| John F. Kennedy International Airport (JFK) is a primary gateway
to densely populated New York City for people from all over the
world. To improve access to the airport and relieve traffic congestion
in the city, the airport’s operator, the Port Authority of
New York and New Jersey (Port Authority), undertook the design and
construction of Airtrain JFK, a nearly 13-km (8-mile) long elevated,
dual-track light-rail system that ties the airport’s central
terminal area to major transportation systems, remote parking lots
and car rental facilities.
The Port Authority retained PB as its general engineering consultant
for the design-build-operate- maintain (DBOM) program used to procure
Airtrain JFK. We provided a wide range of planning, preliminary
design, environmental analysis, construction management support,
and procurement support activities; and engineering support to the
Port Authority staff in reviewing the DBOM contractor’s design.
PB continues to support Port Authority staff members at a program
office.

Figure 1: AirTrain Alignment |
Principal Features of the Elevated Guideway
Airtrain JFK comprises three branches (Figure 1):
- A 5.0 km (3 mile) -long line extending west from JFK to a car
rental area at Federal Circle then south to remote parking and
on to the Howard Beach Station of New York City’s subway
system.
- A 4.8-km (2.9-mile) line extending west from the airport property
to Jamaica Station, Queens, a major transfer station to New York
City’s subway system, and the Long Island Rail Road, a heavily
traveled regional commuter rail line.
- A 2.9-km (1.8-mile) loop within JFK’s central terminal
area.
Performance Specifications. The light rail system
envisioned during preliminary design was a continuous aerial guideway
utilizing direct fixation track work supported on concrete or composite
steel box girders. When the performance specifications were being
prepared, it was determined that no single existing code or standard
applied to such a structure, so the American Association of State
Transportation Officials (AASHTO) Specifications for Highway Bridges
and its applicable guide specifications were used with modifications
to incorporate light rail loads and effects, including:
- Light rail vehicle weight and impact factors
- Centrifugal force
- Rolling force
- Longitudinal braking and traction force
- Rail/structure interaction force
Such a system required analysis for interaction between the rail
and structure for the effects of:
- The structure expanding and contracting beneath the rail
- One rail breaking
- The structure restraining the rail from displacing radially
on horizontal curves.
The standard AASHTO loading combinations were used with rolling
force added to the loading combinations with live load, and rail/structure
interaction forces added to the loading combinations with thermal
forces. Loading combinations for service load design and load factor
design were included in the project design criteria.
Seismic Considerations. New structures at JFK have
been designed for seismic forces since 1987, and seismic provisions
were an important aspect of the design criteria. Due to the presence
of deep loose sands at JFK, soil borings indicated the potential
for liquefaction up to a depth of 6 m (20 feet) under a design seismic
event that had a peak rock acceleration of 0.15 g.
In addition to calling for the conventional design for forces and
displacements, the seismic design criteria also required that additional
limitations be met by the foundations and superstructure in order
to allow the system to return to operation shortly after a seismic
event. These limitations avoided misalignment of the guideway and
limited repairs to only the track work.
Design criteria for the foundations required the DBOM contractor
to take additional borings, prepare a geotechnical report and select
a foundation system. Sufficient borings were given in the request
for proposal (RFP) to allow preparation of bids; however, a contingency
fund was established to address unknown soil condition or utility
interferences risks.

