|
The Olympic and Paralympic Games present enormous transport challenges
to host cities. In addition to maintaining the existing transport
demand, the games require the separate movement of athletes, officials,
media, Olympic family members, sponsors, workforce and spectators,
as was the case with the Olympic Games of 2000 in Sydney.
Overview of the Transport Plan
Sydney Olympic Park (SOP) was the focal point of the 2000
Games. Located 20 km (12 miles) to the west of Sydney's central
business district, SOP incorporated the Athletes' Village and
twelve venues, including the Olympic Stadium. The close proximity
of the Athletes' Village to many venues certainly simplified the
critical task of athletes' transport--not so, however, for all
other client groups, such as officials, media and Olympic family
members, who were accommodated in areas outside SOP.
In terms of the magnitude of demand, spectators were the largest
single client group. SOP had a ticketed capacity for 200,000 spectators
on peak days. With multiple sporting sessions being held each
day, however, total on-site crowds of around 400,000 people were
expected. It was clear from early in the planning process that
realistically, the magnitude of spectator transport to SOP could
be met only with a very high use of public transport.
Rail access to the site was achieved through use of an existing
rail corridor and construction of a high-capacity rail station
that was capable of moving 40,000 to 50,000 passengers per hour.
Rail services were supplemented by the operation of regional bus
services that provided direct services to SOP on about ten different
routes from parts of Sydney that had poor access to rail.
The operation of regional bus services for the two-year period
leading into the Olympic Games consolidated bus routes and operations.
As part of the strategy to educate the public about using public
transport to travel to SOP, the regional bus services were operated
for major events prior to the Olympics, including three annual
Royal Easter Shows that attract around 1 million visitors over
a two-week period.
A challenge remained for the Olympics, however--constructing two
bus terminals with sufficient capacity for Olympic Games demand.
Transport planners and engineers from PPK Environment & Infrastructure,
the Sydney-based company that joined PB in March 2000, worked
with the Olympic Coordination Authority on the planning and design
of this effort.
The layout of SOP was designed with a view to the long term, post-Olympic
environment. Transport terminals, including the rail station,
bus terminals and most car parks, were located inside the venue
core area to maximize the access to the regular events. The two
permanent bus terminals, in particular, were located close to
the center of the site. Each was capable of moving 8,000 people
an hour.
For the Olympics, however, the required capacity for each bus
terminal was in the range of 15,000 to 20,000 people per hour.
In addition, because the permanent bus terminals were located
on what was to be the main pedestrian boulevard for the Olympics,
the sheer volume of pedestrians expected during peak times meant
that new locations had to be found for the Olympic period. The
net result was two new, temporary terminals, called the Northgate
and Southgate Bus Terminals.
In addition to designing these terminals, we also prepared designs
for 13 other bus/rail interchanges across the city to serve other
venues. Some of these experienced intense periods of demand. The
interchanges serving the equestrian venue, for example, had to
cater to crowds that could reach about 50,000 spectators on the
two busiest days. All these people had to be shuttled by bus from
rail and remote car parks.
Design of Two High-Capacity Bus Terminals
The Northgate Bus Terminal was intended to be the busiest
of the two terminals. Our challenge was to convert an existing
car park and access road into an Olympic-size bus terminal capable
of servicing five regional bus routes and other shuttle buses.
Identifying Design Requirements. The following design
requirements were identified early on:
-
Target capacity of 15,000
arriving and 20,000 departing passengers per hour-numbers that
equate to 300 and 400 buses per hour respectively in the peak
arrival and departure periods
-
Ability to handle cross-over
periods with high levels of both arriving and departing passengers
-
Complete separation of vehicle
and pedestrian movements
-
Separation of arriving and
departing passengers for security and capacity reasons
-
Flexible allocation of bus
stands to different bus routes
-
Sufficient area to hold (layover)
about 400 buses prior to peak departure period
-
Minimization of conflicts
between bus movements
-
Separate facility for set
down and pick up of disabled spectators.
Although some indication of demand by bus route was developed
from preceding SOP events, we faced considerable uncertainty regarding
Olympic demand. For example:
-
How many spectators would
come by bus versus rail?
