|
The Central Artery/Tunnel (CA/T) project in Boston, Massachusetts
is certainly one of the largest infrastructure investments in
the U.S. Mirroring PB's early history--William Barclay Parson's
career began with railroad work--the CA/T project's design and
construction contracts began with railroad work. The South Boston
Haul Road (SBHR), now renamed the South Boston Bypass Road, transformed
an old, over-grown, under-used, four-track urban railroad corridor
into one rebuilt railroad track with an adjacent two-lane commercial
vehicle roadway.
The concept of the SBHR was to use an existing transportation
corridor for both railroad freight and commercial highway vehicles.
The positive benefits projected for various stakeholders included:
-
The Community: Reduced
truck traffic volume (which was as high as 14 percent of average
daily traffic) in the residential neighborhoods of South Boston
with corresponding enhanced safety, reduced noise and improved
air quality
-
Highway Users: Significantly
reduced trip times
-
Railroads: Land sale
income and new railroad tracks
-
Public Agencies:
Reduced commercial traffic (trucks, busses, taxis, etc.) on
roadways being reconstructed as part of the CA/T project
-
Commercial Users:
A direct, non-stop route through the South Boston community
for commercial traffic and CA/T construction vehicles.
PB, in joint venture with Bechtel, performed the concept development
and preliminary design, wrote a stand-alone environmental impact
statement, assisted with final designer procurement, managed technical
and commercial issues during final design, assisted with contractor
bid/award and acted as owner's representative during construction.
The unique challenges we resolved during planning/permitting,
design and construction of this multimodal shared-access corridor
are the focus of this article.
History of the South Boston Haul Road
In the 1850s, the SBHR route began to be used for railroad access
to Boston from south of the growing city. Before 1900, it was
made a two-track, depressed route with 12 overhead bridges. Extensive
freight yards and maintenance facilities were constructed near
the South Boston waterfront. The present MBTA Red Line subway
tunnel, constructed in 1913 along Dorchester Avenue, crosses the
cut on a diagonal under a bridge. The top of the tunnel is about
0.6 m (2 feet) below the railroad track on a three-level multimodal
structure: passenger subway below freight railroad below highway.
The depressed railroad route was widened from two tracks to four
by 1920.
After the 1940s, passenger service was discontinued and freight
service levels declined. The result was that two tracks in the
depressed track area and seven yard tracks remained in various
levels of deferred maintenance. The other two tracks remained
in service for the (usually) daily local freight until the mid-1980s.
The route was suggested as a possible multimodal shared-access
corridor early in the CA/T project; community reaction was favorable,
and a study of feasibility was authorized in 1987.
Preliminary Engineering
Field Survey and Mapping. The first effort was an old fashioned
field survey. Much of the SBHR area was outside of the aerial
mapping prepared for the CA/T project although, ultimately, aerial
photographs were taken and mapping prepared for final design.
Interestingly, the aerial photographs were enlarged and used as
wall displays at community hearings, where they generated numerous
positive comments. Initially, however, Mylar base map roll plans
were prepared manually from the field surveys (CAD systems were
not in place at the time).
Highway and Railway Layouts. Highway and railroad layouts
were plotted manually on the Mylar base map roll plans. These
layouts were found to be unusually straightforward. The highway
alignment was straight (tangent) for 1.6 km (1 mile)! This was
surprising in Boston, the largest city in New England, long noted
for its "unusual" street grid patterns. It was especially
surprising considering that one end of the SBHR is only 1.6 km
(1 mile) from downtown locations such as Boston City Hall and
the Massachusetts State House.
It was no surprise, however, that the existing grade (profile)
was not a problem for highway traffic because railroads are flatter
than highways. Vertical clearances under the existing overhead
bridges were not a problem for highway vehicles because railroad
equipment is higher than trucks.
Highway Traffic Analyses. Traffic analyses showed that
one lane in each direction was adequate for the expected commercial
traffic, and that a single through railroad track plus a runaround
track and a two track yard was acceptable for railroad service.
The wall-to-wall width of the four-track railroad cut was just
wide enough for the two-lane highway and single railroad track;
therefore, favorable horizontal and vertical alignments probably
already existed-a major benefit of multimodal shared access routes:
No homes or businesses were taken or even disrupted-another major
benefit in a city.
