Parsons Brinckerhoff
Worldwide LocationsContact PBLegal NoticeSite MapHome
PB Websites search Advanced Search
MarketsServicesAbout UsPeople and CareersNews and EventsResearch LibraryProjects
PB Network Email This Page
Go To Other Issues | Contact PB Network | Print This Article 
<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Projects in Australia and New Zealand
July 2003 • Issue No. 56 • Volume XVIII • Number 2
Transport
Sydney’s Parramatta Rail Link: Moving Forward
By Jim McNamara Sydney, New South Wales +61-2-9743-0333 jmcnamara@pb.com.au, and Paul Hewitt, phewitt@pb.com.au
PB took an innovative approach when designing a section of the Parramatta Rail Link —particularly the wide-span station caverns in shale and sandstone — and developed strategies to meet restrictive water inflow criteria.

The Parramatta Rail Link will be a new, mostly underground, 28-kilometre (17-mile) -long railway linking Parramatta and Chatswood via Epping (Figure 1). It will add four new stations to the Sydney Rail (CityRail) network and enable the upgrading of seven existing stations, including a new A$100 million transport interchange at Parramatta. The project includes twin-bored heavy rail tunnels running 12.5 km (7.5 miles) from Epping to Chatswood. The rail link represents a major investment in public transport by the New South Wales Government.

PB has teamed with consultant Gutteridge Haskins and Davey (GHD) to provide the design services for the civil and rail systems contract, which covers the Epping to Chatswood section. We played a major role in the pretender design for the winning group. Subsequent to the design/build contract being awarded to the Thiess Hochtief Joint Venture in July 2002 for approximately A$850 million, our team has been engaged to provide continued services. Our scope covers design of the rail alignment, tunnel and cavern excavation and support, and station structures; technical overview of ventilation design; and modelling of all temporary access works.


Figure 1: Alignment of Parramatta Rail Link.

Overview of the Parramatta Rail Link

The main component of the Parramatta Rail Link works will be 17-kilometre (11-mile) -long twin tunnels from Carlingford in Sydney’s northwest to Chatswood, on Sydney’s north shore. The tunnels will:

  • Measure 7 m (23 feet) in diameter and vary in depth from about 15 m (50 feet) to about 60 m (200 feet)
  • Run mostly parallel to each other
  • Pass under commercial and residential properties, universities and other institutions, and the Lane Cove National Park
  • Have cross passages located at regular intervals (approximately 240 m, or 790 feet) for emergency and maintenance access between the rail tunnels.

These tunnels, along with another 3 km (2 miles) of twin tunnels proposed to connect Rosehill and Parramatta in western Sydney, account for about 70 percent of the entire Parramatta Rail Link route. The remainder of the project includes:

  • A cut-and-cover tunnel under the Lane Cove River
  • Duplication and upgrading of the Carlingford Line
  • Dive structures at locations where the underground tunnels meet the surface tracks
  • Integration works to connect the new rail link with the existing Main North, Main West and North Shore lines, including rebuilding/ upgrading several road and rail bridges and associated infrastructure.

Innovative Design

We developed the following strategies during the tender design to solve problems presented by restrictive water inflow criteria and the need to build caverns in shale.

Geology and Hydrogeology on The Civil and Rail Systems Contract

The Epping to Chatswood section of the project is located in the upper sedimentary formations of the Sydney Basin, with a stratigraphic sequence that consists of Hawkesbury Sandstone, Mittagong Formation and Ashfield Shale. The Ashfield Shale forms a “capping layer” on elevated portions of the route, including Chatswood, Delhi Road, Macquarie Park and Epping. The residual soil overlying the bedrock is generally less than 2 m (7 feet) thick over sandstone, but up to 7 m (23 feet) thick over shale.

The Lane Cove River Valley where the cut-and-cover tunnel is to be constructed under the river is a palaeovalley comprising alluvial and estuarine sediments to depths of 17 m (56 feet) below ground level overlying fractured sandstone. High horizontal stresses have led to valley bulging and localised high permeability zones.

