Parsons Brinckerhoff
Worldwide LocationsContact PBLegal NoticeSite MapHome
PB Websites search Advanced Search
MarketsServicesAbout UsPeople and CareersNews and EventsResearch LibraryProjects
PB Network Email This Page
Go To Other Issues | Contact PB Network | Print This Article 
<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Making Better Communities Through Contextual Infrastructure Planning
March 2001 • Issue No. 49 • Volume XVI • Number 1
Contextual Infrastructure Planning and Design
Blending Complex Engineering Challenges and Aesthetics into Community-Friendly Solutions
By Joan Witt, Tempe, Arizona 1-480-966-8295, witt@pbworld.com
The design that our team developed for a segment of Pima Freeway addressed complex engineering challenges and community concerns, and it allowed construction to be completed ahead of schedule.


Figure 1: Shea Boulevard Single-Point Urban Interchange

Figure 2: Pedestrian and Bike Path
The Arizona Department of Transportation selected PB to design the first segment of Pima Freeway to be built within the City of Scottsdale. The residents feared the impacts from construction and they wanted the freeway to serve as an attractive gateway to their City. The project was under tight public scrutiny. Our design team had to address both community concerns regarding aesthetics and noise as well as many engineering challenges.

We were responsible for the fast-track design of:
  • 2.4 km (1.5 miles) of depressed, access-controlled freeway that consists of:
    - Six general-purpose lanes
    - Two auxiliary lanes
    - One single-point urban interchange (SPUI) at Shea Boulevard- a two-span, cast-in-place, post-tensioned concrete box girder bridge (Figure 1)
  • Three grade-separated structures and a pedestrian and bike pathway (Figure 2)
  • Onsite and offsite drainage systems
  • Retaining and sound walls
  • Signing, striping and lighting
  • Traffic control plans.
The project constraints included high traffic volumes in the construction corridor, numerous utility lines and limited right-of-way.

Creative Solutions

As described below, we combined "top down" construction techniques with innovative design concepts to improve the technical design and minimize traffic impacts, and we used architectural treatments to enhance the aesthetics in the corridor and gain public acceptance. Our team also worked in concert with the neighborhoods and nearby businesses to incorporate community-friendly elements, such as pedestrian and bike paths (Figure 2).

Top Down Construction. By using the top down viaduct construction technique in our bridge design for the Shea Boulevard SPUI, we minimized traffic delays and risks to the public. The central part of the structure was constructed first, with traffic detoured around the construction area. We designed the high abutment required for this bridge so it could be constructed at ground level without major excavation. After abutment and pier construction, the superstructure was formed on the existing ground and concrete was placed. After the superstructure post-tensioning was complete, partial excavation under the bridge allowed access to the drilled shafts for tie-back operations. Subsequently, traffic was placed on the completed deck and the exterior ramp connectors were constructed and attached to the new bridge.

Although the top down concept for building viaducts is not new, using this technique was one of the keys to completing the project safely and quickly, and with the least impact to traffic.


Figure 3: Innovative Culvert/Retaining Wall System


Figure 4: Two Examples of Architectural and Artistic Treatments (Decorative Handrails as well as Lizard and Plant Designs Incorporated into the Bridge and Walls)

Culvert/Retaining Wall System. Another challenge our design team faced was accommodating all of the following elements within a very restricted right-of-way:
  • Travel lanes
  • Retaining walls
  • Shoulders
  • Sound walls
  • The utility corridor
  • A pedestrian and bike path
  • A 3-m by 4-m (10-foot by 12-foot ) box culvert.
To address this challenge, we developed a combination box culvert and retaining wall system (Figure 3) that saved space while incorporating the required engineering elements and aesthetic enhancements. The retaining wall system resists all external forces and carries stormwater while remaining within the restricted right-of-way. Our structural team designed the wall system to include a box culvert above a retaining wall as well as a 2-m (6-foot) extension to the exterior face of the box culvert to act as an additional retaining wall. In some locations, the total height of the wall system is 10 m (33 feet).

Detour. The corridor's high traffic volumes and tight right-of-way required creative solutions to construction challenges. To reduce construction impacts to the surrounding neighborhoods and businesses and to shorten the construction schedule, we developed a detour concept to move the existing traffic out of the construction corridor. With no traffic in the construction zone, one portion of the construction was completed six months early.

Aesthetic Treatments. Our team worked with homeowners' associations to incorporate their requests for privacy walls, landscaping, access, lighting and pedestrian and bike paths. With the freeway being the gateway to the Scottsdale, the city officials wanted the facility to make a strong artistic statement. We worked closely with city staff and their architectural treatment consultant to incorporate southwestern design elements into the retaining wall system, other walls, bridge piers and abutments (Figure 4), and to coordinate these treatments with the neighborhoods. Our team also developed new concrete form liner materials and worked with the City's artist to develop constructible architectural treatments to enhance the freeway and the pedestrian and bike paths.

Project Exceeds Expectations

Working together with the Arizona Department of Transportation, the City of Scottsdale and its architectural consultant, business owners, and residents, we developed a vital transportation facility that was based on sound engineering practices blended with aesthetics and community-friendly elements. Our efforts exceeded ADOT's expectations by providing cost-effective solutions that were completed within the construction cost estimate and by facilitating the construction process, which resulted in the project being completed 30 days early.

Our team also met the expectations of the City of Scottsdale by creating a freeway with a unique appearance that serves as an attractive gateway to Scottsdale. The Arizona Department of Transportation, the City of Scottsdale, residents and businesses are all enjoying the benefits of this truly successful project. In October 2000, this project won an Outstanding Award for Engineering Excellence from the Arizona Consulting Engineers Association.

Joan Witt, a Business Development Associate with 15 years of experience in sales and marketing, is a marketing coordinator with PB's southwest district.
<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Go To Other Issues | Contact PB Network | Print This Article 
Markets  |  Services  |  About Us  |  People + Careers  |  News + Events  |  Research Library  |  Projects
Worldwide Locations  |  Contact PB  |  Legal Notice  |  Site Map  |  Home
© Parsons Brinckerhoff