| The Vietnam Veterans Memorial Bridge is a 1453-m (4,766-foot)-long
crossing of the James River in Virginia, directly downstream from
the Port of Richmond. It is part of the 14-km (9-mile) -long Route
895 design-build toll-way project that will link Chippenham Parkway
(Route 150) in Chesterfield County with I-295 in Henrico County
near the Richmond International Airport.
The bridge spans the 61-m (200-foot) -wide navigational channel
leading to the port, can accommodate a possible future widening
of the channel to 91 m (300 feet), and provides the required vertical
clearance of 44 m (145 feet). The total width of the river is approximately
206 m (675 feet).
The bridge comprises two 3-lane roadways over the river and an existing
interchange of I-95 and the Chippenham Parkway. Additional ramps
connecting I-95 and Route 895, also part of this project, are located
on the west side of the river, directly adjacent to existing industrial
plants and a municipal waste treatment plant. Right-of-way constraints
and the height of the mainline above grade resulted in complex geometric
arrangements for the ramps and relatively high piers. Many buried
utilities were in the area of the west approach span because of
the industrial character of the riverbank area, and the profile
required relocation of high voltage power lines that crossed the
alignment.

Figure 1: West Bound Bridge Elevation (Larger
Image) |

Figure 2: West Approach Span Plan and Section |
PB prepared a bridge type in 1997 as a subconsultant to the ramp
designer. We were selected subsequently by the design/build team
to prepare the final design for the approach spans and river crossing
bridges, which are shown in profile in Figure 1. The major elements
of the project are the:
- Crossing Bridge. Cast-in-place, variable depth segmental concrete
box girders with a maximum span of 206 m (675 feet)
- Approach Spans. Constant depth, precise segmental concrete
box girders with a maximum span of 64 m (210 feet)
- Tangent Ramps. Constant depth, precast segmental concrete box
girders
- Curved Ramps. Steel plate girders.
Approach Spans
The west approach spans were divided into two units:
- Unit 1 extends 415 m (1,360 feet) between the west abutment
and the ramp gore area for Ramps F and G (Figure 2) and is comprised
of seven spans.
- Unit 2 is more complex, extending 162 m (530 feet) from the
ramp gore area to the river crossing and comprised of three spans
of differing lengths to accommodate the existing I-95 mainline
and Chippenham Parkway ramps directly below (also shown in Figure
2).
Substructure. The area is relatively low-lying
with a high water table. Rock was encountered at a relatively shallow
depth of approximately 6 m (20 feet) below grade at the west abutment
and 15 m (50 feet) at the west riverbank, and hazardous materials
were reported present in the soils. Vertical and battered steel
H piles driven to rock were used for the foundation system with
the bottom of the footing elevation located near existing grade
to minimize or eliminate excavating existing soils and minimize
hazardous materials issues.
Benefits of Hammerhead Pier Caps. Single column
piers with hammerhead pier caps were selected for the approach piers,
giving a relatively conventional substructure configuration. Because
the deck cross slope varied and the deck segments were a constant
depth, the cross slope of the caps was varied and the geometry standardized
to eliminate adjustments in the cap forms and allow the use of a
typical prefab reinforcing cage. We used these caps on the steel
ramp structures also to have a common substructure type for the
majority of piers on the project and improve the overall aesthetics
by reducing the number of potentially visually conflicting elements.
Seismic Issues. The site is in an area with a
design bedrock acceleration of 0.13 g. The AASHTO Seismic Performance
Category (SPC) B classification required detailing the column bases
for concrete confinement to provide for ductile hinge development,
so we used circular columns to facilitate predictable hinge development
and simplify construction. A709 (not the more conventional A615)
reinforcing bar hoops with mechanical couplers were used in the
ductile hinge areas. These couplers were adopted based upon their
successful testing and application on many projects constructed
by the California Department of Transportation (CalTRANS), which
has some of the strictest seismic design standards in the U.S.
Superstructure. The bridge decks consist of two
precast segmental concrete box girders connected by a longitudinal
cast-in-place construction joint. Typical segments are 3 m (9.84
feet) long and 3 m (9.84 feet) in depth. To accommodate the varying
width for Unit 2 in the vicinity of the gore area for Ramps F and
G, the width of the cantilevered slab overhangs that extend from
the trapezoidal box core of the girder was varied. This arrangement
standardized the core forms for the casting machines and simplified
formwork adjustments to accommodate variations in the transverse
segment geometry. The standardized core form also made it possible
to use the same casting machines to fabricate the approach spans
and the ramp superstructures.
Complex Geometry. Horizontal curves were introduced
in the girders adjacent to Pier 7 to limit the maximum overhang
dimensions. There were also variations in the segment cross slope
over the length of the gore areas. This complex 3-dimensional geometry
was accommodated by the short-line, match cast, precasting equipment
that was custom-fabricated for this project. The segments were transversely
post-tensioned in the casting yardand longitudinal post-tensioned
in the field during erection.
From a structural design perspective, this arrangement also called
for complex analysis. The longitudinal girders are torsionally stiff
and restrain the connecting deck slab. A 3-dimensional finite element
analysis was prepared to determine the internal forces and stresses
resulting from dead and live loads. Time dependent material effects
such as creep and shrinkage were investigated by use of specialized
segmental design software. Service load combinations specified by
AASHTO were investigated, as were ultimate strength requirements.
The box girders are supported on pot bearings to allow for longitudinal
movement. Seismic pintels are placed at the bottoms of the pier
diaphragms to restrain seismic movements of the superstructure relative
to the substructure.
Unusual Feature. One unusual feature of this project
is the combination of the precast segmental concrete box girder
mainline superstructure with the structural steel plate girder ramp
structures. Steel ramp structures are used primarily in areas adjacent
to the mainline due to tight horizontal curve geometry or tall columns
on curved areas. As a result, the gore areas had to be detailed
to accommodate both bridge types.
Durability. Durability of the segments was addressed
by the use of epoxy coated deck reinforcing 45 MPa (6.5 ksi) concrete
with slag cement, galvanized bars for the parapets, and coated transverse
prestressing hardware in the upper areas of the deck slab. In addition,
the precast segments were steam cured. Further protection was provided
by a 50 mm (2-inch) latex or micro-silica deck overlay.