The Environmental Impact Study
After we determined that the SBHR was technically feasible, the
approvals process started. We decided that a stand-alone environmental
impact statement would be prepared to allow the SBHR to be constructed
before and serve as mitigation for the extensive CA/T project
work that was to follow. The project would result in the many
positive benefits listed above; however, some specific considerations
were also identified. These were:
-
Traffic conditions at both
ends of the SBHR
-
Rainfall runoff collection
and drainage outfall
-
Railroad needs
-
Abutter concerns
-
Property rights
-
The permitting process
-
A nearby hazardous material
site
-
An adjacent park playground.
Nevertheless, public hearings resulted in positive responses
from the community. The lack of negative comments was considered
unusual in our increasingly litigious society. In hindsight, we
have a better understanding of why the public probably reacted
favorably. The route had long been accepted as a transportation
corridor through the community so its existence was not an issue
and this project would only improve it. Approval to proceed was
given in due course.
Design Issues
The actual final design of the SBHR consisted of three main parts:
highway, railroad and drainage.
Highway. The highway design itself consisted of three
main parts:
-
Tie-in to the local street
system at the north end
-
Main highway route along
the existing railroad
-
Tie-in to the local street
system at the south end.
Tie-in at the North End. The existing railroad line crossed
a designated truck route street at grade so the SBHR simply tied
into this street. Traffic modeling indicated that only a stop
sign was needed for traffic control, but that traffic control
signals would be warranted after a few years if traffic volume
increased as expected. Provisions were made for tie-ins to a future
CA/T Interstate Route 90 Interchange.
Main Highway Route. The northern half of the SBHR alignment
was in flat, open area of the former railroad freight car storage
yard. The area, built on land filled by dredging, had less that
0.3 m (1 foot) of elevation change in 0.8 km (0.5 mile) and no
occupied buildings within hundreds of feet. The southern half
of the SBHR alignment was in the formerly four-track railroad
cut. There were 12 overhead bridges.
In the open area, full-width standard highway shoulders were provided,
but in the cut area narrower shoulders filled the distance between
concrete "Jersey" barriers on the railroad and wall
sides of the highway. There was sufficient highway width to allow
two-way traffic around a disabled truck in the shoulder except
at the Dorchester Avenue bridge center pier (with subway underneath).
Interestingly, because of high axle loads from the high percentage
of trucks, the owner decided to construct four test pavement sections
using different combinations of varying thickness and type of
material for sub-base, gravel base, and bituminous concrete. The
granite and concrete walls of the railroad cut, which also served
as bridge abutments in most cases, were rehabilitated where needed.
Three of four one-lane wooden bridges (one of which was closed
due to fire damage) were removed and not replaced. The fourth
was repaired to serve as access/egress to a new police station
constructed concurrently with SBHR work. Bridge protective screening
was added at sidewalks on the remaining bridges to protect highway
and railroad traffic below. Other bridge repairs were performed
at each bridge as needed, with needs varying greatly. A noise
barrier at the adjacent park playground, general brush/vegetation
clearing, fire protection, fire truck access, water lines, fencing,
signs, lighting, duct banks, slope improvements plus many other
miscellaneous needs along both sides of the cut were included.
Tie-in at the South End. The existing railroad line ran
under Dorchester Avenue, a major city thoroughfare and a designated
truck route. A loop ramp at a 5 percent grade was constructed
partly through a bus storage yard to a traffic control signal
at Dorchester Avenue. Provisions were made for direct access from
the bus garage access to the SBHR. The design included elements
to allow easy extension of the SBHR via a future CA/T connecting
viaduct to an interchange with Interstate Route 93.
Railroad. Railroad design was routine, as expected on
an existing railroad line. The former yard area was reconfigured
with a single through track to the waterfront, a runaround track
and two storage tracks. The old yard was then removed along with
several abandoned railroad structures, such as freight car scales,
scale pit, team track loading dock, light towers, etc. A single
new track on the east side of the railroad cut provided access
to the yard. Turnouts at the south end of the cut were relocated
to match the new track location and new turnouts to two freight
sidings were installed. There are no railroad signal systems on
these tracks. No railroad/highway grade crossings were added.
