Most large airports face or will soon face
the need to complete a major construction project while maintaining
airport operations. Owners don’t have the option of closing
the airport for an extended period of time, so they face the dilemma
of balancing ongoing construction with the demands of the traveling
public.
What is the best way to achieve this delicate balance in light of
the multitude of alternative construction project delivery systems?
You’ll have to consult your favorite swami for the answer
to that question, but in this article you will read about what PB
did to enhance a client’s existing project delivery system.
Construction Manager/General Contractor
The Port of Portland has been using successfully a form of cost-plus-fixed-fee
contracting called construction manager/general contractor (CM/GC)
as the preferred construction contract format for major capital
improvements to the Portland International Airport. This project
delivery system involves using a quality-based selection process
to choose a contractor, bring the contractor on during design and
negotiate a cost-plus-fixed-fee contract for the work prior to design
completion. CM/CG offers several advantages. It has:
- Provided the port the flexibility
and adaptability it needs to respond to emerging and changing
customer requirements in a dynamic, time-critical operating airport
environment.
- Allowed the port to start a design, then
bring in the construction contractor at an early stage before
design is completed to participate in and help to shape the final
design.
- Given the port the opportunity to
start construction on a project before the entire design is completed.
The drawback to the CM/GC form of contract
is the “cost plus” nature of the contract. How can the
owner control and minimize cost?
Portland International Airport |
Controlling Costs
Guaranteed Maximum Price (GMP). In an effort to
control cost, the port has coupled the cost-plus-fixed-fee CM/GC
contract with a GMP, which provides a “cap” for the
cost of the project. The port pays all costs up to the GMP, and
the contractor pays all costs over the GMP.
This cap provides some measure of cost control for the owner but
there is no direct, overall incentive for the contractor to minimize
costs or stay on schedule. This is because the contractor will be
paid for all costs incurred up to the GMP and any savings under
the GMP accrue to the owner.
The port has generally had good results with CM/GC but wanted to
add an element to the contract that would provide an incentive for
the contractor to exceed the performance typically expected of a
quality contractor.
Traditional Incentives. The port had used traditional
monetary incentives on previous CM/GC contracts with mixed results.
These incentives generally rewarded specific, measurable performances
and the rewards were tallied at the end of the job. The port’s
incentives had been tailored generally to rewarding contractors
for:
- Early completion. The early
completion incentives seemed to foster questions during construction
as to whether the port or its contractors were responsible for
causing delays, and they resulted in negotiations for additional
time if changes were made in the planned sequence of construction.
- Exceeding pre-established safety
standards. The safety incentive sometimes frustrated
a safety-conscious contractor who had a minor accident despite
a superbly implemented safety program, or frustrated the owner’s
safety manager when a contractor with a less-than-stellar safety
program had no accidents.
The goal of using a CM/GC contract was to select
a quality contractor and create a team that worked together cooperatively,
was flexible and adaptable, and responded to changes required to
accommodate the needs of the traveling public without engaging in
laborious negotiations for minor changes. The traditional incentives
just didn’t seem to fit well in the CM/GC contract format,
however.
Children playing on a bronze inlay
of the Columbia River in the new concourse of Portland International
Airport |
South Security Lobby of Portland
International Airport |
A New Incentive System
For solutions, the port turned to PB, which had been hired to provide
construction program management support. We developed a new incentive
system to overcome the shortcomings of the traditional incentive
system. It included the following elements:
- Periodic evaluations and rewards
- Rewards for behavior, not outcomes
- Subjective evaluations
- Owner as the final deciding authority.
This incentive system was inserted into the
current CM/GC contract for expansion of the existing terminal and
demolition and construction of a 13-gate concourse. The contract:
- Established an incentive fee (expressed
as a percentage of the original GMP), the number of evaluation
periods and five evaluation criteria (listed below)
- Required the port to establish the amount
of the total incentive fee “pool” that would be available
for each evaluation period
- Provided flexibility for the port to weigh
the five criteria for each evaluation period, with the only requirement
being that the port let the contractor know what the criteria
weight would be at the start of the evaluation period.
