Parsons Brinckerhoff
Worldwide LocationsContact PBLegal NoticeSite MapHome
PB Websites search Advanced Search
MarketsServicesAbout UsPeople and CareersNews and EventsResearch LibraryProjects
PB Network Email This Page
Go To Other Issues | Contact PB Network | Print This Article 
<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Segmental Bridges
February 2004 • Issue No. 57 • Volume XIX • Number 1
Design and Construction
Melbourne City Link – Segmental Design and Construction
By Jim Rozek, Sydney +614-818-531, rozek@pbworld.com
Some of the more unique design and construction features of the Bolte Bridge and 4.5-km-long twin viaducts are presented in this article. These structures were major components of one of the largest infrastructure projects undertaken in Australia in recent years.


Figure 1: Bolle Bridge, with Melbourne in the Background

The $A 2.0 billion Melbourne City Link Project (MCLP) was Australia’s largest infrastructure road ever undertaken under the build-own-operate-transfer (BOOT) process. The project featured 22 km (13 miles) of eight- and six-lane new, widened, or existing freeway. Its landmark feature is Bolte Bridge, an architectural and engineering accomplishment that is unique because of its twin 140-m (462-foot)-high non-structural towers above the center span (Figure 1). The outer barrier of the bridge has a metallic edge strip, and both the superstructure and the towers are painted. The second major feature of the project that involved segmental construction is a 4.5-km (2.7-mile) -long viaduct constructed from precast match-cast elements.

PB was a member of the Office of the Independent Reviewer (OIR), which had a statutory role in the design and construction of the MCLP. The OIR had a unique contractual arrangement as it was under contract to the state government of Victoria as well as the owner/operator of the 34 year concession, Transurban. PB was brought into the role because of its experience in big bridges and mega projects.

Design and Construction of Bolte Bridge

Bolte Bridge is one of the largest balanced cantilever cast-in-place box girder bridges in Australia. The balanced cantilever method of construction involves casting large concrete box units symmetrically from the top of substructure, thus maintaining a balanced condition. It utilises a complex temporary travelling formwork.

Bolte Bridge comprises twin structures, each a 490-m (1,618-foot)-long, 4-span bridge with two main spans of 173 m (571 feet) and side spans of 72 m (238 feet). The bridge superstructure has a single-cell box girder 8 m (26 feet) wide and up to 12.7 m (42 feet) deep. It provides a minimum vertical clearance of 29 m (69 feet).

Foundation Design and Construction. The steel pile foundation used for the bridge had 1200-mm (4-foot) -diameter piles up to 50 m (165 feet) long driven through the compressible Coode Island silts. The top 15 m (50 feet) were mucked out and filled with concrete to provide the flexural capacity and connection to the pile cap.
The center pier island was man-constructed to provide a work platform and protect the bridge from ship collision. Its pile cap contained more than 3000 m3 (3,900 cubic yards) of concrete and was placed in one 24-hour continuous pour.

Superstructure Design and Construction. Interesting superstructure features included large fillets at the top of each web to house the cantilever prestressing anchorages. A total of 102 prestressing ducts were located in three levels within the top flange and a bottom flange that varied from 300 mm to 1400 mm (1 foot to 4.75 feet) at the center pier.


Figure 2: Center Pier Construction with Traveler Forms

Major temporary works involved in construction were the eight deck form-work travellers fabricated for this project (Figure 2). Four operated from the main center pier and four from the side piers. The travellers consisted of three elements:

  • A top support structure that carried the external forms and was advanced by hydraulic equipment
  • External forms made up of a bottom flange soffit, external walls and the top flange wing soffit
  • Internal forms that were self contained and consisted of support beams and a rolling form for the top flange support and inner walls of the web.

Each new segment was post tensioned onto the existing structure by two tendons, one located at the top of each web. The other end of the tendons was anchored in face anchors at the leading end of construction on the other side of the pier. All prestress of the cantilevers during construction was in the top flange. The cantilevers were joined by a closure pour, which was post tensioned in the bottom flange from “blisters” in the bottom flange of the cantilevers.

The superstructure was cast integrally with the hollow center piers to form a fixed connection. The pier heads at piers 2 and 4 had sliding bearings that used a temporary prop on the out of balance side and temporary fixing connections during construction (Figure 3).


