Parsons Brinckerhoff
Worldwide LocationsContact PBLegal NoticeSite MapHome
PB Websites search Advanced Search
MarketsServicesAbout UsPeople and CareersNews and EventsResearch LibraryProjects
PB Network Email This Page
Go To Other Issues | Contact PB Network | Print This Article 
<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Power Engineering
November 2000 • Issue No. 48 • Volume XV • Number 3
Power Systems Studies
Minimizing Risk in Power Plant Development Projects
By Peter Reimann, Wellington, New Zealand, +64 4495 8615, reimannp@pbworld.com

Power plant developers naturally focus on money and time, but a variety of pitfalls that often have engineering roots can lead to project cost and schedule overruns. Apart from taking these pitfalls on board ourselves, we have a responsibility to educate our clients about them.
Many power plants are constructed by developers who obtain funding from banks and other lending institutions. To minimise risk, the construction is awarded to an engineer, procure and construct (EPC) contractor, often on a "turnkey" basis. The developer, or "owner," frequently hires an engineer to oversee all or part of the project. The lenders usually employ an engineer also-the "independent engineer"-in an auditing role, to ensure the project in which they have invested is robust. Despite these precautions, some projects have been dogged with cost and schedule overruns and the final plant has been less than satisfactory.

The engineer, who has been involved in the implementation of a variety of projects, is in a unique position to comment on the pitfalls that cause these problems. These pitfalls, which often have engineering roots, are avoidable. Apart from taking these on board ourselves, it is our responsibility to educate our clients about them. It is hoped that this article will provide a starting point for this process. The cases presented are drawn from recent experience and observation.

Inadequate Feasibility Study/Concept Design

The feasibility study for a project should identify areas of uncertainty that require further investigation. Time constraints may dictate proceeding with preparation of contract documentation before these areas have been properly resolved, however, and before the conceptual design has been completed.

Outcomes and Risks:
  • Delays in completing the contract documentation
  • The need to issue addenda to bidders after contract documentation has been issued
  • Issues not coming to light until after the contract has been awarded, requiring time and resources to resolve.
Mitigation: Adequate time and resources for the feasibility study and conceptual design are essential.

Capital Cost is too Low

The capital costs estimate is used at the conceptual stage to decide on the viability of a project. If the EPC contract is awarded several months later, the capital costs may be higher for one or more of the following possible reasons:
  • The full extent of the project scope may not be fully understood at the conceptual stage (e.g. foundation requirements).
  • Conditions of the contract are not formulated at the early conceptual stage (e.g., terms of payment).
  • The suppliers' budget prices that are used to make up the estimate can be unreliable.
  • Market prices, exchange rates and political influences can change radically.
  • The contingency margin is inadequate.
  • Some optimistic assumptions have been made.
Outcomes and Risks: Too low a price places pressure on all subsequent phases, forcing the owner to take possible actions that introduce risks as follows:

Mitigation: The conceptual stage is too early to form reliable price estimates, so developers and bankers need to apply an appropriate margin in the sensitivity analysis during financial modelling. The engineer can assist in establishing this margin.

Project Schedule is Too Short

There is a natural tendency to compress the schedule for a quick return on investment-even more so when the project is marginally viable.

Outcomes and Risks: A compressed schedule puts pressure on all phases of the project, introducing the following risks:
  • Lateness
  • Errors and omissions that arise from all who are involved in the project working under extreme pressure.
Mitigation: Risk of lateness is usually transferred to the EPC contractor by imposing a penalty payment. The owner should consult with the engineer and prospective supplier at the conceptual stage to ensure that a realistic schedule is adopted.

Owner's Engineer is Inappropriate

The owner's engineering firm is usually selected on the strength of its proposal in response to a brief prepared by the owner. The price for a project needs to be fixed for financing purposes, so the contract with the owner's engineer is on a fixed-price basis. The appointment of an inappropriate owner's engineer can result from the selection of the lowest priced proposal.

Outcomes and Risks:
  • Owner's engineer has inadequate experience.
  • Owner's engineer has inappropriate personnel.
  • Owner's engineer has allowed for carrying out the duties, but to insufficient depth.
Mitigation: The owner should provide a detailed, comprehensive brief that, if necessary, is prepared in consultation with prospective engineers. Adequate time must be given for proposal preparation. The engineer's proposal should demonstrate that adequate quality systems are in place. The owner needs to recognise that the lowest-priced proposal may not be the most cost-effective, and should give most weight to reputation and experience.

Inappropriate Personnel/Clashes

The appointment of inappropriate personnel or clashing personalities or cultures can be a disaster for a project. This potential problem applies across the combination of owner, owner's engineer and EPC contractor. These appointments are often made on the apparent strength of the curriculum vitae (CV) or resume, aided by the verbal acumen and networking of the candidate.

This approach is far from infallible. CVs can distort the facts. For example, the management record on a CV may look impressive, but conceal incompetence. Referees nominated in a CV will be those who the candidate feels are more likely to report favourably.

A person may be impressive at an interview, but later performance shows otherwise. Even if the exercise of appointments is successful, a project can still be riven by personality clashes or insensitivity to cultural differences.

Outcomes and Risks:
  • Errors and omissions
  • Delays
  • Lack of cooperation
  • Low morale.
Mitigation: The independent engineer can play a key audit role of personnel during the progress of a project. A periodic audit can be based on a questionnaire that is structured to reveal any weaknesses of key members of the project team-the owner, owner's engineer and EPC contractor. An independent party who is skilled in this area should conduct the audit for the independent engineer in order to preserve impartiality and confidentiality. The audit report should be circulated to all parties, including the lenders, for appropriate action if necessary.

