Parsons Brinckerhoff
Worldwide LocationsContact PBLegal NoticeSite MapHome
PB Websites search Advanced Search
MarketsServicesAbout UsPeople and CareersNews and EventsResearch LibraryProjects
PB Network Email This Page
Go To Other Issues | Contact PB Network | Print This Article 
<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Movable Bridges
July 2000 • Issue No. 47 • Volume XV • Number 2
Construction
Merseyside's Poulton Swing Bridge
By Richard Sansbury, Taunton, U.K., +44-1823-253291, sansburyr@pbworld.com
Replacing an old moving bridge over the busy Merseyside docks in the U.K. gave our bridge design team the opportunity to present a full range of services-from conceptual planning through detailed design to contract administration.

The docks at Merseyside contain several moving bridges that date back to the early 1900s when the Port of Liverpool was a major gateway for international trade. The docks are quieter now, but are still active and remain a focus for heavy industry in the centre of a large population. A busy network of roads with a high proportion of heavy trucks crosses the docks, and maintenance of the original bridges requires a considerable effort from the local highways authority.


The original bridge is demolished
The Need to Replace Poulton Bridge

Poulton Swing Bridge crossed the docks carrying a main road from Birkenhead to Wallasey. Built originally in 1926, its primary use was to carry a single quayside railway track. The quayside railways were torn up long ago but the original steel truss bridge remained, although with dimensions more suited to railway traffic than road traffic. With only 3.9 m (12.8 feet) of headroom and 5.4 m (17.7 feet) width between kerbs, the steelwork was damaged frequently by passing vehicles.

In 1993, we were commissioned by the local authority, the Metropolitan Borough of Wirral, to carry out a feasibility study for easing the width and headroom restrictions on the bridge. It soon became apparent that any attempt to keep the existing bridge trusses would not be cost effective. A wider structure would have to be set back further from the dock edge in order to give full clearance to passing ships and, thus, the main span would be increased. The trusses would have needed strengthening and the cross girders would have had to be either lengthened or replaced. Moving the pivot point of the swing span would require extensive modifications to the mechanism and foundations. Therefore, a new bridge structure was recommended.

Although other forms of moving bridges were considered, a new swing bridge was chosen to replace the original. A swing bridge suited the site because it would have a shallow foundation depth and the empty land required for the bridge to swing over was already available.


A 200 Tone section of the new Poulton Bridge is craned into position on the new foundation
Detailed Design

Following the successful feasibility study, the Borough extended our commission to include the detailed design of the new structure. It was agreed that the bridge deck and foundations would be fully designed at this stage, but the mechanical and electrical (M&E) works would be included as a design/build element of a construction contract due to their specialised nature.

Deck and Foundations. Detailed design of the new structure was carried out in our Taunton office. The bridge superstructure design comprises a 860 tonne (846 ton) steel box girder deck with a 42-m (138-foot) -long main span and 24-m (79-foot) -long back span. The decking is an "orthotropic" steel deck with steel cross beams and main box girder beams to either side of the road.

Because of the shallow construction depth required, the box beams are partly above and partly below road level and are protected from traffic damage by a crash barrier. The walkways are supported on cantilevers to the outsides of the main beams, safely away from the traffic. The counter balance is provided by a 380-tonne (374-ton) concrete slab that also acts as the deck of the back span, and the foundation design is a reinforced concrete slab on bored piles.

M&E Works. We prepared an outline M&E design and performance specification in which the bridge was to be rotated by hydraulic rams acting on a chain around the central pivot. Before rotating, the bridge first tilts back slightly so that the nose end lifts clear of the end bearings. This tilt is achieved by a system of jacks and wedges at the tail end that allows the tail bearings to slide clear which, in turn, allows the tail end to drop down onto rollers.


The new bridge as it nears completion
Construction

The £3 million construction contract commenced in 1995. A traditional British form of contract was used with our firm acting as "the Engineer" with responsibility for contract administration, approval of the M&E design and full time site supervision. The contractor was Birse Construction Limited and their designer for the M&E works was Sir William Arrol, part of the Rolls Royce group. Their design for the main hydraulics differed slightly from that specified in that the chain around the pivot was replaced by a system in which a pair of main hydraulic rams aligned at 45° to the bridge to act directly on the central cross girder.

Construction took 15 months, slightly longer than intended. There were obstacles encountered during piling that required redesign of the foundations, and some issues with the design/build element of the works that delayed the installation of fundamental M&E components. Despite these problems, however, the bridge opened in the first quarter of 1996 and is successful in providing a much improved highway across the docks.

Richard Sansbury BA (Cantab) CEng MICE is a bridge design engineer based in PB's Taunton, U.K. office with eight years experience in design and assessment of bridges of all types. He was part of the design team for Poulton Swing Bridge and one of the site supervisors during construction.
<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Go To Other Issues | Contact PB Network | Print This Article 
Markets  |  Services  |  About Us  |  People + Careers  |  News + Events  |  Research Library  |  Projects
Worldwide Locations  |  Contact PB  |  Legal Notice  |  Site Map  |  Home
© Parsons Brinckerhoff