Figure 3: West Approach Span Construction — Note the
overhead truss used to place segments. |

Figure 4: East Approach Span Plan and Section |

Figure 5: East Approach Span Construction — Note the
cranes used to place segments. |
Overhead Erection Method. Overhead erection methods
were used because access from below was limited due to the existing
roadways and temporary detours directly beneath the bridge. Erection
of the approach span segments in cantilever was done with an overhead
erection truss (Figure 3) used previously on a precast segmental
concrete cantilever bridge in Florida. This self-launching truss
places segments on opposing longitudinal faces of the pier segment,
minimizing longitudinal unbalanced moments on the substructure.
The truss also supports stressing platforms necessary for installing
longitudinal tendons in the upper portions of the segments.
For the taller columns, there were limitations on transverse unbalanced
moments and deflections that resulted from erecting one entire cantilever
in advance of erecting any of the segments on the adjacent girder.
The truss was equipped with a chassis system that allowed for transverse
launching or “side shifting” at piers. As a result,
a portion of one girder was erected, the truss side shifted, a portion
of the second girder erected, and the truss side shifted again to
finish erection of the first girder.
East Approach Spans. The 6-span east approaches
extend 351 m (1,150 feet) and are located on curved horizontal alignments
(Figure 4). Span lengths range from approximately 41 m (135 feet)
to 64 m (210 feet). In contrast to the west approach spans, the
east approaches were located in good soils at a height of approximately
15 m (50 feet) above the James River floodplain, and the water table
was further below existing grade, as is the bedrock. The steel H
pile foundation system was used here also, however, to simplify
installation and provide better driving resistance through cobbles
and boulders.
The east approach spans have many of the same features as the west
approach spans, although the geometry was not as complex because
there were no gore areas. The primary difference was in the erection,
which was done in cantilever from the piers using ground based cranes
(Figure 5) because the relatively open terrain on the east side
of the river posed few limitations on contractor access. Longitudinal
stability of the partially completed cantilevers required use of
cable stays anchored into the footings to resist out-of-balance
erection moments.
River Crossing Bridges
The eastbound crossing is three-span cast-in-place segmental box
girder with span arrangement of 115 m, 205 m, 24 m (377 feet, 672
feet, 406 feet). The 205 m (672 foot) main span enabled us to locate
the piers directly adjacent to and behind the river banks, thereby
limiting the hydraulic impacts of the foundations and eliminating
the need to design the foundations for ship impact.
The 4-span westbound bridge is considerably longer and has a significantly
different span arrangement of 75 m, 129 m, 205 m, 118 m (246 feet,
423 feet, 672 feet, 388 feet) because the existing Chippenham Parkway
interchange ramps limited pier placement locations and resulted
in the necessity to add the fourth span. The main span piers are
located on a common foundation with the eastbound main span piers
(Figure 6).

