
Figure 1: Nineteenth century cantilever bridge construction
(the Firth of Forth Bridge in Scotland) |
Early Developments
Nineteenth-century iron and steel truss bridge builders developed
a method for constructing large bridges without the use of falsework.
They placed individual members in a sequence outward from the supporting
piers toward the midspan in as close to a balanced condition as
possible to prevent “tipping” of the entire, partially
completed structure. This method required only minimal falsework
for support during construction because most of the bridge’s
weight was supported by the previously constructed structure. Resistance
to tipping was provided by limiting the unbalanced weight and either
fixing the superstructure to the foundation or using temporary supporting
piers. This construction scheme was referred to as “canted
lever” or cantilever erection (Figure 1).
In the 20th century, cantilever methods for building prestressed
concrete bridges were developed in response to advancements in construction
technology. The first generation of prestressed concrete cantilever
bridges was constructed in the 1950s as part of the overall reconstruction
and expansion of European post-World War II infrastructure, particularly
in war-damaged Germany and France. Reconstruction had created a
demand for large highway and railway bridges that could be constructed
with a minimum amount of factory- manufactured items, such as large
fabricated steel members, because many manufacturing facilities
had been damaged during the war and were in the process of reconstruction
themselves at that time.
Prestressed concrete was a logical material for development under
these conditions. It allowed for construction of concrete spans
with reduced cross sections and less weight than reinforced concrete
construction, and it had undergone an early period of development
in Europe by Eugene Freyssinet and other pioneers in the early century.
Post-tensioning of high-strength steel wires, bars and strands had
become an established construction method by this time.
Starting with construction of Ulrich Finsterwalter’s Lahn
River crossing in Germany in 1951, more than 300 prestressed concrete
cantilever bridges were constructed prior to the mid 1960s. These
early bridges pioneered development of much of the erection equipment
and procedures that remain in use today for cast-in-situ segmental
bridge construction. The bridges were constructed using a series
of full-depth “slices” or segments that were cast-in-situ.
Falsework was not required because the relatively short traveling
forms needed for casting the concrete segments were supported by
the previously erected portions of the bridge superstructure. Longitudinal
post-tensioning tendons were placed in the upper portion of the
segments and then stressed to provide the compressive force needed
to resist tensile stresses from the structures’ dead loads
and loadings applied after construction.
The vast majority of the early concrete cantilever bridges were
box girders due to the efficiency of the structural form and the
stability inherent in the box cross section configuration. Without
the requirement for falsework, these early bridges could be constructed
at great heights above the ground. The development of high-strength
prestressing steels allowed construction of long spans. By the mid
1960s, the first generation of prestressed concrete cantilever box
girder bridges had extended concrete girder bridge construction
to spans of nearly 150 m (500 feet).
1960s and 1970s: Refinement and Extension
of Technology
A majority of the pioneering work in technology, equipment and structural
forms that are in use on contemporary segmental bridge projects
was developed during the 1960s and 1970s. Earlier bridges had been
constructed with midspan deck hinges that allowed the structure
to deform under sustained dead loads without inducing large internal
forces in the girders, but resulted in rideability problems after
the bridge profile geometry changed over time. This problem was
addressed by using closure joints between cantilevers to make the
multi-span structure continuous. The first rigid frame segmental
bridge was the Bouguen Bridge constructed in France in 1963.
Computer Programs for Design. The use of continuity
required an improved understanding of the plastic behavior of concrete
under sustained loading and of the mathematical models suitable
for design. The development of improved material-behavior-prediction
models coincided with early applications of generalized structural
analysis computer programs for the design of bridges. Specialized
computer programs for designing segmental concrete bridges were
in the early stages of development during this time.
Following the early developments in Germany and France, cast-in-situ
cantilever bridge construction began to be disseminated to many
other parts of the world. The first cast-in-situ concrete cantilever
bridge constructed in the U.S., the Pine Valley Bridge near San
Diego, California, was opened to traffic in 1974.

