Access to the shipping channel of the Ohio River must be maintained
during construction of the Owensboro Bridge. The cable-stayed spans
of the bridge were designed to be constructed by the balanced cantilever
segmental method, which ensures that ship traffic lanes will remain
clear and free of temporary construction supports.
The Balanced Cantilever Segmental Method
The construction sequence of the balanced cantilever method is as
follows:
- The tower is constructed.
- A centrally positioned superstructure segment is erected at
the tower and supported by temporary bracing in the area of the
towers.
- The remaining superstructure segments are then erected sequentially
on alternate sides of the tower until connection is made at the
approach pier and finally at midspan.
The dimensions of a typical segment for the Owensboro are the
full superstructure width by 13.7 meters in length. A typical segment
consists of a steel frame (two edge girder segments with cable connections,
three floorbeams, and a center beam) and deck (six precast concrete
panels and cast-in-place concrete closure strips placed between
deck panels and along the edge girders).

Figure 1: Typical Erection Cycle |
Modular Construction
Each superstructure segment is erected in the stages listed below.
Typical erection stages are shown in Figure 1.
- The steel frame is lifted into position by a barge-mounted
crane and field spliced to the edge girder of the previously installed
segment. It is allowed to cantilever freely.
- Two stay cables connecting the steel frame to the tower are
installed and tensioned to an initial length.
- The six precast deck panels are installed and the cast-in-place
concrete closure strips are placed between them and along the
edge girders of the previously installed segment.
- The two cables are tensioned to their final length, and the
procedure is repeated on the opposite side of the tower.
At least two-level tensioning of the cables is necessary in order
to control both erection and “locked-in” stresses in
the deck and edge girders.
Maintaining Balance And Stability
Maintaining a balanced and stable structure during construction
cannot be over emphasized. It becomes increasingly difficult to
do so as the cantilevered superstructure increases in length. To
reduce the bending moments in the tower that are caused by wind
loads and construction sequence imbalances, a temporary tiedown
is connected to the superstructure of the back span. In addition,
counterweights are strategically positioned and repositioned on
the deck in order to control stresses in the superstructure.
A 3-D computer model (see “Structural Analysis For The Owensboro
Bridge” by Fadi Hamawi and Ruchu Hsu) enabled us to:
- Confirm the constructibility of the structure
- Confirm the adequacy of the superstructure elements to resist
the forces induced during erection
- Determine the initial cable tensions.
Utilizing Expertise
The construction sequence was developed partly on the knowledge
gathered from studying other cable-stayed bridges in the U.S. and
from discussions with steel erectors who have cable-stayed bridge
experience. We also profited from the experience of many PB experts
in the field. |