Parsons Brinckerhoff
Worldwide LocationsContact PBLegal NoticeSite MapHome
 
MarketsServicesAbout UsPeople and CareersNews and EventsResearch LibraryProjects
PB Network Email This Page
Go To Other Issues | Contact PB Network | Print This Article 
<< Go To Previous Article | Table Of Contents | Go To Next Article >>
PB's Aviation Toolbox: Airport Planning, Design, Finance,Construction & Program Management, O&M
Winter 1995/96 • Issue No. 33 • Volume IX • Number 3
Construction and Program Management
New Orleans International Airport: Airport Design Management New Orleans Style
By Lino H. Neri, Jr., Metairie 504-830-0070
Good design management of the $650 million capital facilities improvement program at the New Orleans International Airport led to FAA approval for each individual project in only two weeks.


Figure 1: New Orleans International Airport

Effective design management starts a project off correctly. It assures the owner’s requirements are covered, provides an accurate projection of expected cost and conveys construction requirements clearly. PB’s activities in design management on airport programs have continually assured that individual projects will bid accurately and can proceed smoothly with a minimum of conflicts, requests for changes, delays and claims for damages.

As lead member of the Aviation Program Managers of Louisiana, one of our responsibilities was providing design management services for 70 projects of the New Orleans Aviation Board (NOAB) for the $650 million capital facilities improvement program at the New Orleans International Airport (Figure 1).

Responsibilities of Design Management Team

The design management team was responsible for providing oversight management and coordinating the design consultants who NOAB selected to prepare design documents for each of the projects of this important program. The team was comprised of a design manager and project engineers and architects who were supported by technical specialists on an as-needed basis. Our tasks included:

  • Project scope and criteria
  • Design oversight
  • Quality assurance
  • Design, maintainability and constructibility review
  • Value engineering
  • Design support during construction.

Project scope and criteria. Upon notice-to-proceed, we held initial meetings with each design consultant to review the project definition and scope of services, explain design directives that were to be followed and review the design schedule to identify check points and critical interfaces that had to be maintained. We provided each design consultant with:

  • Airport layout plan
  • CADD manual
  • Scheduling information
  • Accounting and reporting procedures
  • A review of the project scope of work and design criteria and standards and the appropriate Federal Aviation Administration (FAA) Advisory Circulars.

Design oversight. The design manager and a project architect or engineer acted as lead coordinators for a specific project or group of projects within their areas of specialty. Under this guidance, the design management team:

  • Reviewed the design consultant’s preparation of layout and conceptual drawings
  • Monitored the consultant contracts through preparation of the construction bid documents
  • Served as the focal point for all issues pertaining to the projects under their area of responsibility.

We visited the design consultant’s office on a regular basis to assure timely and proper performance. We provided
specific guidance and problem resolution support for this in-house effort and monitored compliance with the design contract, schedule and cost performance. These “on the board” reviews avoided our having to wait for the formal review submittal process to make corrections and/or adjustments to the designers work.

Quality assurance. The design management team developed a quality assurance (QA) system to verify that the design consultants maintained quality control while preparing their design documents. The QA system was based on assuring conformance to the FAA Advisory Circular, national and local codes and applicable regulations.


We firmly believe that
if you want it to happen,
you must state it clearly
in the contract documents!


Design, maintainability and constructibility review. We conducted design reviews at the 30 percent, 65 percent and 95 percent stages of design, making a significant review at the 30 percent stage to facilitate the 65 percent and 95 percent reviews and minimize design changes at these later stages.

Each review cycle included an evaluation of the proposed schedule for the contract. Long lead procurement items were identified and expected construction sequences and durations analyzed to determine whether the contract documents were adequate and reasonable. Work of other contractors, work authorizations, etc., were also reviewed. Requirements for special permits and environmental protection were checked and we compared all permits and licenses to ensure that the specifications and drawings met all terms and conditions.

Our reviews included a site inspection to verify existing site conditions and identify any obstructions, interferences or problems. Work areas, delivery access and site traffic flow routes were field-evaluated to assure that all functions would work according to plan.

During the design reviews we also addressed maintainability, working closely with NOIA’s maintenance department to evaluate maintainability of the facility itself and equipment that might become part of the facility. (See also “Airport Maintainability Reviews: A Value-Added Service” by Richard Coullahan.)

Design review is essential for the development of construction documents that are consistent with the criteria established. The documents must contain the essential technical requirements to permit construction of the project.

The design management team reviewed construction plans and specifications for each project to:
  • Identify potential problems (e.g., ambiguous requirements) that could impact the bid, construction or administration of the contract.
  • Ensure that each project design was coordinated with all parties who could be impacted by the work.

We performed a constructibility review with the construction team to eliminate or reduce the two most common sources of construction contractor change orders:

  • Defective plans and specifications
  • Unclear plans and specifications.

We firmly believe: If you want it to happen, state it clearly in the contract documents!

Value engineering. Value engineering services were provided during the design, maintainability and construction reviews. We analyzed type and kind of materials, equipment costs and method of construction to ascertain that each was the least costly and would ensure that the project criteria would be met.

FAA Approves Bid Documents

The design management team knew the FAA Southwest Regional Office submittal requirements for approval to advertise for construction contracts, and the procedures that must be followed before a construction contract can be advertised, awarded and notice-to-proceed given to the contractor. With this knowledge, we were able to submit 100 percent bid documents along with certification from the design consultant and the sponsor. In only two weeks, FAA gave permission to advertise based on the 100 percent bid document submittal. Some minor certification revisions were addressed in an addendum.

Through the end of 1995, we assisted the construction department on as as-needed basis during construction of the project.


<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Go To Other Issues | Contact PB Network | Print This Article 
Markets  |  Services  |  About Us  |  People + Careers  |  News + Events  |  Research Library  |  Projects
Worldwide Locations  |  Contact PB  |  Legal Notice  |  Site Map  |  Home
© Parsons Brinckerhoff