PB Websites search Advanced Search
MarketsServicesAbout UsPeople and CareersNews and EventsResearch LibraryProjects
PB Network Email This Page
Go To Other Issues | Contact PB Network | Print This Article 
<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Geographic Information Systems (GIS) Also: Web-Based Project Management Tools
September 2001 • Issue No. 50 • Volume XVI • Number 2
Hudson-Bergen Light Rail Transit System
Utility Relocation for a DBOM Project
By Asim K. Datta, Newark, New Jersey 1-973-353-7627, datta@pbworld.com
As the general design consultant to NJ TRANSIT, PB was responsible for design and management of utility relocation for the initial operating system of the HBLRTS project. This approximately $40 million relocation in a densely populated industrial corridor was a unique and challenging endeavor.

PB began the design and management of the 15 km (9.3 mile) -long Initial Operating Segment (IOS) of the Hudson-Bergen Light Rail Transit System (HBLRTS) in 1994. As the general design consultant (GDC), PB carried the responsibilities of the production of preliminary engineering documents, which in some cases were more than the traditional 30 percent design drawings.

Due to the unique nature of the design/build/operate/maintain (DBOM) concept, it was decided to complete the utility design to the 80 percent to 90 percent level. At the outset, we realized the importance of successful utility relocation and its impact on the project schedule, however, and determined this high level to be important.

Identifying Construction Impacts

The project required that 30 percent of the design activities be done by the Disadvantaged Business Enterprises (DBE). After careful consideration, PB selected qualified local subconsultants familiar with the area to complete the existing utility mapping for the IOS. This mapping included the existing utility information from the municipal and private utility agencies for a 152-m (500-foot) -wide corridor 76 m (250 feet) on either side of the alignment. The mapping was validated by field-verification and revised by PB engineers for CADD standard and technical correctness.

The IOS was divided into nine design units for better management and design control. It was very important to maintain a tight schedule and meet the client’s requirements. We completed preliminary engineering for some of the design units and subcontracted others out to local DBE subconsultants, while taking complete responsibility for the management of the design.

We asked each design unit team to review the mapping and, if necessary, update it by field inspection and additional survey. We then finalized the existing utility mapping and prepared the “Composite Plan of Existing Utilities” drawings (25.4 mm = 9.154 m, or 1 inch = 30 feet). These drawings were sealed and signed by PB.

Designers identified the construction impacts the HBLRTS facilities would have on the existing utilities, then designed new facilities and relocated existing ones in accordance with HBLRTS’s Manual of Design Criteria and the utility agency’s requirements. They prepared large-scale details as required to address the design needs.

Designers prepared detailed utility impact matrices for each design unit to inform the DBOM contractor of each affected utility along the LRT corridor and the recommended rearrangement solution (Figure 1). To this point, the work processes were the same as those of the traditional design/bid/construct project.


Figure 1: Utility Impact Matrix
In-Progress Preliminary Submittal

The demanding schedule created a special challenge for our team. A design/bid/construct project normally has the luxury of four stages of submission, review and coordination process—preliminary, in-progress, pre-final and final. Naturally, the time required is substantial. For the HBLRTS project, the time available from conception to the production of final preliminary document was only eighteen months. We accepted the challenge, and decided to make only one submittal—”in-progress preliminary.” Schedule was critical.

We sent in-progress design unit submittals to all utility agencies, received review comments, met with the utilities and municipal agencies numerous times, coordinated their comments and resolved all conflicts. Designers checked the impacts due to final storm sewer modifications, revised utility drawings, accordingly, and updated the utility impact matrices. Designers completed final preliminary drawings (80 percent to 90 percent level of design) for the DBOM contractor, ready to be bid.

Preliminary (DBOM) Submittal

On this DBOM project, contractors submitted their bids based on the set of preliminary design documents. We were actively involved in the selection process and helped the client to choose the DBOM contractor, who was responsible for the final design and construction. It was decided that all water, sanitary and storm sewer construction would be done by the DBOM contractor and that all other utility construction would be done by the respective utility agencies.

As NJ TRANSIT’s representative, we also maintained an active role during the review and construction phase, continued coordination with the private utility agencies and eventually received their final design and construction cost estimates. We then submitted our comments and resolutions to the DBOM contractor for action.

Because of the higher level of completion of the design, preliminary (DBOM) submittal was extremely valuable for the DBOM contractor. There were no surprises for the private and public utility companies. The utility agreements were in place, funds were available, and construction was ready to continue at a fast pace.

Final Design and Construction

PB continued to assist the contractor to resolve design conflicts and advance the construction. When private developers along the LRT corridor came up with their plans for future construction and required additional utility services, we addressed their needs and incorporated the design into DBOM construction, saving money and disruption to public right-of-way.

During the construction phase, public and private utilities came up with additional requirements that we helped to resolve, keeping construction on schedule.

Conclusion

The following are some of the important factors that contributed to the success of the project:
  • The client was actively involved in the selection, review and design process.
  • Our knowledge of large transit projects helped the client to anticipate the issues before it became critical.
  • We did not underestimate the need for a detailed existing utility survey.
  • We set up and maintained an open channel of communication with the client.
Our experience coupled with the cooperation of an extremely qualified and hands-on client helped to make this DBOM project a successful one.

Asim K. Datta, a professional civil engineer and PB certified senior project manager is the manager of utilities design, H-BLRTS. His 23 years of service in fixed guideway system design at PB included two successful projects, Metropolitan Rapid Transit Authority (MARTA) in Atlanta, Georgia and Bay Area Rapid Transit (BART) in San Francisco, California.

<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Go To Other Issues | Contact PB Network | Print This Article 
Markets  |  Services  |  About Us  |  People + Careers  |  News + Events  |  Research Library  |  Projects
Worldwide Locations  |  Contact PB  |  Legal Notice  |  Site Map  |  Home
© Parsons Brinckerhoff