The tunnel will be constructed mostly within the Hawkesbury Sandstone groundwater system. The deeper water in the sandstone is semi-confined — that is, the aquifer is confined by a low-permeability layer that permits water to flow through it slowly.

Tunnel Alignment. The tunnel alignment at the new Macquarie Park Station was lowered to maximise the extent of mined station cavern in the more competent Hawkesbury Sandstone. This step allowed the designers to achieve settlement criteria, reduced ground support in the overlying shale and allowed the contractor to maximise production rates in the station caverns.

Ground Support. Based on numerical analysis and local experience with large span openings in Hawkesbury Sandstone, we also established support criteria for the vertical alignment design to select requirements for ground support. Doing so allowed the use of an observational approach to ensure the degree of support was optimised by matching the ground support to the in-situ conditions.

Groundwater Flow Analyses. One of the major project issues was groundwater control to limit groundwater level drawdown and surface settlement, and reduce discharge quantities of tunnel inflow to treatment facilities and the environment.

The tunnels will be driven by a tunnel boring machine (TBM). The economics of tunnel excavation using such equipment is predicated on rapid and uninterrupted machine advance. Large uncontrolled inflows and/or the stoppage or delay of tunnel drive for probe drilling and grouting are disadvantageous to TBM progress and performance. About 80 percent of all inflows were derived from just ten locations between Chatswood and Epping, where long-term infiltration rates were estimated to exceed 1 L/sec/km.
 
            Probe Holes. We proposed that forward observation holes up to 30 m (100 feet) long be driven beneath the alluvial valleys and areas of high predicted inflow to quantify the groundwater inflows and provide a staging area for pre-excavation grouting of these areas. This forward heading will provide the ability to assess steady state groundwater inflows prior to full width excavation, drainage placement and lining.

Probe hole grouting in the zones identified will allow a more reliable indication of the rock quality and anticipated water inflows than is possible based on the borehole data. Probe holes may be drilled up to 30 m (100 feet) in front of the heading and the tunnel advanced to within 5 m (16.5 feet) of the end of the probe hole before the probe hole is extended. Thus, probe drilling may be performed during the maintenance or off shift.

Water inflows will be monitored and should flows exceed the desired level, cement fan grouting performed from the tunnel heading may be undertaken. Probe drilling/fan grouting in this manner will allow the shortening of the grouted zones, as grouting would only be performed as dictated by measured inflow. As the water pressure testing results apply only to the zone around the boreholes tested, it is not yet possible to verify the true extent of the leaky rock zones. Probe drilling will allow individual zones to be tested and will generally reduce the zone where grouting is required.

The proposed delay period between tunnel bore and the lining construction will be used to observe and monitor groundwater inflows. A combination of grouting works and tanked construction will be adopted over areas of high flows to ensure the flows will satisfy the owner’s requirements.

           Groundwater Modelling. Groundwater inflows to the tunnels were assessed at pre-tender stage using an analytical method similar to that used by Heuer (1995). We took into account the packer results, groundwater head and geological/topographic features and our local experience on major tunnels. A recharge mechanism from rainfall was assumed to maintain the existing water table levels within the rock.

Groundwater modelling to predict tunnel inflows and assessment of settlements adopted Groundwater Modelling Guidelines developed for the Murray Darling Basin Commission, New South Wales. PB’s John Ross was a principal author of these guidelines, which are recognized throughout Australia as a defacto national standard on groundwater modelling.

We developed a three-dimensioned groundwater model for the Lane Cove River crossing and underground service facility site to simulate groundwater flow and estimate distributions of drawdowns, and to allow design of grouting and ground treatment in alluvium and fractured sandstone where water pressure (packer) testing had given results ranging from less than 0.5 Lugeon units to over 200 Lugeon units. The U.S. Geological Survey’s Groundwater Simulation Model, MODFLOW, was used to simulate groundwater flow in three dimensions in steady-state and transient modes. The inflows predicted by both the empirical (pre-tender) and three-dimensional analyses were within 10 percent of each other, considered good agreement.

