| In an area accustomed to top entertainment and “headliners,”
the headline currently getting Las Vegas residents’ attention
is that relief has finally come to the I-15/U.S. 95 Spaghetti Bowl
Interchange. This interchange lies at the geographic center of the
Las Vegas Valley and used to be the central bottleneck in the area’s
regional transportation network. As the local population swelled,
the upgrade of I-15/US-95 Interchange became Nevada’s number
one statewide transportation priority.
Table 1: Growth Trends  |

Figure 1: Model of the Spaghetti Bowl Interchange |
Table 2: Spaghetti Bowl Major Ramp Superstructure Statistics
 |
Table 1 summarizes the growth that led to the need for this major
improvement, which was to facilitate smooth traffic flow to downtown
Las Vegas from just north of the famous Las Vegas strip, a major
tourist destination offering gambling, entertainment and family
recreation. Another important need was that existing traffic flows
on the intersecting roadways not be interrupted.
The Project Setting: Major Structures and
Construction Methods Used
The reconstruction of the I-15/U.S. 95 (Spaghetti Bowl) core interchange
was the first major project in the western U.S. to use precast concrete
segmental construction with external tendons. The four major ramp
structures that comprise approximately 65 percent of the overall
interchange superstructures (Figure 1) were constructed of precast
concrete segments. Table 2 summarizes the structural arrangement
of these ramps. The design of each ramp used a combination of frame
structures. Each frame is made up of four to five continuous spans
that range in length from 36 m to 65 m (120 feet to 215 feet).
The spans were erected by the span-by-span method except for the
four 65-m (215-foot) -long spans of ramp N-W crossing over US 95,
which were constructed by the balanced cantilever method. The maximum
length for the span-by-span arrangement was 45 m (150 feet).
Making it Possible: Priming the Construction
Market
The difficulties of using segmental construction included the need
for specialized construction equipment and personnel with the skills
to operate and maintain that equipment. In addition, tight geometric
control was required during casting and erection of the segments.
Recognizing that this level of complexity was not typical to the
local construction market, the owner and our design team raised
the question:
Can we expect reasonable bids in a market that never had
experience with segmental construction technology?
An affirmative answer was made possible through an aggressive
contractor awareness campaign aided by the American Segmental Bridge
Institute (ASBI). The campaign included extensive advertisement
and a series of pre-bid conferences for contractors.
Selecting the Precast Segmental Alternative
The selection of a precast segmental alternative was a result of
a comprehensive bridge type study and evaluation of the following
alternatives:
- Steel plate girder
- Steel box girder
- Cast-in-place concrete box girder
- Precast I-girder
- “Bath-tub” sections
- The standard ASBI/PCI/AASHTO box girders.
The candidates were measured against a series of evaluation criteria
that considered a combination of factors, including:
- Construction in an urban environment
- Minimum required clearances
- Aesthetics
- Maintenance of traffic
- Seismic performance
- Cost.

Figure 2: Overhead Construction Over Uninterrupted Traffic |
Challenges Posed by Urban Construction. Construction
in an urban environment such as busy downtown Las Vegas requires
that projects minimize lane closures, detours and traffic interruptions.
Key to minimizing these impacts is minimizing the duration of construction.
Fortunately, precast segmental construction using an overhead gantry
offered unquestionable advantages in this regard over the other
construction techniques considered (Figure 2).
Overhead erection minimized impact on the structure’s footprint
and the work envelope required for construction. Segments for the
subsequent spans in the erection cycle were supplied from the previously
completed span, so the work envelope below the deck level was minimized
to a small quantity of “below-deck” false work that
was used to erect the pier segments and, in some cases, to provide
lateral stability during erection.
Minimum Required Clearances. The resulting segmental
alternative provided the structural solution with the minimum horizontal
and vertical clearance requirements for the overall interchange
layout. Further reductions in encroachment were realized when the
pier caps were eliminated at all the interior spans. Pier caps were
required at the expansion piers, however. This type of hinge support
was selected over an “in-span” hinge because we believed
it has inherently greater reliability during a seismic event.