All work was done without disrupting railroad operations. The
CA/T construction contractor built the tracks and railroad personnel
installed the track tie-ins. Freight trains were re-scheduled
to avoid operation during day-shift construction.
Drainage. Highways always require drainage, but SBHR's
drainage needs were a surprise. An early field survey revealed
that portions of the railroad cut were more than 1.5 m (5 feet)
below mean sea level. As one might expect, the expression, "You
have got to be joking," was heard many times. Gravity drains
to the nearby ocean were physically impossible.
Additional investigation revealed that there was a railroad pump
station near the south end of the railroad cut. It became clear
that a pump station with force main to a properly approved outfall
would be required. The drainage collection system for the SBHR
was of conventional design. The total distance from the pump station
to outfall is over 0.8 km (0.5 mile). Numerous utilities and obstructions
were encountered, so close coordination with the operations of
the various entities along the outfall route was necessary.
Several Surprises and Lessons Learned
Several surprising, unexpected, and "lessons learned"
items emerged on the SBHR.
Property Acquisition. One big surprise was the amount
of effort required for property acquisition. Much of the railroad
right-of-way was owned by Conrail, but other portions were owned
by Amtrak and Massachusetts Bay Transportation Authority (MBTA).
Portions of the railroad yard were owned by a local businessman,
including the air rights over land owned by Conrail. Some of
the bridges were owned by three parties, with the City of Boston
owning and maintaining the roadway and sidewalks, the Commonwealth
of Massachusetts owning and maintaining the bridge structures,
and Conrail owning and maintaining the bridge abutments and
walls.
When the railroad cut was physically widened from two tracks
to four, the railroad did not officially widen the property
in all cases. The City of Boston and several abutters owned
some of the land where trains operated. Some land was owned
by the U.S. Postal Service and by the U.S. Army, so special
federal procurement procedures were activated. Land owned by
MBTA, the Massachusetts Port Authority and the City of Boston
activated special Massachusetts procurement procedures. These
property items had to be handled properly and legally to allow
clear title for the highway to pass to the Massachusetts Highway
Department.
Hazardous Materials. Railroads are at locations with
high potential for finding hazardous material, so careful assessment
for hazardous material is always prudent if railroad right-of-ways
are to be reused/rebuilt. The SBHR was no exception. A large
site with polychlorinated biphenyls (PCBs) in the ground was
found at a former junk yard that specialized in cutting-up and
scrapping electrical transformers. Locations with high concentrations
of other hydrocarbon products were also identified. Substantial
investments of time and money were required to determine the
extent of pollution and mitigate the sites. Interestingly, the
regulations for site mitigation changed greatly during program
development, but the impacts to final remediation were slight.
Two buried railroad tank cars, probably used for fuel storage,
were found and removed during construction.
Nearly a Decade of Service
After more than one year of construction the SBHR opened in
1993. It has served emergency and commercial vehicles continually
since then. The SBHR was extended to the south to tie into a
recently constructed frontage road system at Interstate Route
93. The north end was modified to provide direct commercial
vehicle access to the new Third Harbor Tunnel to Boston's Logan
Airport while retaining access to the local street system in
Boston's growing waterfront area. Railroad freight volumes actually
increased due in part to delivery of bulk and over-size materials
to the CA/T Project.
The SBHR is essentially an urban two-lane limited access highway
more than 1-mile long. As such, the SBHR has future potential
for use as a very long ramp for all highway vehicles to and
from Interstate 93 and Interstate 90.
Additionally, a large convention center complex is under construction
adjacent to the SBHR. The potential exists for the SBHR to provide
substantial traffic relief before and after convention center
events.
In Summary
The highly successful transformation of a little used railroad
corridor into a busy multimodal route was both routine and challenging.
With its combination of the easy and the difficult, however,
the SBHR was an extremely satisfying project to work on. PB
should always be proud to transform an underused transportation
route into a highly useful piece of infrastructure. When it
is possible to add another transportation mode to an existing
route, all planners and engineers should seriously consider
doing so.
|