Allegheny County Airport (AGC), located in
West Mifflin, Pennsylvania, 16 km (10 miles) south of downtown Pittsburgh,
is the reliever airport to the Pittsburgh International Airport
(PIT). In 1996, AGC was the third-busiest airport in Pennsylvania
after PIT and Philadelphia International Airports based on the annual
number of operations. AGC has an air traffic control tower that
operates around the clock.
The management of AGC together with the Federal Aviation Administration
(FAA) Airport District Office approved the full-depth replacement
of the bituminous-concrete-surfaced Runway 13-31 with a new Portland
cement concrete surface in 1997. PB was selected to provide construction
management and inspection services.
Design of Runway
The design of the new, 30-m- (100-foot-) wide runway called for
the majority of construction joints (transverse and longitudinal)
to be saw cut. Dowels that permit horizontal movement of adjacent
slabs were to be used at interior transverse joints to provide for
transfers of loads across the joints and to prevent relative vertical
displacement of adjacent slab ends. The diameter of the dowel bars
was to be 2.5 cm (1 inch).
Dowels were to be placed across transverse contraction joints within
30 m (100 feet) of the free ends of the pavement and within 18 m
(60 feet) of the expansion joints at intersections with existing
pavement. Additional dowels were to be placed at expansion joints
and at intersections of the runways, taxiways and aprons.
Some of the interior longitudinal joints were supposed to have smooth
dowel bars to allow for minor horizontal movement between slabs,
and tie bars were to be used across certain longitudinal contraction
joints to hold the slab faces in close contact. Tie bars themselves
do not act as load transfer devices, but by preventing the wide
opening of the joint, they allow for load transfer to be provided
by the aggregate interlock in the crack below the groove-type joint.
The tie bars called for in the design were 1.3 cm (.5 inch) in diameter
and deformed.
Phasing and Schedule Limitations
Runway 10-28, which intersected with Runway 13-31, was open to traffic
at all times during the construction. Work within the Runway 10-28
safety area was:
- Not permitted from 6:00 a.m. to 9:30 a.m.
and from 3:00 p.m. to 6:30 p.m.
- Not recommended during other daytime/daylight
hours, but permitted if the contractor had all workers and equipment
leave the safety area within 15 minutes of a request from the
FAA control tower and permitted unrestricted aircraft movement
on the runway.
The contractor was provided a detailed work
sequence and phasing of the project. All work was to be completed,
tested and fully operational within 84 calendar days from the notice
to proceed. The contractor would have been assessed liquidated damages
of:
- $5,000 per day for each calendar day beyond
the completion date that the project was not finished
- $100 for each 15-minute increment beyond
6:00 a.m. that the contractor failed to have Runway 10-28 re-opened.
In addition, the contractor would have had to stop all operations
an equal amount of time earlier on the next work shift.
Figure 1a: Doweled or Tied Construction
Joint Type F, not to scale |
Figure 1b: Doweled Contraction
Joint (Type D), not to scale |
Contractor Requests
Change in Joint Types
The contractor used a Bid-Well paver that placed 15-m- (50-foot-)
wide lanes. All longitudinal joints were to be saw-cut joints except
for the centerline full depth construction joint. The design and
construction considered the following types of slab joints:
- Type F, a full-depth, formed
joint (Figure 1A). FAA
pavement design assumes that the smooth formed surface does not
provide shear transfer, so the joint dowels are designed to provide
the full shear transfer. The smooth dowels are also greased to
permit temperature expansion/contraction and movement in the horizontal
direction.
- Type D, a partial-depth saw cut
joint (Figure 1B).The rest of the joint
is formed by the cracked concrete below the saw-cut joint surface.
The FAA pavement calls for shear transfer within this irregular
cracked surface to be provided by the aggregate interlock and
assures this transfer by placing “tie bars” to keep
the cracked joint tight.
Given the 15-m- (50-foot-) wide slip-form concrete
placement, the contractor requested and was given approval toreplace
the proposed Type F interior doweled construction joints (2nd and
3rd joints from the edge of the pavement) with Type D contraction
joints and tie bars. The centerline joint would remain a full depth
construction joint
The alignment and elevation of the steel dowels and tie bars across
the joints is extremely important. Usually a wire cage or basket
anchored firmly to the subbase of the pavement is used to hold the
dowels or tie bars at correct horizontal and vertical locations.
