|
West Rail Phase I, the largest infrastructure
project currently underway in Hong Kong, is a 30.5-km (18.5-mile)
long domestic twin-track passenger railway that links South West
Kowloon with the North West New Territories. PB was commissioned
by Kowloon Canton Railway Corporation (KCRC) in March 1998 to
prepare detailed design documents and provide design coordination
and site supervision services required for construction of three
of the major West Rail Phase I facilities:
-
The Pat Heung Maintenance
Centre
-
The West Rail (Headquarters)
Building
-
The Kam Sheung Road
Station (one of the project's nine stations).
In the planned Phase II, the Kam Sheung
Road Station will be one of the major stations with interchange
(intermodal) platforms. It is also one of the five "line"
stations identified as "emergency termini" that need
to be capable of continued operation in the event of an incident
causing an adjacent line segment to either close one line or close
completely. For this reason, we designed the associated public
transport interchange (intermodal platform) specially to meet
the requirements of handling passengers during various emergency
scenarios.
Basic Design of the Public Transport
Interchange
Situated in the rural country areas of Kam Tin and Pat Heung,
Kam Sheung Road Station is above ground on a viaduct with the
concourse at grade and the platform at viaduct level. Parking
facilities and loading/unloading areas are located to the west
of the station while the public transport interchange is located
to the east. Bicycle parking is also located within the public
transport interchange. New access roads that link the station
with nearby trunk roads are being built as part of the project
to cope with the potential increase in traffic flow in the area
after West Rail opens.
Our design of the intermodal facilities was based on patronage
analyses, particularly the AM and PM peak hour patronage. We then
analysed the overall patronage further to determine the share
of these patrons amongst the different modes of access-walking,
bus, minibus, feeder bus, other bus, taxi and car.
Based on our analysis results, we recommended the following facilities
to ensure that the public transport interchange would provide
for quick and convenient interchange between rail and the other
transport modes:
-
Bus terminus capable
of accommodating five terminating routes and two passing routes
-
Public light bus terminus
capable of serving seven different routes
-
Private bus/coach lay-by
-
Urban taxi stand
-
Rural taxi stand
-
Kiss-and-ride facility
-
Facilities for ancillary
uses, such as operator's office and public toilets
-
Cycle park
-
Automobile park (discussed
below in more detail)
-
Pedestrian crossings
with clearly defined routes
-
Access route for emergency
vehicles.
We proposed an automobile park (parking
facility) located immediately west of Kam Sheung Road Station.
The size of this facility depends on several factors, however,
such as parking cost, need for car, car availability factors,
value of time, etc. We suggested a normal interlocking layout
at a parking angle of 90 degrees. The dimensions of the parking
stalls were the standard 2.5 m x 5.0 m (8.25 feet x 16.5 feet)
and the lot was divided into sub-areas by an internal road circulation
network of one-way roadways to reduce vehicular conflict as far
as possible. This facility is shown on Figure 1, which illustrates
the entire passenger transport facility.
Design for Passenger Transfer
During Abnormal/Emergency Conditions

Figure 1: Passenger
Transport Interchange |
In designing Kam Sheung Road Station
as an emergency terminus, we examined four possible scenarios.
For each scenario we assessed the capacity of the station, including
the public transport interchange, in relation to the following
considerations:
-
Platform and Concourse
Capacity. Capacity assessments were conducted for station
platform and vertical and concourse circulation elements.
-
Emergency Road Transport
Provision. We examined the maximum demand for emergency
road transport provisions to carry passengers to other stations.
This demand was compared with the supply of road transport and
constraints were identified to highlight the situation when
the abnormal operation arrangement of the railway has to be
altered.
-
Areas for Queuing
Passengers and Bus Loading Points. Adequate space was provided
to accommodate the requirements as identified in the analyses.
-
Bus Loading Points.
The number of bus loading points for passengers awaiting onward
transfer to other stations was identified for use in various
combinations.
-
Crowd Control.
Actual emergency termini scenarios could cause significant crowd
control problems, particularly if the scenario were to occur
on a very hot or wet day, so we evaluated the sizes of crowds
during these conditions to ensure that the layout of the public
transport interchange would be adequate.
The results of our analyses demonstrated
that we had designed the Kam Sheung Road Station and its associated
public transport interchange to handle normal and emergency conditions.
The design of station and the associated intermodal facilities
has been completed and these facilities are now under construction.
|
| More
details about this project can be found in the following Web site:http://www.kcrc.com
br>
Louis Lee is a railway system engineer. He is now the project manager
of the detailed design of Kam Sheung Road Station and is the division
manager of the Rail Systems Division in PBA, Hong Kong.
[Ed. note: To read about work PB completed on another project or
KCRC, the rolling stock maintenance facilities at Ho Tung Lau, see
"Kowloon Canton Railway Corporation Maintenance Center"
by C. A. Gaskin in PB Network Issue No. 30, Winter (4th quarter)
1994/95.]
|