Figure 2: Precast span-by-span construction with overhead
truss (the Spaghetti Bowl in Las Vegas, Nevada). |

Figure 3: Cast-in-place span-by-span construction with self-launching
forms (Rosario Victoria Bridge in Argentina). |

Figure 4: Incrementally launched deck for Neckarburg Arch
Bridge in Germany, 1977. |
Precasting. A revolution in concrete bridge construction
came about during this era in response to the demands of the post-war
economy for a large number of high-quality concrete structures that
could be assembled in a short time frame-the application of precasting
technology to segmental bridge construction. Precasting bridge segments
in a plant environment:
- Offered the advantages of improved curing and better quality
control
- Reduced the influence of weather on production rates
- Offered opportunities for schedule compression because portions
of the superstructure could be fabricated in the plant and placed
in storage while the substructure was being constructed.
Many large construction companies developed increasingly larger
capacity equipment for precasting, transporting and erecting concrete
segments. Specialized epoxies for sealing the precast segment joints
were developed. In addition, match cast technology provided a method
to precisely match adjacent segment face geometry, allowing the
necessary precision to achieve the required structural geometry
in the field. The first segmental concrete bridge with precast segments
was the Choisy-le-Roi, constructed in Paris in 1964.
Alternative Construction Methods. Alternatives
to cantilever erection were developed to extend the scope of segmental
bridge construction to many new applications, including:ftnt1
- Span-by-span. An entire span of segments is
supported by a temporary truss or girder until it is post-tensioned
and self-supporting. The truss or girder is launched to the next
adjacent pier, and the process is repeated (Figures 2 and 3).
- Progressive Placement. The erection of multiple
span bridges proceeds in one heading, often with temporary supports
to limit stresses in the structure during erection. This method
is particularly well suited to sites with severe access limitations
or where environmental issues limited contractor access to the
work site. Its first cast-in-situ application was in Finland in
1967.
- Incremental Launching. A segment is attached
to the previously completed bridge superstructure, and then the
entire completed bridge is launched outward before the subsequent
segment is assembled. This method was first applied on the Rio
Caroni Bridge in Venezuela in 1963 (Figure 4).
Concrete Cable Stayed Girder Bridges. Another
feature of this era was the development of concrete cable stayed
girder bridges which, being erected in cantilever from the piers,
represented a logical extension of concrete cantilever bridge erection
methods except that most of the prestressing tendons were external
to the bridge deck cross section. Cable stayed concrete bridges
extended the span length of concrete bridges to beyond 360 m (1,200
feet) eventually and made concrete bridges cost competitive with
steel trusses and arch bridges. Concrete’s high compressive
strength made it ideal to resist large axial forces that stays introduce
into the deck.
The development of reliable computer software for predicting structural
behavior during construction and under service was a necessary precondition
for design and construction of this highly indeterminate bridge
type. The first concrete segmental cable stayed highway bridge was
Venezuela’s Lake Maracaibo Bridge, constructed in 1962. This
bridge was followed by cable stayed bridges in Europe and Africa
in the late 1960s and early 1970s. The most notable examples of
the first generation of concrete segmental cable stayed bridges
in the U.S. are the Pasco Kenewick Bridge in Washington and East
Huntington Bridge in West Virginia.
Other Bridge Types. A final feature of this period
was the application of segmental concrete construction methods to
bridge types other than box girders. Precast segmental arches were
constructed on the 385-m (1,280-foot) -span Kirk Bridge in Yugoslavia
(1980), while cast-in-situ segmental concrete arches were constructed
in cantilever for the 195-m (650-foot) -span Van Staden Bridge in
South Africa (1970) and other structures in Europe and Japan.
1980s and 1990s: Dissemination of Technology
These decades saw the expansion of segmental construction technology
to an increasing number of bridge projects around the world, along
with the transformation of segmental construction from a research
and development environment to a widely accepted mass production
environment.
The large-scale introduction of segmental concrete construction
to the U.S. coincided with the completion of the interstate highway
construction program in the 1980s and continued throughout the 1990s,
with the increasing volume of construction in the Sun Belt states
and infrastructure reconstruction in the industrial states. The
growth of segmental construction projects was aided also by the
declining market share of steel bridges in favor of prestressed
concrete structures.
The rapid growth of the Asian economy in the 1990s created a demand
for transit systems and elevated expressways that could be constructed
with minimum impacts. Development of specialized erection equipment
and large-scale prefabrication yards allowed construction of increasingly
larger segmental concrete bridge projects. As an example, the Bang
Na Expressway constructed in Bangkok in the late 1990s is a 1200-span,
continuous, 50-km (30-mile) -long viaduct with a cost of more than
$1 billion.
Mega-bridge projects, such as the Storaebelt and Oresund Bridges
in Denmark and the Confederation Bridge in Canada, expanded the
range of segmental construction to “mega” applications
with the weights of concrete segments exceeding 6803 metric tons
(7,500 short tons). This heavy lift technology is largely the continuation
of previous projects constructed in Europe for use in the North
Sea. Continuing developments in heavy lifting technology offer the
prospect of increasing span lengths and mean greater use of prefabrication
yards to speed erection time.
Current construction of the San Francisco Bay Bridge replacement
includes the precasting, transport and erection of segments greater
than 453 metric tons (500 short tons). This represents a quantum
leap relative to previous precast cantilever bridge projects in
the U.S.
The computer revolution of the 1990s gave us a large number of commercially
available design tools for engineering these sophisticated structures.
The increasing use of the Internet allows projects to be designed
in multiple locations, provides closer links to the construction
sites and provides tools to assist in the management of larger scale
projects.