Having the flexibility to determine the amount
of incentive fee and the weight of the evaluation criteria gave
the port the ability to have each evaluation tailored to the particular
phase of construction. For example, the initial evaluation could
be more heavily weighted to the criteria associated with getting
started—such as team building and planning—while subsequent
periods could focus more on safety, cost control and schedule control.
The Five Evaluation Criteria. The criteria were
established to reward behavior, not outcomes—the rationale
being that if the behavior is correct, the outcome should be positive.
The five criteria are the effectiveness of the contractor’s:
- Efforts to minimize disruption to
airport operations, passengers and tenants
- Implementation of a safety program
- Management of the construction schedule
- Management of costs
- Team-building efforts.
For example, instead of the traditional criteria
of providing a reward for completing so many days early, the schedule
control criteria focuses on whether the contractor is proactively
looking ahead, anticipating problems and taking timely action to
avoid schedule slip. Likewise, the safety criteria evaluation focuses
on the implementation of the safety program, not whether or not
the contractor got lucky and had no accidents.
Evaluation Process. The five criteria are subjective,
so how are they evaluated? A three-member committee comprised of
port representatives does the evaluations. The port’s project
manager and the contractor’s project manager each prepare
an evaluation (limited to one page per criteria) of the contractor’s
performance against the five criteria for the evaluation period
under consideration. The port seeks input from various interested
parties, such as the airport operations staff, in preparing its
evaluation report. The two project managers’ reports are submitted
to the evaluation committee and exchanged between the two project
managers. The two project managers may be asked to make a short
presentation to the committee and respond to questions.
The committee evaluates the contractor’s performance and makes
a written determination as to the amount of available incentive
fee the contractor is to receive for the evaluation period under
consideration. The committee’s determination is final and
is not subject to appeal or review. The contractor is paid the earned
incentive fee with the next monthly progress payment. Any unearned
fee is lost (retained by the port) and not available to the contractor
in subsequent evaluation periods.
Contractor’s Response. The contractor was
enthusiastic about the incentive fee provision and during the negotiations
of the CM/GC contract agreed to add a portion of his fixed fee into
the incentive fee pool of funds. The port contributes 75 percent
of the incentive fee pool and the contractor contributes 25 percent.
This means that if the contractor receives an award (grade) of less
than 25 percent in any evaluation period, the contractor will be
paying the port.
Light Rail Station at Terminal
Expansion |
Update
The contract has been under construction for twenty-nine months
as this article goes to press. We have concluded five of the seven
incentive fee evaluations periods and the contractor’s average
award has been approximately 84 percent.
The process has proven to be a valuable communications tool for
the project team. It has been especially beneficial in that there
has been no animosity between the port and the contractor. We have
noted that in many instances the contractor was more critical of
his performance than the port was.
The system has also provided a valuable means to focus the contractor
on issues that the port feels are significant. One such example
was that during the first evaluation period the contractor’s
safety program did not appear to be as effective as the port thought
was necessary to ensure success on a very critical phase of the
work. The contractor was going to construct a large canopy structure
over the airport’s upper roadway (for departing flights) during
that phase while keeping passenger access to the terminal open.
Because of the concern for safety, the contractor’s performance
was noted in the evaluation, and the percentage (weight) of this
criterion was raised for the subsequent evaluation period. The contractor
altered his behavior, focused on this issue and the critical construction
sequence was handled superbly.
The incentive fee structure provided the flexibility to change the
weighting of the criterion to fit the construction phasing and provided
an opportunity to alter one of the criterions. Quality was implied
in all of the criteria originally, but we found that we were identifying
quality issues as we evaluated all of the various criteria. In response,
the contractor, suggested that we create a criterion that dealt
with quality only to avoid “watering down” valid criteria.
We changed the team-building criterion to “Effectiveness of
the Contractor’s Quality Control Program” before the
fifth evaluation period.
|