Parsons Brinckerhoff
Worldwide LocationsContact PBLegal NoticeSite MapHome
PB Websites search Advanced Search
MarketsServicesAbout UsPeople and CareersNews and EventsResearch LibraryProjects
PB Network Email This Page
Go To Other Issues | Contact PB Network | Print This Article 
<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Making Better Communities Through Contextual Infrastructure Planning
March 2001 • Issue No. 49 • Volume XVI • Number 1
Networking
PB's Other Face
By Judith Kunoff, New York, New York 1-212-791-9346, kunoff@pbworld.com
Our team met a variety of distinct challenges on four projects within one building. The results were an historic, architecturally detailed interior being revived in a modern context.

PB's predominance in the areas of infrastructure design and construction management is familiar to all of us. Perhaps lesser known is our influence on architecture. In the case of the U.S. Courthouse at Foley Square in New York City, for example, our architectural influence resulted in a newly renovated courtroom that has been toasted by the U.S. Court of Appeals.

Our challenges on this project included:
  • Working with a limited low budget
  • Meeting modern technological needs without disturbing the historic quality of the space
  • Responding to a many-faceted client whose needs and priorities were not always aligned
  • Following State Historic Preservation Office regulations for National Historic Landmark Buildings while changing the use of a courtroom.
In our role as construction quality manager, we worked hand in hand with several entities to produce a state-of-the-art courtroom in an historical landmark building. These included a many-facetted client-General Services Administration (GSA) Property Development Division, the property administrator; GSA Building Management Division, the property manager; and the U.S. Court of Appeals-the end user, Perkins Eastman Architects and the designer, Cosentini Engineers.


Figure 1: Historic detailed ceilings were double high and constructed to the underside of beams
Budgetary Constraints

At the onset, GSA's Property Development Division requested funding from the U.S. Senate to renovate and upgrade spaces and services for the entire courthouse building, but the Senate was unable to fund this large project. Each of the tenants at Foley Square funded smaller priority projects throughout the building. As such, a limited budget was allocated for each of our four projects, which were:

  • Renovating and changing the use of an existing large district courtroom to house the Appellate Court for the U.S. Court of Appeals, Second Circuit, and renovating three small district courtrooms to house the chambers of three appellate judges and their staffs-a project funded by the U.S. Court of Appeals, Second Circuit.
  • Upgrading the entire electrical feed and fire alarm throughout the building-funded by the U.S. Senate through the GSA Property Development Division.
  • Renovating existing office space to house chambers for three additional appellate court judges and their staffs-funded by the U.S. Court of Appeals, Second Circuit.
  • Repairing the exterior facade-funded by the GSA Project Management Division.

Figure 2: This door tran-som houses some of the new audio-visual equip-ment
These tight budgets resulted in a tight construction/quality control budget as well. Although our services were limited by hours, however, our team showed great eagerness and made a strong effort to produce a quality project. As a result, GSA and the varied clients were fully satisfied and we exceeded our proposed margin.

Preserving Historical Features While Meeting Modern Needs

Older buildings provide a challenging construction environment and the U.S. Courthouse, designed by Cass Gilbert in the 1930s, was no exception. For example:
  • Historic, detailed ceilings in courtrooms and public corridors (Figure 1) are double high and were constructed to the
    underside of beams. These features do not allow for the simple installation of electrical, plumbing and mechanical systems.
  • Access panels were not installed in the original construction of the historical ceilings, making it quite challenging to access the existing wiring above.
  • The original wood veneer panels that faced the walls of the courtroom were put together in place originally without facing nails, so it would have been prohibitively expensive to remove these panels to install infrastructure and then reinstall them.
The contract required that a number of fairly advanced technological systems be installed and that the historical details original to the courtroom be maintained. We were not able to gain access behind panels or the chase across the historic ceiling, so we used creative routing and the skills of talented painters to hide the many boxes and wires required to house an audio-visual system that allowed for closed circuit broadcasting of sessions (Figure 2). These same techniques were used to hide an advanced security monitoring system from the eyes of the day-to-day users.


Figure 3: Placement of the emergency flood lighting convays a sense of design
Protecting the historic architectural aesthetic of this courtroom did prove to be almost too much of a challenge at times, as in the case of battery supported emergency floodlighting required by code. The budget dictated the use of a most imposing fixture that could not be obscured. Our team's solution was to make sure that the placement of these obvious fixtures was chosen according to the architectural aesthetics used throughout the project. We placed these fixtures on center of the pilasters just below crown molding. This placement did not obscure the fixtures, but it did convey a sense of design (Figure 3).

The challenges of meeting all of the client's modern technological needs while protecting the architectural and historical aesthetic remained a goal to the entire design and construction team, and we made sure that they were achieved within the budgetary, schedule and political constraints that defined this project.

Satisfying a Many-Faceted Client

Aesthetics is a subjective term. When the client is many facetted as ours was-the U.S. Court of Appeals, Second Circuit; GSA Property Development Division and GSA Property Management Division- opinions on the desired aesthetic can be varied. We rallied to align all representations of "the client" to the same aesthetic goals.

At times, this challenge appeared to be the greatest challenge of all. Visiting case studies, viewing and reviewing mock-ups, and persevering in discussion brought about a vision that was not only accepted by this "client," but that became the example to be followed. Subsequent to the completion of the renovation of this courtroom, the Second Circuit Court of Appeals chose to renovate the 17th floor courtroom to meet the standard we had achieved on the 15th floor.


Figure 4: This view toward the back of the courtroom shows the main entry that was added in the rear, and the hi-tech controls on the clerk's bench in the foreground
Meeting Regulations

Although not a client, the State Historic Preservation Office regulates design and construction within National Historic Landmark Buildings, so it also directed the aesthetic achieved in the 15th floor courtroom project. Many decisions had to be brought before this body for approval, particularly during the design phase.

The design team reviewed the basic requirement to alter an existing District Courtroom (used for litigation trials by jury)
to an Appellate Courtroom (used for presenting appeals) and determined that the following changes were needed:
  • The jury bench had to be removed and incorporated into a judges' panel bench.
  • The flow of traffic into and out of the courtroom would change completely, so certain doors had to be removed and new doors installed in existing walls.
  • The spectator seating had to be reconfigured.
SHPO needed to decide whether these changes, which clearly would alter the original design and design intent, should be allowed. Would these changes cause an irreversible change and prevent protection of the historic quality and nature of this building? SHPO determined that these design changes would be acceptable, assuming the grandeur and the details defining that grandeur were protected and remained intact. The resulting renovation (Figure 4) has become the toast of the United States Court of Appeals.

Teamwork Was the Key

The solution used over and over again to resolve the challenges that we faced and achieve a grand architectural aesthetic was teamwork. We orchestrated the players in such a fashion so as to encourage all of them to express their opinions, share their knowledge and acknowledge and appreciate each others' strengths and weaknesses. The balance and harmony apparent upon entering the courtroom is the direct result of this orchestration.

Judy Kunoff has been with PB since early 1997. A licensed architect, she is Project Manager on several construction quality management projects, including the U.S. Courthouse project.
<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Go To Other Issues | Contact PB Network | Print This Article 
Markets  |  Services  |  About Us  |  People + Careers  |  News + Events  |  Research Library  |  Projects
Worldwide Locations  |  Contact PB  |  Legal Notice  |  Site Map  |  Home
© Parsons Brinckerhoff