Conflicting Requirements Yield Improper
Joint Steel
The fabrication of the steel baskets was on the critical path of
the job, and they required six to eight weeks for delivery after
the order was placed. The contractor ordered the steel baskets for
the project in accordance with Publication 407, Pennsylvania Department
of Transportation (PENNDOT) specifications that referenced the PENNDOT
Roadway Standard Drawings (RC Series) and used standard industry
practices for PENNDOT and the Pennsylvania Turnpike (highway jobs).
Publication 407 was supposed to change only the formats of the FAA
specifications, but it had unintentionally introduced changes to
them because of discrepancies between FAA and PENNDOT specifications.
Publication 407 had been generated for airports jobs and was used
in hopes of encouraging bids from highway contractors, who were
usually not familiar with FAA specifications.
All dowel bars were ordered as deformed bars even though some joints
were designed to use smooth bars because PENNDOT specifications
define steel dowels as deformed bars. FAA specifications, on the
other hand, define them as smooth bars.
The contractor received all the steel baskets with greased deformed
dowels or tie bars. Where the designer had specified a smooth dowel
bar, the delivered material was a deformed bar; at locations where
an ungreased deformed bar had been specified, a greased deformed
bar was received.
Design firms in Pennsylvania have stopped using the PENNDOT Publication
407, consequently, as of the time of this writing. The field investigation
concluded, however, that the grease coating of the deformed bars
was the fabricator’s error.
We asked the designer to analyze the effects of the coating on the
steel and the effects of using the deformed dowel bars in lieu of
smooth bars in order to avoid significant project delays and associated
air traffic delay costs. After several discussions with experts
in the field and given the nature of the runway’s prime purpose
(visual, cross-wing runway for light aircraft), the designer accepted
the joints steel as received from the fabricator because there were
no anticipated impacts to the life of the runway pavement.
Figure 2: Paving Train |
Figure 3: Hairline Cracks Appeared
Adjacent to Transverse Joints |
Cracks Develop in the
Concrete
In placing the concrete pavement, ready-mixed-concrete trucks approached
the fully automatic Bid-Well paver adjacent to the paved area of
the runway and dumped the concrete onto a conveyor belt hopper.
The concrete was conveyed laterally for up to 15 m (50 feet), and
the operator controlled the point of discharge. The paver speared,
vibrated and finished the concrete slab, then advanced forward.
Concrete finishers performed minor manual touch-up work at the edge
of the pavement and sprayed the curing compound on the fresh surface.
Within the safety area of the intersecting Runway 10-28, however,
concrete placement was done manually with hand-held vibrators and
a 8-m- (25-foot-) wide finishing roller screed.
The productivity rate of this paving train (Figure 2) was high,
with up to 610 m (2,000 feet) of pavement being placed per night,
when most of the paving was done to allow the 8-km (5-mile) haul
from the concrete plant to the site to take place with no delays.
The majority of the paving activities were completed within two
weeks.
Each night’s paving activities were followed within 12 hours
by the “green” cut of the concrete surface. Widening
of the original joint cut followed. The saw cutting generated concrete
slurry that covered the concrete surface, so cleanup of the surface
was required before the joint material was placed.
We noted several hairline cracks adjacent to transverse joints during
these cleanup operations (Figure 3). The cracks appeared to be surface
cracks ranging from 100 mm (4 inches) to 300 mm (12 inches) in length.
They were located directly above the dowel bars. Core samples taken
immediately indicated that the cracks were 25 mm (1 inch) to 38
mm (1.5 inches) deep. In some places the cracks went down to the
top of the dowels. They occurred only in places where the Bid-Well
paver had been used for concrete placement.
Our Investigation Turns Up Several Possible
Causes
Some theories we considered as explanations for the formation of
the cracks include the following:
- The pavement over the steel might
have cured faster that the rest of the pavement, with the steel
dowels acting as moisture barriers.