Figure 3: Positive Aesthetic Appearance of Ramp in Service |
Aesthetics. The positive aesthetic appearance
of the trapezoidal segmental box solution needed minimal architectural
enhancement (Figure 3). The treatments used were in the form of
fractured fin texture, which was applied to the surfaces of the
piers and abutment back-walls; therefore, the aesthetic impacts
did not result in the cost penalty that was attached to some of
the other alternatives that were evaluated.
Seismic Performance: The Integral Superstructure-Column
Connection. Our client, the Nevada Department of Transportation
(NDOT), expressed its preference for an integral superstructure-to-column
connection right from the start because it provides additional redundancy
in the framing system, so greatly improves structural response during
a seismic event. Such a connection provided a greater lateral capacity
overall when compared to the other conventional framing alternatives
that were considered. In the case of the Spaghetti Bowl, this larger
seismic capacity gives the ramp structures in the interchange a
higher level of serviceability in the event of an earthquake.
Design and Construction of the Integral
Superstructure-Column Connection
Although this integral connection could be constructed without adversely
affecting the cost competitiveness or time efficiency of segmental
construction, special details had to be incorporated to accomplish
frame integrity. The integral pier segment was subject to the following
unique conditions compared with the traditional pier segments supported
on bearings:
- Less space was available for reinforcement and post tensioning
anchorages because the precast segment had a large center block-out
reserved for the cast-in-place integral connection with the column.
- Transverse post tensioning and additional reinforcement was
required to resist vertical loads because of the single column
support.
- The plastic hinge moment from the column had to be resisted
by extra reinforcement projecting into the pier segment and the
cast-in-place beam-column joint.
- The support condition and forces would vary during the construction
phases before the final integral condition could be accomplished.

Figure 4: Integrated 3D CADD Drawing of Face (Front/Rear)
Reinforcement. |
Acknowledging the pier segments’ importance, we addressed
these technical challenges by using unique techniques for designing
and detailing. Computer aided design and drafting (CADD) was used
to expedite the design and improve the accuracy of the reinforcement
design. Perspective renderings, such as the one shown in Figure
4 of the integral pier segments, were created to help potential
contractors understand the design in order to prepare their construction
bids.
The bridge erection sequence required special considerations to
accommodate the integral superstructure-column connection. Ducts
of longitudinal post tensioning bars were inserted through the segment
diaphragms and the column reinforcement cage. The concrete was then
placed through the deck opening into the segment to achieve the
integral connection between the precast segment and the cast-in-place
column. Upon completion, the launching gantry was then advanced
forward and fastened on top of the integrated segments. To complete
the cycle of span assembly, the typical span segments were erected
individually while supported by the overhead launching-gantry. The
gantry spanned between the previously assembled integral pier segments.
Special Design Characteristics
The special characteristics of this project reflect how the different
issues presented above were addressed.
Selecting the Cross Section of the Segments. The
cross sections had to specifically satisfy the single-lane ramp
and double-lane ramp structural requirements. ASBI/PCI AASHTO standard
boxes were considered; however, they did not meet the project-specific
seismic design requirements and they required a greater footprint
for the piers. As a result, custom designed cross sections were
developed.
Frame and Column Selection. Continuous frames were
proportioned to balance the conflicting effects of creep, shrinkage,
temperature and seismic demands. The designers by and large found
that creep and shrinkage produced the maximum moment demands on
the outer piers of the continuous frame. In some cases, erection
loads were found to control. Because seismic demands did not govern
the column designs, an added challenge was introduced to the seismic
resistant design.

Figure 5: Ramp N-W Showing Cross-Section of the Deep Segments
and Longitudinal Elevation of Transition Between Span-by-Span
and Cantilever Construction |

Figure 6: Ramp N-W |
Remember that seismic design criteria were based on the capacity
design principle of the “weak column-strong beam”; therefore,
we had to enable column plastic hinging while also ensuring that
the superstructure and the foundation remained elastic. The design
objective was to keep the substructure stiffness as consistent as
possible. In some specific cases, column casings were required to
increase the flexibility of the shorter piers. The overall goal
was to keep the plastic capacity of the columns within manageable
limits so that a practical superstructure and foundation design
could be achieved (Figures 5 and 6).
Checking the Columns for Estimated Erection Loads. We
had anticipated that the curved alignment of the ramps was going
to put additional demands on the piers. An estimate of the eccentricities
resulting from the horizontal offsets of the gantry’s tangent
alignment and the ramps’ curved alignment was developed. These
offsets, coupled with the assumed gantry reaction magnitude and
location, formed the basis of the column demand estimate.
Keeping in mind that the designer has no way of predicting exactly
what equipment the successful bidder will use to erect the bridge,
erection schematics were offered to the contractor in the bidding
documents. Analyses of this erection scheme resulted in some cases
where construction controlled the design of the piers and once the
real erection loads were known, some modifications were necessary.
Incorporating these changes into an efficient design required the
team (owner/designer/ constructor) to maintain a delicate balance
in order to develop a solution that was suitable for construction
and yet maintained the design intent of the single shaft pier. This
balancing act continued to be sorted out as the project matured.
Many Contributed to this Successful Project
In closing, it is only proper to acknowledge the support we received
from NDOT in its encouragement of a segmental solution for this
complicated urban interchange project. Acknowledgement is also due
to Meadow Valley, the general contractor, along with its segmental
contractor, Walter-SCI, and construction engineer, Finley McNary
Engineers, for the execution of the project; and to Figg Engineers
for their field supervision support to NDOT. This project is a benchmark
for further applications of segmental construction in urban areas,
as well as in areas of high seismicity. |