| City officials of Clearwater, Florida, envisioned an architecturally
significant structure to replace an ailing bascule bridge when they
first considered the Memorial Causeway Bridge several years ago.
Built in the early 1960s, the original bridge was notorious for
getting stuck in the raised position and blocking traffic on the
main downtown roadway. The leaders of this tourist-driven community
decided that they could not wait until the end of this decade for
the bridge to be replaced as Florida Department of Transportation
had planned and, instead of a lower cost AASHTO girder bridge, they
wanted a signature structure that would leave a lasting impression
on the tourists who cross the bridge to get to Clearwater Beach,
the city’s main attraction.
To achieve these two goals, the city struck a deal with FDOT —
the city would find the money to acquire the necessary right of
way and provide the design for the bridge, and FDOT would procure
and manage construction. City officials tapped several sources to
acquire the funding, including city, county, state and federal funds,
and they hired an architect to work with the bridge designer and
produce landmark design for the city’s gateway to the beach.
After several years of planning and design, the city presented FDOT
with a design for a cast-in-place segmental concrete bridge. It
consisted of a twin box girder section 34 m (112 feet) wide and
depths varying from 2.7 m (9 feet) in the center spans to 5.4 m
(18 feet) at the pier tables. The bridge was 690 m (2,300 feet)
long and had nine spans. The main span was 108 m (360 feet) long
with a 22-m (74-foot) clearance over the channel at high tide.
Under a joint project agreement, the city deposited its funds with
FDOT. The FDOT’s portion of the agreement was to hire a consultant
to perform construction engineering and inspection and a construction
firm to build the bridge. In May 2001, FDOT selected PBCS as the
CEI and in September 2001 put the project out for bid. Much to the
city’s surprise, all of the bids came in above the engineer’s
estimate. There was much speculation about the contract time given
for the project — 800 days — and its effect on the bid
prices, which ranged from $47.7 million to $61.0 million.
Initially, city officials were doubtful that the project would be
built. They had agreed to put up a contingency amount equal to 10
percent of the bid price, but when the bids came in over the engineer’s
estimate, the city did not have the required funding. After a series
of City Commission workshops, however, additional funding by FDOT,
and indications from the low bidder that there were value engineering
savings to be had, the City and FDOT agreed to award the construction
contract to PCL Civil Constructors in late November 2001.
As soon as the construction contract was executed in early December,
PB, FDOT, the City of Clearwater and PCL had the first round of
meetings during which PCL presented a value engineering package
that ultimately preserved the aesthetics the City had worked so
hard for while reducing the costs by $1.34 million. To PCL’s
relief, the agreement also included a 60-day delay to the construction
start date and a contract time extension of 60 days. The agreement
called for FDOT and PCL to share the savings equally.
The Value Engineering Proposal
PCL’s value engineering proposal called for changes to the
substructure and superstructure of the bridge. In fact, the changes
were so significant that PCL’s designer became the engineer
of record under the agreement.
Substructure Changes. In the substructure, the drilled shafts were
changed from 1.5-m (5-foot) diameter to 2-m (6.5-foot) diameter
shafts. The original design was bound by guidelines that limited
the size of the drilled shafts to ensure competition among the bidders,
but now PCL was not bound by the same requirement and was able to
capitalize on the abilities of a qualified drilled shaft subcontractor.
As a result of this change, the total number of drilled shafts was
reduced from 88 to 24, leading to significant time and cost savings.
In turn, the footing sizes were reduced from over 765 m3 to 500
m3 (1,000 cubic yards to 650 cubic yards). Lastly, the shape of
the columns was changed very slightly to maintain consistency, allowing
the same forms to be used on all of the columns. The total savings
for the substructure changes was approximately $577,000.
Superstructure Changes. In the superstructure,
the changes were more discrete but no less significant:
- To accommodate the tight construction schedule, the erection
method was changed from balanced cantilever construction on each
span to a combination of balanced cantilever and construction
on falsework. This change allowed the schedule to be met with
two pairs of form travelers.
- The overhang portions of the bridge decks were shifted to create
a symmetrical box, allowing for a more economical form system.
- The amount of post tensioning was increased and the thickness
of the web walls was decreased, resulting is a lighter section,
that in turn, reduced the cost of the form traveler and of material.
- The bearings at four of the columns were replaced by Freyssinet
hinges at two of the columns and fixed integral connections at
the other two.
The total savings from the superstructure changes was approximately
$750,000.
Lessons Learned
The purpose for delaying the construction start date was to allow
the value engineering design to be completed and reviewed first.
We quickly found that the time frames proposed by the contractor
for design production were not reasonable. As a result, construction
began without a complete set of approved plans and the engineering
has been chasing the construction all the way. Without the approved
design plans, the construction engineering (the contractor chose
a different consultant than the new Engineer of Record), was constantly
driving the construction schedule. On more than one occasion, the
construction could not proceed because the contractor was waiting
for a shop drawing to be produced or approved. In addition, the
tight schedule probably resulted in more errors in the shop drawings
than would have occurred otherwise.
We also believe, however, that the project would not have gone forward
without the value engineering proposal. The additional work and
effort by everyone involved in the production, review and implementation
of the value engineering change proposal was a good trade.
One of the most overlooked advantages of the value engineering proposal
is that the owner was able to transfer design problem risk to the
contractor and limit costs for design problems to the roadway portion
of the project only. On a project with very little funding for overruns,
this was a significant achievement. For future segmental projects
though, planners should give serious consideration to the design/build
concept. Our experience with the value engineering proposal shows
that most of the savings came from changes that were suited specifically
to PCL. Under a design-build concept, the owner may have enjoyed
even greater savings. |