|
A large percentage of New Jersey
residents live in coastal and inter-coastal communities. Oftentimes,
the primary routes to and from these communities are over navigable
waterways spanned by movable bridges. The majority of these structures
are bascule bridges (single leaf or double leaf), although there
are also vertical lift and swing span structures. Typically constructed
50 to 70 years ago, many of these bridges have undergone significant
deterioration due to their age, the surrounding harsh marine environment,
heavy use of deicing salts during winter months, high traffic volumes
and numerous bridge openings.
The New Jersey Department of Transportation's (NJDOT's) inspection
program requires that each bridge receive a structural inspection
every two years and an in-depth mechanical/electrical inspection
every four years, including testing of the machinery and electrical
components. In between these four-year inspections, the movable
span's mechanical operation is given a cursory visual inspection
concurrent with the two-year structural inspection.
Common Problems
Our Princeton office has inspected and evaluated many of these bridges
in the past 20 years. During that time, we noticed a pattern of
similar problems at many of the movable bridges, including:
- Deterioration of the supporting superstructure
in the movable span(s) under an open grid deck
- Incremental movement of the approach spans
towards the movable span (particularly bascule spans), which can
affect functionality of the bearings, damage the end diaphragms
or floorbeams, and jam the deck joints
- Jamming of the bascule span in extreme hot
weather (particularly the side that is exposed to southern sun)
- Improper seating and inadequate locking at
the toe of the bascule span's live loading bearings
- Jamming of the center lock in double leaf
bascules
- Overstressing of the end floorbeams under
live loads.
In many instances, our inspectors
uncovered deficiencies that required immediate attention, so we
had to prepare emergency or high-priority repair details quickly-usually
within two to three days after the inspection. Often, the information
we needed was not available on plans, so it was critical that we
recognized the severity of defects in the field, understood the
reason for their occurrence, made the right judgment, and obtained
adequate information in the field for proposing the appropriate
solutions.
We take several factors into consideration when preparing repair
details:
- Simplicity of the details
- Adverse effects of adding weight to the bascule
span(s) where further balancing of the counterweight(s) is not
feasible
- Age of the bridge, its remaining service
life, and known previous rehabilitation or planned replacements
- Party responsible for performing the repairs (in-house maintenance
staff or outside contractors).
A few examples of the emergency/high
priority structural repairs that have been performed on several
New Jersey bridges are presented below.
Route 47 Over Grassy Sound
The steel expansion bearings in this multi-span bridge had tilted
excessively due to the movement of the superstructure into the bascule
span. An unusual feature was the inclination of the first pier from
the south toward the south abutment.
Late in 1990, a review of the construction plans determined that
this tilting was the result of the pier foundation having moved
away from the abutment. The south stub abutment is supported on
short piles that may have moved toward the span due to their inadequate
anchorage in a firm stratum. The fill supporting the abutment may
have slid and pushed over the adjacent pier's foundation, which
was built at the toe of the abutment fill.
Our recommendation was to take no corrective action because no change
had occurred in the tilt of the pier or the bearings for more than
a decade. The excessively tilted bearings were reset, however. The
bridge was rehabilitated in late 1998/early 1999.

Figure 1: Steel shim blocks prevent further loss of bearing
support area.

Figure 2: Spalled concrete pedestals |
Route
35 Over Shark River
One of the busiest movable bridges in New Jersey (handling a high
volume of both marine traffic and vehicular traffic), this single-leaf
bascule bridge showed excessive movements of the approach spans
and bearing top plates toward the bascule span (Figure 1). The bearings
consist of pinned op shoe elements sliding over bottom castings.
At the time of our inspection in the early 1980s, the top plate
had moved up to 150 mm (6 inches) toward the span with respect to
the bottom casting. Note that the approach span superstructure for
this bridge consists of a three-girder system. To prevent the top
casting from further loss of bearing support area and potential
of catastrophic failure, our repair scheme consisted of extending
the bottom casting by installing galvanized steel shim blocks on
the concrete pier cap under the excessively expanded top castings.
During our 1998 inspection, we discovered that the supporting concrete
pedestals under some of the excessively expanded bearings had spalled
off (Figure 2), resulting in the loss of the previously installed
shim blocks. Keeping in mind that the bridge was due for replacement
in the near future, we proposed building steel column sections with
welded cap plates at their tops to support the overhanging top bearing
plates. These columns were attached to the pier columns with drilled
and grouted anchor bolts.
Route 70 Over Manasquan River
This double leaf bascule bridge had a history of jamming in hot
summer weather. Our 1985 inspection uncovered severe deterioration
of one of the support piers. Repeated tidal flows, differential
settlement of foundations and abnormal movements of the approach
spans had all contributed to the deterioration of this lightly reinforced
concrete pier. These effects resulted in wide through full-height
vertical and diagonal cracks in the pier wall and severe erosion
of the concrete at each nose. Our team informed the state immediately
of a potential emergency situation and prepared the required repair
plans in three days (over a weekend).

