The goal of providing rail access to New York
City’s John F. Kennedy International Airport (JFK) from Manhattan
is finally coming to fruition. By the end of 2002, passengers will
be able to connect from the NYC subway system at Howard Beach via
a light rail system (LRS) to one of six LRS stations serving JFK’s
air terminals (Figure 1). The new system, called JFK AirTrain, will
also provide a more direct route to midtown Manhattan’s 34th
Street Penn Station by 2003, when the connection at Jamaica Station
in Queens is completed. With the connection at Jamaica Station,
the total trip time from Manhattan to JFK will be approximately
30-40 minutes, a significant improvement over the current 1-2 hour
trip via the often congested roadways.

Figure 1: Links to New York City's
Subway System via Howad Beach and the Future Connection at Jamaica
Station |

Figure 2: The Ten Station Stops
of JFK AirTrain |
In addition to improving access to the airport
from the outside, the $1.9 billion JFK AirTrain project will improve
access for passengers traveling between terminals and airport facilities.
It is one of four critical factors to capacity planning at JFK.
The others, airport runway, terminal gate and roadway frontage capacity,
are being addressed by a more than $8 billion capital improvement
program that the airport’s operator, the Port Authority of
New York and New Jersey (PANYNJ) is involved with in conjunction
with some of the major airlines.
JFK handled more than 32 million passengers, 350,000 flights and
2 million tons of cargo in 2000. The events of September 11, 2001
impacted air travel, especially international air travel, but PANYNJ
expects the number of passengers to return to 2000 levels in 1-2
years. Pre September 11 projections anticipated 45 million passengers
annually by 2013.
The JFK AirTrain
The 13-km (8-mile) -long system has 10 passenger stations (Figure
2). Six are located in the central terminal area with direct access
being provided to each airline terminal. In addition, there are
stations serving the car rental area, long-term parking lot facilities,
Jamaica/LIRR train station for connections to the Long Island Rail
Road and New York City Transit systems, and the Howard Beach Station
for a direct connection to the NYCT station at Howard Beach.
The AirTrain system provides three distinct services:
- Jamaica Station. During
peaks hours, trains will leave Jamaica Station every four minutes.
These trains will stop at the car rental station on their way
to serving the six stations in the central terminal area and return
to Jamaica Station within 24 minutes.
- Howard Beach. During peak
hours, trains will depart every four minutes and will serve the
long-term parking lot and the car rental area on their way to
serving the six stations in the central terminal area.
- Circular Service. A circulator
service on separate track within the airport’s central terminal
area will provide inter-terminal movements every two minutes.
The trains will be fully automated and monitored from a central
control facility.
It is estimated that an average of 34,000 riders
will use the system daily.
Project Implementation
PANYNJ decided to use a combination of conventional design-bid-build
and design-build-operate-maintain (DBOM) approaches to implement
the JFK AirTrain project. Through a “best value” selection
process, a consortium named Air Rail Transit Consortium (ARTC) was
selected to perform most of the work. ARTC’s responsibilities
included construction of 100 percent designed project elements,
performing design-build services and, after acceptance of the system
by PANYNJ, operating and maintaining the system for at least five
years with the potential for two five-year extensions.
In addition, PANYNJ prepared contract documents for a major renovation
of the Long Island Rail Road and New York City Transit stations
at Jamaica. This portion of the project was designed and bid in
a conventional manner.
PB’s Role
Aircraft Accommodated by New Tunnel
 |

Figure 3: Tunnel Excavation |
PB provided conceptual engineering and prepared
the Request for Qualifications and Request for Proposal documents
for the DBOM contract. We also assisted PANYNJ in managing the procurement
process and supported the Federal Aviation Administration’s
environmental impact statement process.
We are providing general engineering consultant
services for the JFK AirTrain, including a wide range of planning,
design, environmental analysis, and procurement activities. A special
feature of the project is that joint PANYNJ/PB staffs are located
in a project office, and we are serving as an extension of PANYNJ
staff to manage the project.
Early Action Program:
Twin-Cell Tunnel
As part of an early action program, we prepared final design contract
documents for a 580-m (1,900-linear-foot) twin-cell tunnel that
is located under two active taxiways and was designed to carry light
rail transit in one cell, a 10-m (33-foot) -wide tunnel, and airport
service vehicles in the other, a 12-m (38-foot) wide tunnel. These
contract documents were included in the work required by the DBOM
contractor. In anticipation of future new large aircraft, the tunnel
was designed to support several large aircraft on the runway above.
These aircraft are listed in the box at left.
The tunnel was constructed by the cut-and-cover method (Figure 3).
Only one taxiway was taken out of service at any given time. In
order to restrict taxiway outages during summer peak periods, the
contract required temporary decking beams spanning the excavation
and supported on piles.
Contaminated groundwater plumes near the site required creation
of a “bathtub” to limit the movement of the plumes.
A system of horizontal and vertical groundwater cut-offs was designed
to address these concerns. (Vertical cut off was achieved by using
interlocking steel sheet piling and horizontal cut-off was achieved
by chemical grouting.) Detailed specifications for an extensive
monitoring and testing program were also prepared to ensure the
performance of the groundwater control system.
Design Review
 |
A joint PB and PANYNJ facilities review team
was setup to review design submittals for the design-build project.
Due to the large scope of the project (more than 263 separate design
packages) and the fast track nature of design-build construction,
it was essential that design reviews focus on major items.
To accomplish this, we setup a design review
procedure with clear instructions to the reviewers as to what they
shouldfocus on. A senior engineer with extensive design experience
led each discipline team. Frequent on-board meetings were held between
the reviewers and designers to ensure timely resolution of comments.
To date, more than 1,500 submittals have been reviewed by the facilities
review team, including preliminary and pre-final designs packages
and other deliverables required by contract.
Jamaica Terminal
The LRS connection to Jamaica Terminal is a major project by itself,
with a construction cost of more than $300 million. To handle the
extensive design and interagency coordination for this work, The
PANYNJ setup a separate and dedicated staff that included PB members.
We provided both senior level project managers as well as experienced
construction management staff to augment the PANYNJ team. This work
has proceeded through the design and bid stages and is well into
the construction phase.
Conclusion
The JFK AirTrain is a major project with all the complexities that
one would expect for a construction project that is being implemented
in a busy airport and urban environment. The fact that PB could
provide key staff and skills to assist in resolving a wide range
of problems is a tribute to the PB offices in the New York and New
Jersey areas.
|