| By Ruchu Hsu, New York 212-465-5146, Roy
Eriksson, Tampa 813-207-2941, Scott Dean,
Tampa 813-207-2950, and Peter Wahl, New York 212-465-5232
|
| There were concerns that the asymmetry of the transverse cross-section
of the bridge could cause excessive torsion in the towers and that
torsional rotation in the towers might create difficulties during
construction. In addition, we had to examine whether the cantilever
portion of the main span deck should be erected concurrently with
or subsequent to the erection of the mainline. We performed a structural
analysis to address these two concerns specifically.
Torsion in Tower and Deck
The first order of business was to examine the layout of the cables
in the tower top. The cables on the east side of the main span,
which has the cantilevered ramp, are approximately twice the size
of the west side cables, carry double the loads and are designed
to be balanced by only a single back span cable. To minimize torsion
in the tower top, the cable anchorage points were strategically
shifted transversely, reducing the dead-load torsion in the tower
top to negligible levels. The tower top would still experience live
load torsion, however, and the tower legs would still be subject
to both dead and live load torsion.

Figure 1: Tower Rotation Due to Dead Load. |
Nonlinear dead load analyses alleviated concerns that torsion in
the tower will be problematic. It showed that the torsion can be
accommodated in the design with normal reinforcement. We also concluded
that the torsion in the tower due to the unsymmetrical cable forces
will not cause any practical concerns during construction.
The rotations in the tower for the hybrid alternative are very small
(Figure 1) and well within construction tolerances. Results for
the steel and concrete alternatives were similar. (LARSA was used
to analyze the steel and hybrid alternatives and GTSTRUDL was used
for the concrete alternative.)
Constructibility Issue: Erecting the Cantilevered
Ramp
We analyzed two sequences for erecting the cantilevered ramp:
- Concurrently with the main deck
- After the main deck erection is complete.
Ramp erected concurrently with main deck. The
computer model used for the nonlinear dead load analysis was modified
to analyze the north half of the structure just before closure at
mid span. Supports were added to cable connection points at the
deck level in the back span to simulate shoring during construction.
Superimposed dead loads were removed and cable self-weights were
reduced to account for the absence of grout.
The analysis showed vertical displacements of the east and west
sides of the deck at mid-main span to be about equal and the deck
remains essentially level. With the hybrid alternative, for example,
the west side deflected up 426 millimeters and the east side deflected
up 427 millimeters.
Ramp erected after main deck. The ramp structure
was deleted from the previous model to examine the behavior of the
structure without the ramp just before closure. Analysis of the
hybrid alternative showed that the mid-span deflection of the west
side will be up 483 millimeters and the east side will be up 717
millimeters.
Concurrent Construction Preferred
We concluded that concurrent construction of the cantilevered ramp
would be the preferred method of the two, although construction
could be done either way. Concurrent construction would allow for
more efficient use of equipment and provide better control over
stay forces and deflections. If the ramp is erected after the main
structure, the proximity of the existing locks will greatly reduce
the working space of the barge-mounted cranes required for erecting
the ramp structure. |