On October 17, 2000, a derailment occurred at Hatfield on the
East Coast Main Line, about 20 miles north of London. The cause
of the derailment was a broken rail, and the rail break was caused
by a progressive type of fracture called gage corner cracking. Four
people were killed in the unfortunate accident and the aftermath
plunged Railtrack into a crisis from which it is still recovering.
Railtrack began an emergency inspection programme of its system
immediately to find any other rails that exhibited gage corner cracking.
This programme was followed immediately by an emergency replacement
programme. When the defects were found they were classified according
to new engineering standards issued by Railtrack, and “slow
orders” were placed on the tracks. Hundreds of the defective
rails were found and the resulting number of trains disrupted by
the slow zones created havoc around the national rail network.
Railtrack managed the programme with its own staff until late November
of that year, but found that the volume of work was overwhelming
and required additional management resources. As a result, the National
Recovery Programme was begun to manage the crisis and PB, Bechtel
and Fluor Daniel, as Railtrack’s three principal programme
management (PM) contractors, were asked to establish a PM office
at Railtrack’s headquarters.
As background, there are seven geographical zones in Railtrack.
Each zone is responsible for the operation of trains on its portion
of the network and the normal maintenance of the assets through
the use of infrastructure maintenance contractors. It is these contractors
who were performing the inspections and replacing the defective
rails.
Establishing the Programme Management Approach
The new PM team faced significant challenges. Railtrack was under
intense pressure from the government, the press and the public to
quickly return train service to normal. The effects on the overall
economy and people’s lives were dramatic. Tom McCarthy of
Bechtel was established as the programme manager and I was named
deputy programme manager. Our team took the following actions to
establish a centralized approach to the programme.
Defined Clear Roles and Responsibilities. The
lines of responsibilities from the Railtrack Board through the central
PM team and down to the zones were clarified.
Established a Programme Control Center. A national
programme center was set up in London and was augmented by the National
Logistics Unit in York. The center had responsibility for development
and implementation of the national strategy, central collection
of data and progress reports, coordination of supply chain issues,
and other issues.
Began Centralized Reporting. With all the diverse
requests for information both inside and outside Railtrack, it was
necessary to establish one chain of command for reporting. Centralized
reporting allowed the seven zones to report progress through the
central office and enabled Railtrack to respond with a single voice
to the government and press.
Established Central Database. Each of the zones
had developed, of necessity, its own database to track the progress
of its efforts. Without a centralized database with all relevant
information on each of the gage corner cracking sites across the
seven zones, system-wide coordination was not possible. Establishing
this centralized database became the focus of the programme because,
in addition to helping us to address other critical issues, it:
- Enabled the PM center to monitor the overall progress of the
programme
- Enabled the shifting of resources to address imbalances
- Allowed proper coordination of supply chain issues for the
entire network.
Summarized Supply Chain Requirements. The resources
required for the NRP simply overwhelmed the normal Railtrack supply
chain structure. It was necessary to coordinate a system-wide approach
to supply rail, contractor personnel, and other critical resources
in order to be successful. Supply chain issues are discussed in
more detail in a section below, and, for WCRM, in a following article,
“Supply Chain Management Approach—Post Privatisation”
by Lynn Kemerer.
Coordinated Responses to Government. The Office
of Rail Regulator required quick action by Railtrack to address
what it felt was a national rail emergency. At one point, ORR used
its powers to place an “enforcement order” on Railtrack
that required Railtrack to develop a national plan for restoring
rail service by a certain date. The pressure to produce the plan
and deliver results was significant, and our success was possible
only because of the actions mentioned above.
Overall Scope
New engineering standards were established quickly to safely manage
the inspection and management of gage corner cracking defects. It
involved a rating system based on the progressive nature of the
defects, with the highest tiers requiring the imposition of slow
orders for the trains.
The scope of the NRP was continually expanding for a number of
reasons:
- The initial inspections progressed over many weeks, continually
revealing more gage corner cracking sites.
- The initially small gage corner cracking defects progressed
into increasingly larger cracks being revealed that required immediate
action.
- The improvement of inspection techniques during the programme
led to cracks being revealed that were not evident with older
techniques.
In general, the rail being replaced fell into two categories—“plain
line” (standard rail) and “switches and crossings.”
“The number of defects varied significantly across the zones
but in the end, there were approximately 800 km (500 miles) of plain
line rail and 1500 pieces of switches and crossings replaced across
the network, all in a time period of about six months. These numbers
would be impressive if the work had been performed over a few major
sites where one could expect productivity gains. When it is considered,
however, that the NRP scope was performed over almost 2000 sites
across the network, the accomplishment is even more significant.
Supply Chain Issues
The scale of the rail replacement efforts and the short time frames
virtually assured that supply chain issues would present some of
the largest challenges to the programme. Some of the major issues
were related to delivery of rail strings, ordering the correct switches
and crossings, and having an adequate labor pool.
Rail Strings. While the UK steel industry could
supply the rail requirements, there were capacity problems with
regard to the welding of rail “strings” and the delivery
of those strings to the work sites. It was necessary for key routes
to be established so that priorities could be set on the deliveries.
Switches and Crossings. By far the greatest supply
chain issue in the initial stages of the programme was switches
and crossings. Given the diversity of switch and crossing sets throughout
the network, each of the approximately 1500 sets required separate
measurements before it could be ordered, and rail suppliers needed
to be matched to those types of switches and crossings that they
could manufacture—a situation that further limited overall
capacity. As with plain line rail, the orders then had to be prioritized
according to the key routes and commitments made by Railtrack to
the train operating companies.
Labor Pool. The overall rail contracting supplier
network was strained by the volume of work and required management.
For instance, in some zones where contractors in the past had replaced
three or four switches annually, they were now being asked to replace
200 on very short time frames. Inevitably, shortages occurred in
certain labor pools such as thermit welders, signal testers and
others.
Epilogue
With completion of the NRP in May 2001, the immediate crisis was
over and train operations were back to levels of reliability higher
than those that existed before the derailment.
With many normal maintenance activities having been delayed during
the gage corner cracking crisis, however, and with further inspections
showing a significant backlog of long-term deferred maintenance,
Railtrack began an Infrastructure Recovery Programme (IRP) to build
on the momentum of the NRP. David O’Hagan of PB assisted the
Railtrack Programme Manager, Richard Spoors, in setting up the IRP.
In summary, this was a challenging assignment for the programme
management team. The scale and complexity of the mobilization effort,
conducted under significant governmental and public scrutiny, was
a considerable achievement. |