|
Development of an intermodal freight terminal at the Pilgrim
site would be a major investment for the public sector, the terminal
operator, and the rail and motor carriers serving the terminal.
The project must generate a profit for the carriers and operators.
It must reduce transportation costs and improve service for shippers,
receivers and third-party logistics brokers. It must meet the
economic development plans and investment budgets of state and
local agencies; and it must deliver broad public benefits, such
as improved freight productivity, lower traffic congestion, reduced
air pollution and lower consumer prices. We performed a formal
benefit-cost analysis to determine if the facility would meet
these requirements and to support decision making for the Pilgrim
State intermodal site.
Benefit-Cost Comparative Analyses
We conducted comparative analyses for each of three investment
scenarios to determine the incremental improvements in benefit-cost
results as higher levels of market demand are accommodated with
increased levels of investment. Increased investment is of two
types:
-
Direct investments required
to equip and operate the Pilgrim intermodal terminal itself
-
The much greater joint investments
required for greater railway clearances on the Long Island Rail
Road (LIRR) and the rail freight lines along the Hudson River,
improvements to trans-Hudson float operations and, ultimately,
construction of the proposed tunnel across the New York Harbor.
The railroad linehaul improvements would allow for trailer-on-flatcar
TOFC)/container-on-flatcar (COFC) and, ultimately, double-stack-train
service (DST), while improved float operations and the cross-harbor
tunnel would result in more efficient and direct cross-harbor
freight movement.
The following investment scenarios were compared:
-
Scenario 1: LIRR and
Hudson with TOFC/COFC; TOFC/COFC Float. Prior to 2010, the
intermodal terminal would operate initially as a bulk terminal.
LIRR and Hudson Line capacity improvements would be made by
2010 to accommodate TOFC/COFC. Containers would be moved across
the Hudson River via an enhanced float operation and via Selkirk,
the only existing trans-Hudson rail crossing south of Albany.
To accommodate the containers, increased capital investments
at the Pilgrim intermodal terminal would be required just before
or during 2010.
-
Scenario 2: LIRR, Hudson
with DST; TOFC/COFC Float. Same as Scenario 1 but with additional
improvements after 2010 to accommodate DST. Containers would
continue to move across the Hudson River via an enhanced float
operation and via Selkirk.
-
Scenario 3: LIRR, Hudson
with DST; DST Tunnel. Same as Scenario 2 but with additional
improvements by 2020 to accommodate containers moving across
the Hudson River via a newly constructed cross-harbor tunnel.
This scenario represents the maximum, and possibly optimal,
expansion path for movement of containers to and from Long Island
via the Pilgrim intermodal terminal.
Estimation of Benefits
Focus on Travel Benefits.
While benefits of the intermodal facility would extend to many
arenas of economic and business activity, the benefit-cost analysis
focused on travel impacts; that is, benefits from direct and faster
freight transport and, equally important, the impacts on all motorists
resulting from reduced levels of highway congestion as large numbers
of trucks were removed from the system. These travel impacts would
be of two types:
-
Diverting long-haul truck
trips to rail. This market includes commodity types that are
currently moving into and out of central Long Island by truck,
but with origins and destinations that are sufficiently distant
from central Long Island to make it economically and operationally
attractive for a shipper to use rail if such service were available.
-
Converting "indirect"
rail trips (cargo arrives in northern New Jersey by rail and
is drayed to central Long Island, and vice-versa) to direct
rail trips (cargo arrives and departs by rail to and from central
Long Island with only a very short dray).
Input to the Model. We used the Federal Highway Administration's
Surface Transportation Efficiency Analysis Model (STEAM) to analyze
highway-related benefits of the proposed transportation investments
at Pilgrim. The total commodity flows to and from central Long
Island for various years were estimated, as were the amount of
these flows that could be shifted from truck to rail as a result
of the Pilgrim project. These effects were "translated"
into travel outputs, such as changes in vehicle miles and hours
of travel, which, in turn, serve as inputs to the STEAM model.
| Table 1: Annual Benefits ($000)
|
 |
Calculating Benefits. Benefits were calculated for both
"users" and "non-users" of the highway network.