Construction Methods on the Civil and Rail Systems Contract

The TBMs are planned to travel at about 120 m to 180 m (394 feet to 590 feet) per week through the sandstone. Initially a road header will be used from the Waterloo Road site in Macquarie Park to excavate the new Macquarie Park Station, and a second road header from the Wicks Road/M2 site will excavate the new Delhi Road Station. TBMs will then be launched from the Wicks Road site and head west towards Epping.

Related Web Site:

Details of the project can be obtained at the Parramatta Rail Link Web site at http://www.raillink.nsw.gov.au.

During this time, a cut-and-cover tunnel will be constructed under Lane Cove River using dewatered cofferdams that will cross the river in two stages. This technique will enable the river to flow at all times, minimising environmental impact. Once the Wicks Road to Epping section is completed, the TBMs will be brought back from Epping to the Wicks Road site, where they will be launched east to Chatswood. All underground and surface construction work will be closely monitored to ensure that the project meets the Environment Protection Authority (EPA) criteria for noise, vibration, air and water quality and complies with the conditions of planning approval.

The four stations, Epping, Macquarie University, Macquarie Park and Delhi Road, will be about 30 m (98 feet) deep. Underground (mining) excavation methods will be used to minimise impacts to the surface, and surface works will be limited to entrance and service structures. The station cavern “brain” shape was designed to minimise excavation volume while incorporating architectural requirements.

The main platform cavern will have a maximum cross-section of 22 m wide by 16 m high (72 feet by 52 feet), and an adjacent concourse cavern that is 18 m wide by 12 m high (59 feet by 39 feet). These spans will be among the largest of their type in the Sydney region.

Work in Progress

A design stage geotechnical and hydrogeological investigation is in progress to allow the design team to address some of the key issues and risks identified during the tender design. This testing will include in-situ stress testing for tunnel and cavern design and pump testing of the Hawkesbury Sandstone aquifers to quantify water inflows and requirements for ground treatment. Detailed design has been ongoing for a number of months and is scheduled for completion in late 2003.

Construction started in February 2003 on the first station cavern at Macquarie Park (Waterloo Road), where our geotechnical staff is providing geotechnical mapping for the 200 m (66 feet) long caverns, and in march 2003 on Lane Cove cut-and-cover tunnel. Epping dives began in May 2003 and Delhi Road began in June 2003. The first TBM is due to start assembly in July 2003 with boring of the 12.5 km (8.5 mile) long tunnel due to start in September. Completion of works is expected in 2007.

The incorporation of PB expertise worldwide was vital to our success on this project. The contributions of Los Angeles-based Tim Smirnoff to tender designs of the tunnelling work proved critical to developing a winning bid. New York-based Bill Kennedy’s high-level ventilation design assistance further strengthened the effort, as did the continuing contributions during detailed design from New York, Singapore and Los Angeles. The value of such readily available global expertise cannot be over stressed.

Jim McNamara is a Principal Structural Engineer and PB’s design manager for tender and subsequent detailed design for the civil and rail works contract of the Parramatta Rail Link project. Jim has been involved in numerous mass transit, tunnel and marine projects in Australia, Asia, the Middle East and the UK.

Paul Hewitt, a Principal Geotechnical Engineer, was responsible for the tender stage geotechnical and tunnel design of the Chatswood to Epping section of the Parramatta Rail Link. He has worked on several projects involving tunnelling in Sydney; and continues to work on the PRL project.

<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Go To Other Issues | Contact PB Network | Print This Article 
Markets  |  Services  |  About Us  |  People + Careers  |  News + Events  |  Research Library  |  Projects
Worldwide Locations  |  Contact PB  |  Legal Notice  |  Site Map  |  Home
© Parsons Brinckerhoff