-
Where would bus passengers
come from, that is, which routes would they use?
-
What time of day would they
travel to SOP?
-
How long would they be on-site
before and after their ticketed event?
-
How many non-ticketed spectators
would arrive?
Despite the best efforts of planners to construct a reliable,
detailed demand model, there was clearly a need to incorporate
flexibility into the bus terminal design. In particular, we knew
that bus stands might need to be reallocated across bus routes
as the knowledge of demand per route increased.

Figure 1: Olympic Overlay and Operational Patterns of Northgate
Terminal |

Figure 2: Three bus lanes allowed buses to keep moving under
peak conditions. |
General Layout. Figure 1 shows the general layout of the
Northgate Bus Terminal overlaid on the existing car park. Three
pods were serviced by a perimeter road. The central road, in non-Olympic
use, was a bus only access road into the site. The three pods
of the car park were used for spectator set down, spectator pick
up, and bus layover. The movement of buses between these three
areas made use of the perimeter road. The central road was converted
to pedestrian access to SOP. Thus, the terminal operated with
no conflict between different bus movements and no at-grade crossing
of buses and pedestrians.
Arriving passengers were set down on the curb of the perimeter
road. Spectators then passed through a security check area before
accessing the site while buses moved to the layover area. Set-down
operations were simpler than pick up operations because there
was no need to allocate stands to individual routes.
The most intense area for the terminal was the passenger pickup
area. In the concept design, pick up stands were organized into
a series of peninsulas. Spectators moved into the peninsulas from
the central access road while buses moved into the stands directly
from the layover area. Departing buses left via the north end
of the terminal.
Maximizing Throughput. To maximize the throughput of buses,
it was important that buses set down and picked up passengers
in groups of three buses or more. For example, on the pickup side,
a route may be allocated three stands within a single rank. In
such cases, during peak departure periods three buses would move
together from the layover area to the pick up stands. The three
buses would load passengers simultaneously and move off together,
even if all buses were not full. Soon after this group of buses
departed the next group arrived. Adopting this procedure enabled
stands to be located close together, thereby increasing usage
of curb space.
We estimated that a group of buses could arrive at a stand, load
passengers and depart in 3.5 minutes. With an assumed average
bus loading of 50 passengers, the nominal departure capacity was
850 passengers per stand per hour. To deliver an overall departure
capacity of 20,000 passengers per hour, at least 24 stands were
required.
Another challenge was to convince people that three lanes were
required within both the set down and pick up areas to maximize
throughput and prevent blockages. Figure 2 illustrates why three
lanes were required.
The Conversion Works. Converting the original car park
to a bus terminal required the following general works:
-
Internal road widening and
creation of new access points
-
Additional pavement overlay
for areas with expected high volume of turning buses
-
Construction of temporary
set down and pick up stands to achieve a required curb height
of 300 mm (12 inches) for bus loading and unloading
-
Construction of pedestrian
access paths through the car park
-
Additional lighting
-
Pedestrian and vehicle signage
-
Bus driver facilities.
A Great Success
The operation of the actual bus routes through regional
Sydney for the Games was a great success due largely to the experience
gained in running the services for previous events. The need for
high staff levels to manage the passenger pick up stands was highlighted
a supervisor was required for each rank to ensure that buses pulled
into the appropriate location and to indicate when buses were
to move off. Additional staff members were required at each bus
stand to safely load passengers and hold them back if the bus
was full.
During the actual Games period, however, some operational difficulties
arose at the Northgate Terminal that had to be overcome. In particular,
bus staff had not been not trained adequately in the operation
of the terminal before the commencement of the Olympics, and it
took a number of days before actual operations reflected the principles
that we had designed for. Fortunately, the first week of the Games,
before the athletics commence, is traditionally a period of only
moderate spectator demand.
Overall, the Olympic bus terminal designs proved successful. They
made good use of existing infrastructure with substantial temporary
overlay. Efficient operation of the terminal arose from intensive
management of both buses and passengers, and the cooperation and
goodwill of the public.
|