Figure 3: Side Pier-Balanced Cantilever with Prop

Figure 4: Elevated Roads - Segmental Construction

Figure 5: Mainline Substructure Construction

Tensioning Procedures. Ninety-eight tendons are in the top flange for the main spans and 32 in the bottom flange. There are 15 to 19 strands in each tendon. Tendons were grouted as soon as practical, but not more than two weeks after placing in sheathing. Grout for filling prestressing sheathing comprised of cement, water and an admixture methocel was added. Just prior to grouting, the sheathing was blown clean with dry oil-free compressed air.

Elevated Roadway: Match Cast Segmental Design and Construction


The twin elevated roadways weave their way from the Tullamarine Freeway over the Upfield Railway line, along Moonie Ponds creek to the Bolte Bridge, and contain five interchanges. The original concept for the viaduct utilised a superstructure with precast super ‘T’ beams; however, the contractor opted to use a match cast, precast, prestressed segments (Figure 4) This was the first structure in Australia to fully utilise external longitudinal post-tensioning.

The twin viaducts included 203 45-m (149-foot) -long spans, each consisting of 13 segments weighing up to 77 tons. There were two pier segments, eight typical sections and three deviator segments. The superstructure was simply supported on more than 200 mainline piers supported by some 4,500 precast concrete piles (Figure 5). The piers ranged from 5 m to 20 m (16 feet to 66 feet) above the ground. The spans were supported on elastomeric bearings, and were post tensioned with external tendons encased in a single sheath system through deviator blocks and pier segment diaphragms.

The superstructure was designed to AASHTO Guide Specifications, and included time dependent construction sequencing, permanent loads, and the effects of long term forces due to creep, shrinkage, and long term relaxation. These were combined to establish the controlling loads.

A typical span consisted of 10 tendons with 31 strands. One tendon was anchored to the first deviator block from the pier segment. The vertical and horizontal deviations occurred at the outer deviation blocks while in the center, the tendons passed with no deviation. The pier segments and the deviator blocks deviated the tendons and distributed the forces in the superstructure.

Including nine ramps, also constructed segmentally, more that 3600 segments were cast at a yard that was the largest in the southern hemisphere during its operation. All segments were cast in a 20 month period. Average production was about 12 segments per day from 14 moulds. Segments weighed between 45 and 80 ton and varied in width from 9.6 m to 17.3 m (32 feet to 57 feet). The moulds were aligned in bays such that each mould would cast a trapezoidal unit against the previous cast unit, that is, against the same unit to which it would be connected.

The first spans took up to two weeks to erect to overcome the start up difficulties, the learning curve as well as the site conditions encountered, as the spans were erected over electrified tram and commuter train lines, crossroads, and creeks. As the work became systematic, an average erection rate of five spans per week was achieved.


Figure 6: Mainline Underslung Erection Truss

Spans were erected utilizing a pair of underslung trusses for each carriageway. The precast segments were placed onto carriers on the underslung truss, and supported on a three point system on the trusses (Figure 6). As segments were placed on the truss, the segments were aligned and joined “dry.” Multiple shear keys provided shear transfer and facilitate alignment. The keys were not visible from outside of the completed span for aesthetic purposes.

Related Web Site:
Further information is on MCLP is available at the two following Web sites, the first operated by the 34 Concession Owner/ Operator, Transurban, and the second by the Victorian government.
http://www.transurban.com.au
http://www.citylink.vic.gov.au

Fine tuning was performed with small hydraulic jacks and shim plates. After all segments were aligned, the tendons were stressed. The load was then transferred from the trusses onto the bearings at the pier head. The trusses were advanced to the next span. All stressing was usually done before the trusses were moved.

Concluding Remarks

The Western Link of the MCLP, which included Bolte Bridge and the elevated viaduct, opened to traffic in April 1999. The delivery of these two elements in an ambitious program was a reflection of the confidence and reliability in the concrete segmental technology.


Jim Rozek was operations director for the OIR from 1996 to 1999. He is currently working on the 13 km, Parramatta Rail Link in Sydney, which is the subject of an article in PB Network Issue No. 56, July 2003, "Sydney’s Parramatta Rail Link: Moving Forward."

<< Go To Previous Article | Table Of Contents | Go To Next Article >>
Go To Other Issues | Contact PB Network | Print This Article 
Markets  |  Services  |  About Us  |  People + Careers  |  News + Events  |  Research Library  |  Projects
Worldwide Locations  |  Contact PB  |  Legal Notice  |  Site Map  |  Home
© Parsons Brinckerhoff