Figure 5: Vietnam Veterans Memorial Bridge - cantilever
construction of a segmental box girder using traveling forms |

Precast cantilever construction with overhead truss. |
Current Status and Trends
Current developments in construction materials technology offer
the potential for future innovations in segmental concrete bridge
construction. Lightweight concrete has been used for concrete box
girder spans of up to 300 m (1,000 feet) — the current practical
limit — and offers great potential for concrete bridge construction
in areas of high seismicity. Client demands for increased durability
of structures to extend service life and reduce maintenance costs
have led to current developments in cable stay, prestressing system
and grouting technology. The application of polymers to concrete
bridges offers the potential for dramatic reductions in required
concrete cross sections and lighter bridge structures. Condition
investigation and rehabilitation of existing structures offers new
markets for materials and technology developments.
Past experience has shown that segmental concrete bridges are particularly
suited to the following types of projects:
- Environmentally sensitive areas where disruption to the ground
surface must be minimized (e.g., wetlands, slopessubject to erosion
or areas with hazardous materials)
- Reconstruction of large-scale urban expressways where disruption
to existing operations must be minimized or eliminated
- Repetitive bridge projects that lend themselves to standardization
of structural components and construction activities, such as
long transit viaducts or elevated expressways
- Long-span bridges over navigable waterways, long crossings
over water or crossings over waterways subject to scouring or
unique hydraulic features
- Bridges over areas with poor construction accessibility, such
as steep terrain or canyons
- Large-scale projects where a bridge’s construction schedule
needs to be compressed to fit overall project schedule limitations.
We can expect that many future projects will fit into these types
of categories.
It should also be noted that the construction technology associated
with segmental concrete bridges originated from the design-build
contract environment, making it extremely well suited to that project
delivery method. There have been a steadily increasing number of
design-build segmental bridge projects, including PB’s design
of the Vietnam Veterans Memorial Bridge over the James River in
Virginia (Figure 5).ftnt2
|
| Juan Murillo has been involved in segmental
bridges since the 1970s. He worked on the design and construction
of Long Key Bridge, the first precast segmental bridge in the U.S,
and Sunshine Skyway Bridge, the first cable-stayed segmental bridge.
He has directed PB’s segmental bridge work since 1986.
Joe Showers, a former PB employee, was a lead design engineer on
many of PB’s segmental bridge projects.
1These segmental
construction methods are discussed in more detail by Joe Tse in
a following article, “Considering
Segmental Concrete Bridges.”
2 The technical
challenges PB addressed when designing this bridge are the focus
of a following article, “Design
of the Vietnam Veterans Memorial Bridge Over the James River”
by Taka Kimura, Victor Ryzhikov, and Joe Showers.
|