Misunderstanding Between Owner and Owner's Engineer

Owners often like to play a "hands-on" role in a project, and the role of the owner's engineer can be anything from providing "advice when sought" to full involvement. Owners may insist on handling all communication with the contractor and outside parties.

Outcomes and Risks:
  • Misunderstandings
  • Inadequate or incorrect action or omissions on technical matters.
Mitigation: Definition of duties and communication channels are of paramount importance during the formation of the contract between the owner and owner's engineer. Both parties should be formed into a dedicated team in a dedicated office and make the project rather than their respective source companies, their prime commitment.

Contract Documentation is Inadequate

Lenders demand a fixed cost with maximum risk passed to the EPC contractor. This arrangement necessitates an approach under which the EPC contractor performs the detailed engineering and oversees interfacing between subcontracts.

There is sometimes a perception that only the technical specification needs to set out requirements for:
  • Scope
  • Climate
  • Performance
  • Environment
  • Site
  • Safety and health.
In this case, the bidder will opt for the lowest-priced equipment, with quality only high enough to ensure that there will be no risk during the warranty period. During project implementation, the EPC contractor will provide minimum information for review. This situation presents an ideal opportunity for short-cuts and provision of lower quality than required.

Outcomes and Risks:
  • Plant is less than satisfactory.
  • Lower reliability and shorter plant life.
Mitigation: The technical specification needs to include:
  • Definition of standards, materials, corrosion protection and other specific technical requirements that clearly state the quality of the plant
  • Requirement that a certified quality system be in place together with third-party inspection and witnessing of tests
  • Detailed lists of information required for review during project implementation
  • Clear scope/interfaces if any detailed design is to be carried out by the owner/engineer.
The owner needs to ensure that there is sufficient budget for the project team to monitor quality adequately through the design review, manufacturing and site construction, and commissioning/ testing phases.

Bid Evaluation is Inadequate

Bid documentation sometimes gives an inadequate definition of the evaluation methodology and of the information required for tender evaluation. Particular omissions may include:
  • The cost adjustment to be applied for efficiency or output
  • Information about how the quality of the plant will be evaluated.
Outcomes and Risks:
  • Inappropriate plant is provided.
  • Contractual arguments develop later.
Mitigation: A bid evaluation should include price, operating and maintenance (O&M) cost, efficiency/fuel cost, net output/revenue, adherence to the specification and conditions of contract, as well as experience, schedule, availability, degradation, quality system, safety/health and training provisions. The assessment of technical features should look at risks, capability of handling off-design situations, start-up times, maintainability, operability and implications for external provisions.

The bid documents need to detail:
  • The tender evaluation methodology so that the bidders will know what weight will be placed on the above aspects
  • Technical schedules and lists of information required in the bid.
Excessive Pressure on Bidder During Contract Negotiations

At the negotiation stage, the owner is in a position to apply pressure to reduce the price. The bidder may succumb to these pressures, particularly if needing to secure the work.

Outcomes and Risks: The contract negotiation stage is critical in setting the climate for the subsequent implementation. If pressure is too great, a highly adversarial relationship can result. The contractor will try to take short-cuts and lodge as many claims as possible for contract variations, at inflated prices. Particular risks are:
  • Less than satisfactory plant
  • Considerable increase in work for the project team, policing compliance with the contract, and dealing with the claims for contract variations
  • Stressful relationships between owner and EPC contractor, owner and engineer, and engineer and EPC contractor.
Mitigation: The owner should be aware that excessive pressure applied during negotiations can achieve the opposite effect to that intended in the long run. The ideal relationship is a cooperative one that is fostered largely by attitude. The EPC contractor could take up some equity in the project to help achieve a cooperative relationship.

Inadequate Attention Given to Safety and Operability


All projects carry safety and operability risks. It is the team's duty to ensure that statutory regulations, standards, quality assurance and testing are adhered to. There is a risk of inadequate coverage of these areas if a hazard and operability study (HAZOP) is not carried out.

Outcomes and Risks:
  • Accidents
  • Maloperation.
Mitigation: A HAZOP study should be carried out when it will be relatively easy to incorporate modifications that result from the study findings, but also when designs are near enough to finalisation. The HAZOP study brings together all participants-owner, independent engineer, owner's engineer, EPC contractor, major sub-contractors and O&M contractor. Each system is then examined in a structured way for "what if" scenarios. A secondary benefit of the HAZOP study is that it provides an excellent opportunity for the O&M personnel to learn about the system and to contribute.

Conclusions

The EPC or turnkey type of contract is ideal for developers because the capital cost is fixed at the outset and the risk is placed onto the EPC contractor. There are many pitfalls that can result in a less than satisfactory plant. These may lead to capital and O&M cost increases, lower reliability and life, as well as accidents and schedule delays.

It is important that these pitfalls are Recognize so that they can be avoided. The engineer, having had past involvement in implementation of a variety of projects, is in a unique position to assist if introduced to the project at its inception and retained to play a full, active role as owner's engineer throughout. This approach will result in the most cost-effective plant for the entire period of the investment.

Peter Reimann is a mechanical engineer and Senior Professional Associate who, for more than 35 years, has accumulated wide and varied experience in a number of countries. He has worked predominately in the power generation and thermal energy fields with consulting, manufacturing and government organizations.
<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Go To Other Issues | Contact PB Network | Print This Article 
Markets  |  Services  |  About Us  |  People + Careers  |  News + Events  |  Research Library  |  Projects
Worldwide Locations  |  Contact PB  |  Legal Notice  |  Site Map  |  Home
© Parsons Brinckerhoff