| It was not possible to feature complete articles
on every major power project that PB is involved in or has completed
recently so, instead, we are presenting brief summaries of some
of these projects that help to illustrate our capabilities.

Rendering of 250-MW Peaking Plant in Wallingford,
Connecticut |
Wallingford Energy Project
The cleanest peaking power plant in the world is how this new 250-MW
plant will be known to many. It will be that and much more. The
Wallingford Energy Project will provide peaking power in a region
of Connecticut that the state governor identified as needing additional
peaking capacity. It will provide two new 115 kV transmission line
interconnects to the existing power grid and extensive upgrades
to Wallingford's switchyard. The peaking plant's new 115 kV substation
will be tied in with the town's substation in a ring bus arrangement
to provide a third 115 kV transmission line. This third line will
be available to bring power into the Wallingford substation in the
event of a regional blackout.
PB Power is responsible for the design of the Wallingford Energy
Project. Barton Mallow, our consortium partner, is responsible for
procurement and construction of the facility. The new power generation
equipment consists of five new aero-derivative combustion gas turbine
generators that will be fired on natural gas fuel only. Air pollution
control will be achieved by injecting water into the combustors
and by incorporating selective catalytic reduction on each of the
turbines to treat the exhaust gas. The combined effect will be to
reduce nitrous oxide emission levels to 2.5 parts per million or
less for each unit.
The project will be designed and landscaped to improve the view
of the facility from homes in the area. It will also include extensive
measures to reduce noise and to meet stringent state emissions requirements.
Operations at the facility are expected to begin in June 2001. Roger
Lemos and Jay Johnson are the Project Managers.

Under Construction Photo of Site at Orange, Texas |
Sabine 120 MW Cogeneration
Project
PB Power provided complete engineering and design
services for this turnkey, design/build 120-MW cogeneration plant
in Orange, Texas. The facility is intended to provide in excess
of 90 percent of Bayer Corporation Rubber Plant's electrical and
steam requirements. Excess power will be sold to the grid.
This highly efficient plant is comprised of two combustion turbine
generators, two heat recovery steam generators and one non-condensing
steam turbine generator. Its primary fuel is natural gas. Special
provisions were included in the design of this highly efficient
plant to handle the condensate that forms in the stack. Automatic
bypass control of the preheater and economizer provide optimum efficiency
under varying loads.
Poor soil conditions and limited space for equipment created challenges
for the design team. High groundwater and unstable soil made it
necessary to design wastewater lift stations to keep the waste sumps
and oil water separator as close to grade as possible. This approach
avoided the costs associated with sheet piles and groundwater pumps.
To deal with the limited space, we performed several maintenance
access studies to ensure that all the equipment could be removed
and maintained with readily available equipment.
We also incorporated a single-pedestal pipe support system in the
design that was similar to one we had developed for another project.
This system allows the pipe contractor to do most of the welding
at grade. Sixty-foot lengths of pipe can be lifted onto the rack
at one time because there are none of the vertical obstructions
that are typical of conventional pipe rack designs.
The project was completed in December 1999. The facility performs
well, providing a reliable supply of electricity and steam to Bayer
Corporation. Jay Johnson served as project manager.

The Sabiya Power Station in Kuwait is one of the world's
largest oil-fired plants. |
Sabiya Power Station
PB is serving as owner's engineer for the Kuwait Ministry
of Electricity and Water for one of the world's largest oil/gas-fired
plants-the 2,400-MW Sabiya Power Station. The facility will play
an important role in meeting Kuwait's rapidly increasing demand
for electricity.
We were responsible for performing studies, preparing specifications
and tender documents, adjudicating tenders, awarding contracts,
conducting detailed civil design and mechanical and electrical contract
design review, supervising civil engineering and building works,
installing M&E plant and equipment. We are now overseeing final
commissioning and testing.
The project commenced in 1988, was interrupted by the Gulf War in
1990, resumed in 1993, and is now in the final stages of completion.
The plant commenced operations in August 2000, with six of eight
300-MW units in operation. Full plant completion is anticipated
in the first quarter of 2001. Eric Burton was the original Project
Manager; the current Project Manager is Bill Weddell, who is resident
on site in Kuwait.
Improvement Study of the Operation of the
Greek Transmission System
PB Power is conducting a major, comprehensive study of Greece's
transmission system as a precursor to deregulation of the country's
electricity system. The aim of our study is to investigate all transmission
related areas and to recommend measures to enhance the system's
reliability, efficiency and security.
The interconnected power system of Greece covers the mainland and
some islands in the Ionian Sea. Thermal and hydropower plants are
connected to a 150 kV sub-transmission network and a 400 kV grid
that is interconnected with the neighbouring power networks of Albania,
Bulgaria and the former Yugoslavian Republic of Macedonia. This
network, together with the network in Romania and Yugoslav networks,
forms a separate synchronous grid.
The study includes a complete technical audit of the existing transmission
organisation and assets and a full review of operation and maintenance
procedures and staffing in order to assure that the system performance
will meet recognized international benchmarks. Fred Carr is the
Project Manager. |