- The vibration rate on the Bid-Well paver
might have been set too high, causing uneven vibrations over the
steel dowels. This could have caused segregation of the aggregates,
resulting in additional shrinkage.
- Vibrators touching the dowel baskets might
have caused a localized mix segregation that could have promoted
excessive shrinkage.
- The dowel baskets might have rebounded as
the paving head moved above them.
- The dowel baskets might have tipped, leaving
the dowels grossly out of alignment and possibly shifted close
to the concrete surface.
- The surface might have torn as the paving
head moved above the baskets.
- Settlement cracks, as described in the ACI
224R-38, “...are the natural result of heavy solids settling
in a liquid medium.”
Rebar locators used to confirm the locations
of the dowel bars indicated that they were perpendicular to the
joints and in a horizontal position, as designed. The concrete cover
was within the design tolerance of 16 mm (5/8 inches).
Microscopic-level petrographic examination of
the hardened concrete was performed to determine the probable cause
of the crack formations and to predict future performance. Concrete
cores were taken from a cracked section of the runway and tests
were performed in accordance with the American Standard Test Method
C856. The results showed that the cracks were formed very early
during the concrete curing process—the top surface had hardenprematurely
because it lost moisture to evaporation faster than the moisture
could be replenished by bleed water.
The concrete mix had a relatively low water content. The paving
was performed at night, which reduces the chance of dry shrinkage,
but the airport is situated in an area subject to constant wind
conditions. These conditions may have contributed to the quick evaporation
of water from the concrete.
The rate of application of the curing compound met the specifications
requirements, but the time gap between the placement of the concrete
and the placement of the curing compound may have been the cause
of the cracks.
We concluded that most probable cause of the cracks was that the
concrete surface shrank more quickly than it was supposed to. Windy
conditions caused the surface to dry out too quickly, which caused
shrinking and cracking. We also concluded that this was a highly
localized condition, and the majority of the runway surface was
acceptable.
Lessons Learned
- Do not use FAA specifications that
are modified to another industry’s specifications,
such as PENNDOT Publication 407—or use them only with
extreme caution.
- Identify long-lead items in the project
early on and communicate the design intent with the contractor.
- Apply curing compound as early as
possible to fresh concrete surface to minimize premature
water evaporation.
- Consider using Roadware 10-Minute
Concrete Mendertm for hairline crack repairs.
|
A Search for the Best
Repair Method
It was determined that a crack repair method should be identified
and analyzed as a potentially acceptable solution instead of removing
and replacing the cracked slabs. We led the search and performed
analysis and testing.
The American Concrete Paving Association suggested an epoxy injection
repair that had been used successfully in Denver to repair shrinkage
cracks in a new airport runway surface. With the contractor’s
help, we identified and tested two possible epoxies. Both manufacturers’
representatives demonstrated their products by repairing a dozen
cracks each. Post-injection testing was performed by analyzing cores
from the test sites.
Based on visual examination of the penetration depth of the material,
the polymer product, Roadware 10-Minute Concrete Mendertm from Elas-Tech
was selected for further testing. It had penetrated to the bottom
of the crack easily with its low coefficient of viscosity. It was
also applied easily with an application gun and did not require
preparatory steps for the crack. The polymer stained the concrete
surface amber, however, so we used cement powder to absorb excess
material and minimize staining.
Core samples of the concrete that was uncracked and the concrete
that was cracked and sealed with the polymer material were tested
for freeze-thaw and scaling resistance. The tests concluded that
the concrete core that had been cracked and then sealed with the
polymer material exceeded the performance of the uncracked concrete
sample.
Repairs Appear to Be Successful
As soon as the client approved the repair method, the contractor
applied the material to the cracks in accordance with the manufacturer’s
instructions and then sprinkled cement powder on top of the uncured
polymer to absorb excess material. There was very little evidence
of the cracks after cleaning.
A ten-year extended warranty provided by the contractor as a negotiated
settlement of this slab cracking calls for annual pavement inspections
and for the contractor to make additional repairs as needed. The
pavement inspection team has concluded that the pavement remains
in an excellent range, with no change in its condition each year
since opening to traffic in October of 1997. No additional repairs
have been required, and even the surface stains of the concrete
are not visible anymore.
|