| We are seeing an increasing number of concrete bridge designs
come to fruition, especially in the U.S., and they have been mainly
in the form of segmental concrete construction. The versatility
of segmental construction enables construction materials and/or
complete precast units be delivered to their service location quite
invisibly. The contractor’s gantries, formwork and special
equipment can be set up with ground cranes at strategic locations
and times (such as at night or on weekends) to minimize disruption
to the environment or the public. Once the special equipment and
gantries are in place, work can progress uninterrupted. Segments
or materials can be stockpiled on the approach roads and/or partially
completed portion of the structure in order to reduce the need for
staging areas immediately adjacent to construction sites.
It is important that designers understand some of the basics affecting
segmental bridge design and construction in order to made decisions
about whether or not a segmental bridge is the most appropriate
type for any given project. Bridge projects considered appropriate
for a segmental design usually meet one or more of the following
conditions:
- They are large and there is the potential for a lot of repetitiveness
in construction details.
- They are complex because:
– Access to the sites poses significant challenges
– Traffic disruption around the sites must be kept to a
minimum.
- Aesthetics are considered a significant aspect of the designs.

Figure 1: Continuous Span-By-span Design Moment and Tendon
Schematic |

Figure 2: Precast Segments Erected by Ground Crane |

Figure 3: Precast Segments Erected by Deck Mounted Equipment
- Underslung Truss (Elevation) |

Figure 4: Horizontally Segmented Construction |

Figure 5: Cantilever Construction Moments and Tendon Schematic |

Figure 6: Cast-in-Place Balanced Cantilever with Form Travelers |

Figure 7: Precast Segment Erected by Overhead Gantry |

Figure 8: Incremental Launching of Girder With a Steel Nose |
Table 1: Economical Span Range and Span/Depth Ratios
 |
Segmental Construction Techniques
Segmental concrete bridges come in many forms, but are generally
categorized by how they are built. The main construction techniques
used for segmental bridges are span-by-span, cantilever, and incremental
launching.
Span-by-Span Construction. In span-by-span construction,
the bulk of the dead load in each span is applied initially to the
structure by a positive moment at or near the midspan. Consequently,
the post-tensioning tendons that hold the spans up tend to be heavy
about the midspan and placed low in the bridge cross-section (Figure
1). The variations that have seen successful include having the
spans:
- Precast into short segments of approximately 3-m (10-foot)
lengths for ease in handling
- Built in horizontal lifts on rolling forms or special travelers
- Cast off-site and hoisted in complete span-units.
The precast option is by far the most popular of these variations
because of its rapid rate of construction. Once the crew has learned
the routine, it is not unusual to consistently get two to three
spans erected in a week. Figures 2 through 4 show several variations
of the span-by-span construction method.
Cantilever Construction. This method is quite opposite
to the span-by-span method in that it has the majority of the dead
load introduced into the structure as cantilevers over pier supports.
As a result, the final structures see significant negative moment
over the piers, and the post-tensioning tendons in the superstructure
tend to be heavy about the pier supports and placed high in the
bridge cross-section (Figure 5).
Cantilever construction has seen a large variation of successful
applications, the majority of which have segments in the range of
3-m to 4.5-m (10-foot to 15-foot) lengths depending on whether the
segments are precast or cast-in-place. There are also cases where
an entire cantilever is cast off site, delivered and then lifted
into final position. Figures 6 and 7 illustrate several applications
of the cantilever method of construction.
Incremental Launching. The bridge cross-section
is typically constructed at an abutment and pushed into its final
position. This method causes each bridge section to experience a
wide range of positive and negative moments inherent to the span
layout before coming to its final position. The maximum negative
moment occurs just prior to touching down at the next pier. A steel
launching nose is often used to reduce the demand imposed by the
launching stages so that construction does not govern the choice
of the cross-section and principal aspects of the design. The length
of the launching nose is generally about 65 percent of the longest
span (Figure 8).
Another method that has been used involves a system of temporary
stay cables and a tower mounted at the front part of the superstructure
to lift the tip of the superstructure, thus reducing the negative
moment. Temporary post-tensioning tendons are designed to be nearly
concentric to the centroidal axis of the bridge cross-section to
provide appropriate compression in both the top and bottom fibers
of the cross-section. This method requires that the underside (soffit)
of the superstructure follows a constant profile and curvature.
Several projects that have complex roadway geometries were accommodated
by varying the height of the girder webs and the overhangs of the
roadway slabs.
Design Considerations
Stress History and Its Influence on Design. Like many other structure
types that are constructed in stages (e.g., composite steel construction),
a segmental bridge must be designed to account for the construction
stress history. The design process for segmental bridges must also
address creep and shrinkage that may be significant during construction
and after construction is completed. This means that the design
computation must account for the sequence as well as the schedule
of construction. Fortunately, these physical phenomena and their
effects on design are well documented. Also, a host of commercial
computer programs are available to track the stresses and displacement
history of a constantly evolving segmental bridge. Good engineering
practices have also been progressively codified over the years to
ensure uniformity in the design products.
Other Considerations. The design of a segmental
bridge must take into account all the considerations customary to
bridge design, including:
- Horizontal and vertical clearances
- Geometry of the alignmentrequired by the crossing
- Construction schedule
- Site constraints, such as access
- Environmental requirements
- Visual impacts
- Aesthetics
- Economical span range
- Span to depth ratios.
The choice between using cast-in-place or precast segments for
the various methods of construction will depend primarily on the
project size, construction schedule, span length requirements, and
access to the site. Guidelines for the last two considerations listed
above are presented in Table 1.
Choosing the Method of Construction
Perhaps more so than other bridge types, the segmental concrete
bridge manifests the inter-relationship of design and construction
knowledge. Given the impact of construction methods and construction
loads on the basic design of a segmental bridge, a design for service
load alone is inappropriate. An engineer must evaluate the project
as a whole before deciding on the method of construction, span arrangement,
static scheme and cross section to be used. For this same reason,
a feasible, cost effective and complete construction sequence and
methodology should be presented in the design drawings. Where viable,
the construction contract should make allowance for the contractor’s
proposed modifications with regard to construction technology. Provisions
should be provided in the specifications with the basic system requirements
presented clearly to facilitate accurate and responsive bidding.
Conclusion
As never before, segmental technology has matured to a point where
its acceptance is widespread. Concrete technology has also made
recent advancements that will further bolster the viability of segmental
designs.ftnt1 Designers
should be aware of the benefits that this type of construction has
to offer to a project and give it due considerations. The results
may be a competitive design that is relatively low in maintenance
and aesthetically pleasing. |
| Joseph K. Tse is a professional engineer
with more than 25 years’ experience in design and construction
of segmental bridges and cable supported structures. He graduated
from Tri-state University, Angola, Indiana, with a BSCE degree in
structures, and is a senior supervising engineer.
1 For more information
on recent advancements in concrete technology, see the subsection
entitled “Material Evolution” of a following article
by Arthur Palmer entitled “Precast Segmental Casting Yards:
Past, Present and Future.”
|