User benefit categories include changes in vehicle miles traveled
(VMT), trips, travel time, vehicle emissions and fuel costs. For
this analysis, user benefits were segmented into two components:
truck and auto. These two components were analyzed separately
due to the differences in travel time values and operating costs
between commercial and passenger vehicles. About 90 percent of
user benefits are experienced on the auto side rather than the
truck side because reductions in highway congestion "spill
over" to automobile users. Truck transport cost savings comprised
about 10 percent of the user benefits for each scenario.
Non-user benefits represent benefits that accrue to the region
as a whole, rather than directly to highway network users. These
include reductions in emissions, global warming, noise impacts,
other mileage-based costs (such as construction-related neighborhood
impacts), and revenue transfers (e.g., loss/gain of gas tax revenues).
STEAM also calculates user and non-user benefits associated with
changes in accident rates, which are a function of VMT, speed
and congestion.
The results of the STEAM model runs are summarized in Table 1.
All scenarios show positive benefits. Given the much larger scale
of investment and utilization of Scenario 3, however, it is not
surprising that this scenario would ultimately produce the highest
total gross benefits and efficiency benefits.
Benefit-Cost Analysis Results
Using year-by-year estimated benefit streams from the STEAM analysis
and project cost estimates, we conducted a formal economic benefit-cost
analysis. This analysis compared the discounted stream of project
benefits and costs extended over a 20-year period at seven percent
interest per year, beginning one year prior to 2005, when initial
capital investments would be made. The results of the analysis
are the project net present value (NPV) and the benefit/cost (B/C)
ratio. The NPV is the difference between the present value of
project benefits and project costs, including capital and annual
operations and maintenance costs. The B/C ratio is of the discounted
stream of benefits divided by the discounted stream of costs.
| Table 2: Benefit-Cost Results
|
 |
Separate analyses were conducted for each of three investment
scenarios to determine the incremental improvements in benefit-cost
results as higher levels of market demand are accommodated with
increased levels of investment. Both measures are useful. The
NPV typically takes precedence when maximizing overall project
performance, while the B/C ratio is more useful for comparing
across competing projects within a fixed budgetary constraint.
The benefit-cost analysis presented here does not include costs
for any of the "upstream" or off-site railroad system
improvements mentioned above. While these improvements are necessary
for increasing cargo throughput at the Pilgrim intermodal terminal
in Scenarios 1, 2 and 3, we assumed for purposes of this analysis
that the decision to implement (or not implement) those improvements
would be made independent of the Pilgrim project. Thus, those
"joint" costs may be regarded as "exogenous"
to the benefit-cost analysis from the perspective of the cost
side, and no portion of them was allocated to the Pilgrim site
itself. The results of the formal benefit-cost analysis are summarized
in Table 2.
All three scenarios generate a positive NPV and a B/C ratio greater
than 1.0. The extent of benefits increases from Scenario 1 to
Scenario 3 as "upstream" rail improvements, allow more
intensive use of the Pilgrim facility for container handling.
The B/C ratios reflect the benefit and cost of the Pilgrim facility
itself, and not the benefit and cost of regional rail access improvements,
such as TOFC/COFC clearances, double-stack clearances, or a cross
harbor rail freight tunnel. These rail access improvements would
benefit all traffic east of the Hudson River, not just central
Long Island, and the net benefits associated with those investments
would be considerably greater than those shown from the more limited
analysis used here.
Generalized Business and Employment Benefits
The formal benefit-cost analysis represents an important but still
incomplete technique for assessing the potential economic benefits
of an investment. A supplementary approach would be to consider
the potential benefits to industry and consumers on Long Island
if the Pilgrim intermodal terminal comes into operation. This
analysis, unlike a "static" benefit cost analysis, would
take into account the potential economic multiplier effects if
substantial transportation cost savings can be realized for targeted
growth industries on Long Island. These potential impacts include
industry clusters on Long Island, potential cost savings for goods
production activities on Long Island, and potential consumer benefits.
While space constraints do not permit a detailed discussion of
how the potential economic benefits are assessed, any reader who
is interested in additional information can contact me at hirschman@pbworld.com
|