Figure 2: Type 1 Box Section |

Figure 3: Type II Box Section |

Figure 4: Multiple Span Continuous Units |

Figure 5: Completed Structure |

Figure 6: Traffic was maintained during construction |

Figure 7: Tight curvature called for balanced cantilever
construction |
Preliminary Design
To ensure that Airtrain JFK was procured under a competitive process
and the successful bid was based on an awareness of key site constraints,
the preliminary design of the elevated guideway was based on a modularized
twin- or single-box concrete type girder that demonstrated the need
to erect the structure with limited disturbance to the surrounding
existing infrastructure facilities. The RFP required that the final
design be selected and completed by the successful bidder. A composite
steel box with a composite reinforced concrete deck slab was included
as an alternative in the RFP.
For the concrete option, overhead launching trusses in the form
of erection gantries were envisioned for installing individual full-length
girder sections. The trusses would use gantry supports placed on
top of the previously-constructed pier caps to launch the girders
onto their proper positions, and they would be moved along with
the gantry supports hopping from pier to pier.
Features of the DBOM Final Design
The two main differences between the DBOM final design and the preliminary
design in the RFP were that the guideway superstructure was precast
segmental construction that utilized seismic isolation. The superstructure
is comprised of two typical cross-sections-Type I and II Box Sections
that support a single or a dual-track configuration respectively
(Figures 2 and 3). Typically, individual spans were longer in the
DBOM design and post-tensioning tendons were applied across span
closures to create multiple-span continuous units (Figure 4). The
longer spans and continuous units between expansion joints made
it more challenging to control the possible gaps that could result
from a rail break. The DBOM car supplier had to accept the anticipated
rail break gap or, as an alternative, the contractor had to provide
a rail-break detection system. Figure 5 shows a general view of
the completed structure and the design vehicles.
The majority of the guideway was built span by span with cranes
and erection trusses so that traffic on adjacent streets and highways
could be maintained (Figure 6). Some portions that are on tight
curvature or have longer spans were built in balanced cantilever
(Figure 7). The substructure design was often required prior to
the superstructure design, so prudent design assumptions had to
be made by the substructure designers and subsequently verified
as the superstructure design was finalized. For example, on highly
curved structures, creep and shrinkage redistribution of support
reactions on the piers occurred transversely between two bearings
at the same line of support, as well as longitudinally between piers.
Seismic isolation was achieved by using lead-rubber bearings that
allow the superstructure to “float” during a seismic
event. For non-seismic loading, however, the bearing must be fixedlaterally
relative to the track centerline with movement limited to a 3-mm
(1/8-inch) range. The DBOM contractor developed an elastic restraint
system that would withstand non-seismic loads with an appropriate
factor of safety, but would fail at design level seismic loads,
thus freeing the structure to float and avoid potential damaging
seismic forces. For this reason, correct modeling of the guideway
structures and an especially high degree of accuracy in the structural
analyses were important.
Technical Review Issues
The technical review of the DBOM contractor’s structural design
revealed several areas of concern, including those discussed here.
External Tendons. In the proposed use of external
tendons in the span-by-span constructed portions of the guideway,
it was understood that large deflections and joint openings were
expected before the ultimate strength of any girder section was
reached; however, the ultimate strength of the superstructure was
based upon a crushing failure of the concrete at the segmental joint.
This is a non-ductile failure mode. Given the fact that the width
of the compression flanges is significantly less for the guideway
superstructure than that of a regular highway superstructure, the
Port Authority team felt that it was prudent to require the DBOM
contractor’s designers to perform a strain compatibility analysis.
The Effects of Post-tensioning and Secondary Forces on a
Highly Curved Structure. An independent three-dimensional
analysis of stresses and bearing reactions was conducted for highly
curved portions of the aerial guideway that were to be constructed
using the span-by-span and balanced cantilever methods. The analyses,
which accounted for locked-in construction forces and reactions,
creep, shrinkage and elastic shortening, confirmed that highly unbalanced
and even uplift forces could result at those bearings supporting
highly curved superstructure if construction procedures were not
properly planned and executed.
The Application of the AASHTO Guide Specifications for Seismic
Isolation Design. The DBOM contractor selected a complex
multi-mode analysis including combined bearing-pier- foundation
system damping values for the guideway system. The independent verification
of this was a significant issue. The Port Authority team developed
an independent seismic analysis for selected critical spans and
piers that used the more simplified single mode spectral method
to check the damping values and parameters. Additional complexity
was added to all of the models because the continuous rail joined
several multi-span units together.
Conclusions
The DBOM contractor’s approach was a valid option for a complex
urban project such as Airtrain JFK. Lessons learned from the Port
Authority’s perspective may be summarized as follows:
• The owner’s role is vital in overall project management,
construction management oversight, and project coordination with
all affected agencies, tenants and communities.
- The submittal approval process customary to U.S. public works
projects must be modified for DBOM contracts to accommodate the
sequence and pace of the design and construction process.
– The owner’s engineers and the DBOM contractor’s
designers should be prepared to meet frequently to resolve questions.
– Independent analyses can be an expeditious way to identify
and resolve technical differences between the DBOM contractor’s
designers and the owner’s engineers.
– Up-keep and maintenance of design documentation for reference
must be well planned.
- The obligation to conform to project criteria and the prerogative
to elect means and methods in design and construction must be
left with the DBOM contractor and its designers.
- The DBOM contractor must be required to coordinate the work
performed by its designers and their subconsultants and subcontractors.
Acknowledgements
A number of consulting firms and individuals were involved in the
planning, design and construction of this project. The focus of
this article is on the structural aspects of the guideway; therefore,
so too are the acknowledgements. The preliminary design team was
led by Zuss Izakson, a senior supervising structural engineer for
PB. Joseph Kelly, senior consulting engineer for the Port Authority,
supervised the preparation of structural design criteria. |