Figure 3: Galvanized steel sections used to strengthen disintegrating
concrete. |
Galvanized steel plates that were
to be left in place were bolted to the remaining portions of the
pier, including the noses at each end, and repair concrete was pumped
into the form work. Galvanized channel sections were strapped around
the steel plates and pulled together at each nose to contain the
concrete unit (Figure 3). Prior to the installation of the forms:
- All medium to wide cracks were pressure injected
with epoxy resin.
- Low viscosity epoxy resin was used in some
wider cracks, filling them by gravity flow.
- Long anchor rods were installed as stitches between separated
concrete portions to hold them together.
After 14 years, the repaired pier
has not deteriorated further and is still functioning.
Route 50 Over Tuckahoe River
This single leaf bascule bridge also had a history of jamming in
hot weather. The NJDOT had cut off portions of the bascule span's
end floor beam flanges in an attempt to alleviate the problem. Our
inspection of the bridge determined that this was not a desirable
solution because of the reduced flange section, even though the
structural capacity of the end floor beam was not yet compromised.
Our repair details included removal and reconstruction of the deck
joint because the existing steel finger-type joint had been cut
back significantly over the years. Next, the span lock bar castings
were removed and reset to accommodate the reconfigured deck joint
and anticipated movements. These repairs were performed about eight
years ago. No jamming problems have been reported since.

Figure 4: Corrosion of the supporting members. |
Route
30 Over Beach Thorofare, Route 35 Over Cheesequake Creek, and Route
130 Over Raccoon Creek
The Route 30 and Route 35 bridges are bascule; the Route 130 structure
is a vertical lift bridge. All three have open grating decks on
the movable spans. The grating is typically supported by steel purlins
spanning longitudinal stringers that, in turn, are supported by
floor beams that are framed into girders. The open grating deck
allows roadway dirt and debris to accumulate on the supporting members,
causing unabated corrosion (Figure 4). The common deterioration
in each of these movable spans was extensive corrosion of the deck
purlins and stringers, with large areas of holed-through webs and/or
flanges.
In recommending appropriate repair measures, a nagging problem was
whether the weight of the repair material would affect the span
balance. On the bascule bridges, there was not a lot of room in
the concrete counterweights for placing additional steel billets.
After evaluating the additional steel weight required for the repairs
along with their moment arm effects on the counterweight trunnion,
it was clear that a significant portion of the existing deteriorated
steel had to be removed to reduce the overall weight and resultant
force on the trunnion shafts. After installing new elements, the
old ones had to be cut out and removed.
All work was accomplished from underneath the spans while traffic
continued to flow across these heavily traveled bridges. The new
purlins had to be slightly shallower than the existing ones so that
they could be threaded through the space between the existing purlins
and the grating. The new purlins were then shimmed up and bolted
to the top flanges of stringers. Repair plates and angles were bolted
directly onto the deteriorated stringers.

Figure 5: Steel columns cracked at there bases. |
Route
49 Over Salem River
This single leaf bascule bridge does not operate currently, except
for regularly scheduled test openings for the Coast Guard. During
our 1983 inspection, divers uncovered severe undermining at one
of the approach span piers. The scour, which was caused by the very
fast flow (4.5 m/sec or 15 feet/second), was so significant that
they could walk underneath the pier through the timber piles. [Ed.
note: For more information about scour on movable bridges, see "In-depth
Scour Evaluations of Three Movable Bridges" by Tom Anella,
Rama Krishnagiri and Tim Stanford.]
We proposed driving permanent steel sheet piling around the pier
and pouring a tremie seal concrete to fill the void. Riprap was
added to the outside of the permanent sheeting to prevent scouring
at the sheet piles. To install the sheeting, the contractor removed
portions of deck slab, drove the sheeting through the superstructure,
and then reconstructed the deck slab.
Years later, during another inspection cycle, we found that the
steel columns that support the approach span girders adjacent to
the bascule span were cracked at their bases (Figure 5). This cracking
was attributed to the movements of the approach spans toward the
bascule span. Such movement in bascule bridges tends to be due to
a longitudinal discontinuity of the superstructure, frequent opening
of the movable span, longitudinal forces generated by traffic and
lateral earth pressures behind the abutments.
Emergency repair details were developed after our analysis indicated
that the cracked columns could support only the dead loads. The
repair details consisted of tee-sections bolted onto the support
columns to transfer the live loads and dead loads to the substructure
supporting these columns.
Route 52 over Beach Thorofare
This single leaf bascule bridge had jamming problems at the toe
of the main span. Several deck joints on the approach spans had
also completely closed up. As an interim rehabilitation measure,
we developed details to remove part of the concrete end diaphragms
at the approach spans and reconstruct the deck joints.
More Inspections Planned
We have seven bridge inspection contracts with the NJDOT currently.
One of them is a two-cycle contract to inspect seven complex/movable
bridges. This upcoming inspection (at the time of writing) in April/May
2000 should prove to be interesting, particularly at the bridges
we flagged during the last cycle for high priority repairs.
|