This article
traces the development of 25 kV AC power supply delivery to the
overhead line equipment (OLE) on the UK railway network since 1956.
Its aim is to uncover the underlying design issues that govern the
delivery of power supplies to the OLE and highlight the critical
design drivers that influence future design principles of switching
stations on the railway. The term "switching stations"
is used throughout this article to describe all types of 25 kV switching
arrangements.
Overview of Power Supplies Feeding Arrangement
A series of feeder stations installed strategically along an
electrified route are used to feed 25 kV, 50 Hz, single-phase power
to the OLE. These feeder stations are, in turn, connected to the
electricity supply industry high voltage network. The primary connection
voltages include 132 kV, 275 kV and, lately, 400 kV for use on automatic
transformer systems. Figure 1 shows a typical feeding arrangement
diagram. The track, return current systems and switches are omitted
for clarity.
The OLE is divided into main electrical sections separated by neutral
sections at feeder stations and mid-point track section cabins/locations.
Bus-section circuit breakers are installed across the neutral sections.
The feeding system is radial, with the normal arrangement being
feeds from each feeder station out to the open bus section at the
mid-point track section cabin. Radial feeding is necessary because
the supplies from feeder stations are from different phase pairs
and different power networks, thus precluding paralleling. During
abnormal feeding, however, this open point may be moved using the
bus section circuit breakers.
For operational and maintenance reasons, the OLE is further divided
into electrical subsections at track section cabins or intermediate
track section cabins/locations where installed. The OLE sectioning
at these locations is achieved through insulated overlaps between
mechanical tension lengths in the OLE. Typically, dual supply circuits
are installed at feeder stations to safeguard the security of power
to the track. These circuits are usually derived from different
phases and, for added security, perhaps from different parts of
the electricity supply industry network.
Background
Railway switching station design goes back to the early days of
25 kV AC electrification, which started in the UK in 1956 for the
route between Euston, Manchester and Liverpool via Birmingham. The
change to electrification involved the installation of 76 switching
stations. The design concept was to house all high voltage switchboards
in brick buildings together with associated ancillary equipment
(e.g. supervisory control and data acquisition systems (SCADA),
battery and charger heaters, low voltage (LV) panels for domestic
power supplies, and changeover panels for signalling supplies).
The type of switchgear used was K11 oil-filled circuit breakers.
The feeds to the OLE were via cables.

Figure 1: Typical Feeding Arrangement Diagram |
In 1959 the Colchester-Walton and Clacton line was
electrified, but this time using small oil-filled type circuit breakers.
Again, the choice of housing was a brick building and the feed to
the OLE was through cables. Between 1967 and 1973, the Glasgow-Gourock-Wemyss
Bay line was electrified using outdoor oil-filled switchgear K11-W.
The delivery of power to the OLE was through weatherproof bushings
and the connection to the OLE was achieved by aerial bare-copper
conductors.
After completion of the Euston, Manchester and Liverpool electrification
scheme in 1966, equipment suppliers introduced the vacuum circuit
breaker for 25 kV AC single-phase use. The British Railway Board
had always taken an active interest in simplifying the switching
station design and lowering the maintenance burden, and the use
of vacuum interrupters obviously reduced the maintenance work when
compared with oil-filled equipment.
The first vacuum circuit breaker equipment was installed at Camden
track section cabin for evaluation. This trial proved to be successful
and has led to vacuum circuit breakers being used in metal-clad
housing with roof bushings on subsequent electrification schemes,
which included the Weaver Junction to Glasgow electrification in
the mid-1970s and the East Coast Main Line in 1984-1991. In both
cases, the delivery of power to the OLE was through bare aerial
feeds. The switching stations design development profile is depicted
in Figure 2.

Figure 2: Railway Switching Stations Design Status
|
In 1963, Kennedy & Donkin (which joined PB in
1998) provided support to the British Railway Board for calculating
touch and step potentials and has provided many feasibility studies
regarding the 25 kV 50 Hz electrification in the UK. (Touch and
step potentials are calculated to ensure that under normal operating
conditions no harmful voltages will appear in switching stations
compounds, and there is no danger of system workers and users getting
electrical shocks because the switching station is not properly
earthed. Touch and step potentials are very important design safety
parameters for electrified sites. We were very active in the electrification
design activities and, in fact, providing the majority of technical
papers written on electrification.
Switching Station Designs
Traditionally, the switchgear market has been led by the electricity
supply industry, which had used both indoor and outdoor switchgear
successfully on its infrastructure. The railway switchgear market
segment is not normally large, so a "quantity dilemma"
was experienced by manufacturers who were unable to justify the
cost of producing small batches of units specifically for the railway
market. In fact, toward the end of the 1980s some suppliers reported
that the future production of the vital vacuum interrupters might
be disrupted.
Because most vacuum circuit breakers installed on the railway were
approaching their 20-year design life, this situation had caused
some concern to equipment maintainers. Railway authorities are slowly
addressing the issue by the use of design/build and maintain projects
that include manufacturing partners and alliances to deal with long-term
equipment replacements and the new technology available in the marketplace.