Figure 6: River Crossing Bridge Plan and Section |

Figure 7: Pier 13 of the East Bound Bridge Under Construction |
Both the eastbound and westbound bridges have ramps that merge
with the mainline. Both ramp terminals required lane tapers and
drops, resulting in variable-width roadways on both bridges. In
addition, a horizontal curve and super-elevation transition is located
on the east side of the river within the limits of the river crossing
structures. These roadway geometric requirements resulted in unusual,
complex geometry for the two long-span structures.
Substructure. As with the west approaches, rock
was encountered at a relatively shallow depth of approximately 15
m (50 feet); however, hazardous materials were not reported in the
soils in the vicinity of the foundations. All foundations were 2.5-m
(8-foot) -diameter concrete-filled drilled shafts. Some of the advantages
of using drilled shafts as opposed to H piles were a reduced foundation
footprint, improved resistance to seismic forces for these heavily
loaded piers, and the stability of the foundation system during
potential scour events.
Two Pier Types. The nine piers supporting the main
span units are of two general types — double wall and single
wall. The four interior piers that supported the main spans needed
to resist large unbalanced loadings during cantilever erection while
also accommodating longitudinal superstructure movements. A longitudinally
flexible substructure would also reduce the superstructure period
and limit longitudinal seismic forces in the foundation, so we used
twin wall columns for the main piers (Figure 7). The four transition
piers with expansion bearings at the ends of the river crossing
bridges use single columns. Pier WB-11 also used a single column
due to the relatively smaller out of balance erection moments and
limitations in foundation placement resulting from the proximity
to existing ramps.
Standardized Columns. The columns supporting the
river crossing bridge were standardized as much as possible. Each
twin wall column has four circular bar cages with additional face
bars and cross ties, allowing for prefabrication of a large portion
of the cage steel. Also, the use of circular cages accommodated
seismic confinement details at the base of the columns required
by AASHTO SPC B. Column cap dimensions and reinforcing details were
also standardized.
Standardized Superstructure. The superstructure
box girder cross sections for the two bridges were also standardized
as much as possible to allow for reuse of equipment and formwork.
The typical “core” areas of the cross sections consist
of two cells, three vertical webs, and a constant soffit width of
14 m (46-feet). The deck slab is cantilevered past the exterior
webs and the width of the overhang varies to accommodate the variation
in roadway widths. The depth of the girder varied from 12.8 m (42
feet) at the piers to 4 m (13 feet) at midspan, and provided the
required 44.2 m (145-foot) vertical navigation clearance at the
edges of the future 91.46-m (300-foot) -wide channel.
Variations in the deck cross slope were accommodated by variations
in the height of the three girder webs. Thinner webs are used in
the midspan areas with relatively low shear forces to optimize the
cross section and limit the dead load moments during the cantilevering
erection. Segment lengths near the piers were shorter than the lengths
further out on the cantilever arms as a result of the larger and
heavier cross section required near the piers.
Analysis. As with the approach spans, both a three-dimensional
finite element analysis and an analysis using specialized segmental
design software were prepared to determine the internal forces and
stresses resulting from service and erection loads. The analysis
also showed that the variation in web heights resulted in differing
degrees of end restraint of the deck slab by the webs, and resulted
in the need to thicken the deck slab near the piers. The effect
of shear lag on the transverse distribution of normal stresses in
the soffit near the piers was also investigated.
Unusual Feature. A very unusual feature of this
project is the connection of the structural steel plate girder ramp
structures with the far larger segmental concrete box girder mainline
superstructure. From a geometric perspective, the gore area required
a large variation in ramp width over a relatively short distance,
but large variations in the width of the main bridge box girder
core were not possible because of limitations on the forms and other
construction equipment. Steel plate girders were selected for the
framing of a majority of the gore areas because the extent of the
widening exceeded the maximum capacity of the segmental concrete
deck slab cantilevers. The ramp gore framing is supported at one
end on one of the ramp piers and at the other end on a cantilevered
concrete bracket projecting from the outer face of the girder diaphragm.
The deck slab on top of the gore area is detailed with a longitudinal
closure joint to limit the effects of the box girder stiffness on
the vertical deflection of the steel plate girders during deck slab
placement. Design of this area required a finite element analysis
to determine the transverse and longitudinal bending moments in
the deck slab and cantilever overhangs from the box girder.

Figure 8: East Bound River Crossing Bridge Construction
Sequence |
Erection Method. Erection of the segments in “balanced”
cantilever was done with traveling forms supported by the previously
completed portions of the superstructure. These space frames supported
the forms and wet concrete weight of the segments, the largest of
which weighed on the order of 3,692 KN (830 kips) and was approximately
12 m (40 feet) tall. The travelers also support platforms required
to finish the concrete surfaces and install transverse and longitudinal
prestressing tendons. Because of the unequal length of the side
span cantilever arms relative to the main span arms and the very
large rotational stiffness of the twin wall piers, temporary support
towers were required under the side spans at two locations to limit
the erection impacts of on the substructure. The construction sequence
is shown in Figure 8.
Unique Feature. A unique feature of this project
was the use of progressive cantilevering for the westbound bridge
span over I-95 between Piers WB-10 and WB-11. It was not possible
to balance the segment weight at Pier WB-11 because of the span
arrangement, so one arm of the cantilever was made continuous with
the adjacent arm well before the opposite arm was completed. A vertical
jacking operation was also introduced on this arm to control service
stresses and assist in limiting moments in the single column support
pier.
Conclusion
This project has been technically innovative in that it combines
three structure types (steel, precast segmental, and cast-in-place
segmental) into a single job of this magnitude. Adding to the complexity
was the fact that the structure was required to span over a railroad,
an existing freeway, and an active navigation channel without impacting
any of those transportation links. The west approaches, east approaches,
and river crossing bridges were erected simultaneously on this recently
completed bridge.
With respect to project delivery systems, this project has also
been innovative in that it will be the longest span bridge built
in the U.S. using a design/build project delivery method. The successful
completion of this project will show that design/build contracts
are appropriate for projects of this magnitude. |