Movable Bridges
July 2000 • Issue No. 47 • Volume XV • Number 2
Construction
Replacement of the George P. Coleman Bridge
By Michael J. Abrahams, New York, New York, 1-212-465-5185, abrahams@pbworld.com and
Raymond J. Castelli, 1-212-465-5212, castelli@pbworld.com
The Coleman Bridge project was remarkable in many ways. This article focuses on two aspects-reusing existing caissons and the construction sequence.

Awards for the George P. Coleman Bridge

  • 2000 Merit Award, Design for Transportation National Award. U.S. Department of Transportation.
  • 1998 Prize Bridge, movable span category. The National Steel Bridge Alliance/American Institute of Steel Construction.
  • 1997 Grand Conceptor Award. The American Consulting Engineers Council.
  • 1997 Outstanding Civil Engineering Achievement. Virginia Section of the American Society of Civil Engineers.
  • 1997 George S. Richardson Medal for Single Recent Outstanding Achievement. The International Bridge Conference, Pittsburgh, Pennsylvania.
  • 1997 Roebling Award. The American Society of Civil Engineers, Construction Division.
  • 1997 Engineering Excellence Award. The New York Association of Consulting Engineers.
  • PB Project of the Year.
    Constructed projects category, 1996
The Virginia Department of Transportation selected PB to provide engineering services for the replacement of the George P. Coleman Bridge, a major project intended to reduce traffic congestion. The replacement, which was to be done on the existing caissons (pier foundations), was selected from the alternatives proposed in PB's earlier crossing study.

Major Features Established during Preliminary Design


During the preliminary design phase, major design features were established. The bridge was widened considerably to 23.5 m (77 feet), with:

  • Four 3.6-m (12-foot) -wide traffic lanes
  • Two 3-m (10-foot) -wide breakdown lanes
  • Concrete exterior parapets
  • A concrete median barrier
  • A lightweight-concrete deck for the truss and swing spans.
Other design features, while less visible, are equally important to the swing spans:

  • Hydraulic Drives. Instead of what had proceeded to be a mechanical drive system on the original bridge, the new bridge incorporates hydraulic drives.
  • Power Source. The power supply is more reliable than that for the original bridge because there are now two power sources and a backup generator for the entire bridge. Previously there was only one power source and a backup system.
  • Additional Features. Features added to improve inspection and care of the span included, for example, lighted maintenance walkways beneath the roadway and a maintenance parking area on the approach spans.
Evaluating Existing Caissons

An important consideration in the new bridge design was the reuse of the existing river caissons to support the heavier loads of the wider structure. We had to evaluate:

  • Surface and subsurface conditions
  • The piers' resistance capacity
  • Additional loads
  • Likelihood of collapse.
Surface and Subsurface Conditions. During the preliminary design phase, we conducted extensive survey and boring programs to carefully establish existing surface and subsurface conditions-information needed to prepare final design plans. The most effective way to measure the ground's behavior is through soil borings and other on-site tests, which we conducted at depths of up to 70 m (225 feet). PB's geotechnical investigations confirmed that the existing river piers could support a widened bridge.

Resistance Capacity. The adequacy of the existing river piers' resistance capacity against vessel collision was evaluated according to the design provisions established by AASHTO's "Guide to Specification and Commentary for Vessel Collision Design of Highway Bridges" (1991).

A record of all ships using the channel over a 5-year period was obtained from the Coleman Bridge operator's logs and used to establish the size and frequency of river traffic. Because the operator's house was open all day, the logs provided an accurate record of traffic, included the name of each vessel or tug boat and the number of barges being towed, as well as the time and direction of travel.

Additional Loads and Frequency of Collapse. We used a 3-D non-linear, finite element soil-structure interaction analysis to establish the lateral load response for a ship collision load. These capacities were compared to the force generated by the ship population drawn from the 5-year history. We then were able to compute the annual frequency of collapse for the full range of ships and demonstrate that it exceeded 10,000 years.

Therefore, no large-scale independent protective structure was required. The existing timber rub strips and the river piers were replaced with a more modern rubber fender system, however, to provide protection against minor vessel impact.

Construction Includes Floating The Spans into Place

The original plans called for a temporary floating bridge to be located just upstream of the existing bridge to carry traffic during construction. The legislature voted against this option, however, because of costs and the inconvenience of a detour. (We had been planning all along to replace the superstructure using float-in techniques for a number of reasons.)
As a result of the vote and the need to minimize detour time for traffic, contract provisions were developed to provide a large incentive for the contractor to minimize the bridge shutdown. Construction for the bridge widening took place in three phases plus preparation and final cleanup while the superstructure was replaced.

Preparation. Preparation included widening the tops of the river piers, land piers and abutments. The widening of the land piers and abutments was done with added piles, widened footings and widened pier shafts and abutment stems. At the same time, the six new river-crossing truss sections were built off site. These sections were two swing spans, two anchor spans and two suspended spans. The swing spans were each 154 m (500 feet) long-some of the largest in the world. Normal traffic continued on both the river and bridge during this phase of the work.

Phase 1. New outside lanes were built at both ends of the bridge at the land piers. Normal traffic continued as new construction was kept outside of the existing traffic lanes. Then traffic on the approaches was shifted to the newly constructed outside lanes and most of the existing inner lanes were demolished and replaced.

Phase 2. The existing truss sections over the river were removed and the six new truss sections, which had been constructed 60 m (40 miles) from the site, were floated in and the bridge was opened to traffic-all within 9 days.

Phase 3. After the river truss sections were replaced, traffic was shifted to the newly built outer lanes on the approaches. The remaining existing inner lanes on land were demolished and rebuilt. All four lanes were opened to traffic after temporary barrier curbs were removed and final roadway striping placed.

PB provided extensive construction services, including the provision of a resident engineer, continuous field consultation, and mechanical and electrical assistance for the installation of machinery and controls for the swing spans as well as for the automated vehicle identification (AVI) system. We also provided shop drawing review and were responsible for the preparation of as-built drawings.

The bridge, which was dedicated on August 2, 1996, has won a number of awards, as shown in the box above.

Ray Castelli has 25 years experience in conducting and managing geotechnical investigations, foundation design and construction services for major bridge, marine and tunnel projects. He is Operations Manager of the Geotechnical and Tunnelling Division in PB's New York City office. Ray is a member of the Deep Foundations Committee of American Society of Civil Engineer's (ASCE's) Geo-Institute, a corporate representative to the International Association of Foundation Drilling (ADSC), and a licensed professional engineer in four U.S. states

Michael Abrahams is a structural engineer with more than 30 years of experience, primarily in movable and floating bridges. He recently authored the chapter on Movable Bridges in the Bridge Engineering Handbook, published by CRC Press.

<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Go To Other Issues | Contact PB Network | Print This Article 
Markets  |  Services  |  About Us  |  People + Careers  |  News + Events  |  Research Library  |  Projects
Worldwide Locations  |  Contact PB  |  Legal Notice  |  Site Map  |  Home
© Parsons Brinckerhoff