Figure 3: Approximate diagram of 25kV Switching Station
Brick Building |
Indoor Switching Stations
Indoor switchgear had benefited from key features such as the ability
to place the isolate facilities and the earth relevant circuit breakers
inside, precluding the need to go out onto the track environment.
The key features of this design include the following:
- Individual circuit breaker segregation
- Use of cable feeds from the circuit breaker to the OLE
- Use of brick buildings to shelter equipment and maintenance
staff from the weather and vandalism (Figure 3 on the previous
page).
Housing electrification equipment in brick buildings
has served the power distribution discipline well. These buildings
have survived more than 35 years. There are, however, several disadvantages
of the brick buildings:
- Weatherproofing was considered necessary as some buildings
suffered from leaks during heavy rain.
- Both oil-filled equipment and the buildings required considerable
maintenance. In fact, brick buildings were thought to be expensive
and a luxury to have.
- The switch station was difficult to relocate because it is
a permanent fixture by the trackside.
- Such buildings attract the attention of hoodlums in some vandal-prone
areas.
- Construction materials may contain asbestos; hence, a high
disposal cost is possible.
It should be recognised that this method of delivery
was an answer to 1950s power supplies constraints. These have changed
now, and the advent of new technology and materials, such as glass
reinforced plastic, provide an alternative equipment housing material.
Metal-Clad Switching Stations
During the implementation of metal-clad switchgear design in the
early 1970s, a critical decision was taken to transfer the isolation
and earthing facilities from indoor environment to the track environment
by installing track isolators and earthing switches on the OLE.
This change has saved space in the switching stations but has transferred
the problems related to space constraints to the OLE. Consequently,
more overhead system design was needed and more equipment was added
to the OLE, making the catenary system more congested (Figure 4).

Figure 4: Metal-clad Switchgear Arrangement |
It was possible to introduce vacuum switchgear on the railway and
to place the isolation switches on the OLE because of the introduction
of the vacuum circuit breaker, which resulted in integrating the
switching station more with the OLE. The consequences of these developments
have been new maintenance and operational constraints on either
the OLE or the switching station. It was no longer possible to isolate
and earth individual circuit breakers at mid point track sectioning
cabins. Instead, a complete bus bar section and its associated circuit
breakers had to be isolated and earthed to make it safe to work
on one circuit breaker only. Moreover, at intermediate track sectioning
cabins, the complete switching station had to be taken out of service
in order to maintain any one circuit breaker. This was achieved
through the operation of by-pass switches located on the OLE.
In spite of the shortcomings due to the isolation and earthing difficulty,
this type of switching station remains most popular because of ease
of construction and dismantling, and ease of transportation to site.
Structure Mounted Outdoor
Switchgear Station
The initial concept of the outdoor delivery system was to install
the outdoor switchgear on the OLE structures themselves. This
conceptual design was most innovative as it departed significantly
from past practice and cleverly made use of existing OLE infrastructure
to support the switchgear, thus minimising takings of land along
the trackside. Figure 5 depicts the conceptual approach for this
type of power feeding arrangement.

Figure 5: Overhead Line Structure Mounted Outdoors Switchgear
|
Although this design was innovative, it met with
a lot of resistance for the following reasons:
- Two maintenance functions were unified by incorporating
the structure-mounted outdoor switchgear (SMOS) into the OLE
system. Consequently, the end users of the equipment were
unable to formulate an integrated maintenance strategy to
deal with this change. Arguably, this can be thought of as
an organisational problem rather than a design concept deficiency.
- It is particularly difficult to superimpose the SMOS onto
an operational railway during the construction process because
of safety and operational constraints (e.g. red zone working
or complete block to traffic).
- Isolation and earthing procedures for OLE and SMOS are
incompatible. Again, this problem has more to do with the
inability of various departments to work with each other rather
than design weakness.
- Lack of familiarity and training of the end users produced
negative feelings and militated against the SMOS concept.
- SMOS is regarded as visually intrusive. Strenuous efforts
are required to make the SMOS aesthetically acceptable, particularly
in densely populated areas.
Incremental design development took place to mitigate
the perceived visual shortfall in the above arrangement. The result
was the use of outdoor switchgear, but this time entirely detached
from the OLE system by making use of feeder cables to deliver
power to the track. Figure 6 shows the latest approach adopted
on various locations on the electrified track.
Future Development
In the near future, railway systems in the UK will have high-speed
profiles as, for example, the 224 kph (140 mph) service on the
West Coast Main Line that is planned for 2005. Notice, however,
that this speed is moderate in comparison with others in the world's
high-speed train race. Accessing the track to undertake isolation
and earthing activities will become more hazardous during train
running hours and more costly.
In privatised railways, the commercial realities put perceptible
pressure on the designer to improve the functions and features
of switching stations to meet the new operational environment.
Moreover, in order to provide on-time service to their passengers,
train operating companies will demand sustainable power delivery
at the point of need and they will contractually levy a charge
against railway infrastructure companies that cause delays to
their services by switching station or OLE failures.

Figure 6: Fenced Compound Structure Mounted Outdoors
Switchgear |
Further "disentangling" of the switching stations from
the OLE will become necessary. In addition, a reduced need for
maintenance staff to be on or about the line will become a safety
imperative that must be built into the switching station design
process. The challenge to the designer is to contrive design concepts
that lower the asset owner costs whilst raising the efficiency
of their asset.
In pursuit of cost reduction and a higher level of efficiency
in power supply delivery systems, railway infrastructure companies
may consider it worthwhile and economically justifiable to agree
with the electricity supply industry to forward integrate the
railway switching stations with the electricity supply industry
interconnected system. This approach may benefit from the dominant
power of the electricity supply industry in the switchgear marketplace.
Alternatively, the electricity supply industry may choose to lease
the switching stations from key manufacturers and obtain guarantees
that ensure effective servicing of the switching stations.
Both approaches will stimulate the electricity supply industry
and the manufacturers to provide value-added solutions to the
switching station design problems, and allow railway authorities
to focus on the mechanical aspect of the OLE, which is far more
vulnerable to failure than the power supplies equipment. Finally,
another future switching station design type that is worthy of
research is the possibility of using mobile switching stations
as opposed to fixed-location stations.