| Tunnels are generally more expensive than bridges and at-grade
structures, so they may not be selected for some projects even though
they could result in a more sustainable project. In this article
we explore different forms of cost-effective tunnel ventilation
designs with reference to several tunnel projects. Such designs
would make tunnels more viable options, particularly when there
is a call for sustainable development. The resulting environmental
and societal benefits could outweigh the initial higher costs when
looked at over the life-cycle of the project.
Roadway Tunnels: Minimizing Costs and Environmental
Impacts
The type of tunnel ventilation system designed and the features
of the tunnel that affect ventilation can have a major impact on
the sustainability of a roadway tunnel.
Tunnel Ventilation Systems. In general, tunnel
ventilation systems can be divided into three major types, longitudinal,
semi-transverse, and full transverse.
Reference is made to the Singapore Underground Road System (SURS),
a 15 km (9-mile) –long, two-lane (in each direction) ring
tunnel around Singapore’s central business district with 17
underground entry ramps and 16 underground exit ramps. PB is the
concept design consultant for the entire project. For a sustainable
design, the ventilation system was recommended to be a composite
of longitudinal system with point exhaust. Axial fans are housed
in a number of strategically located ventilation buildings with
easy access for inspection and maintenance. Supply air is injected
into each tunnel section through a Saccardo nozzle at constant velocity
in the direction of traffic flow, resulting in a longitudinal airflow
that is then exhausted just upstream of the next ventilation zone.
Apart from significant saving in initial cost (US $200 million),
this concept uses the piston effect of the vehicles to self-ventilate
the tunnel, which lowers energy consumption and operating costs.
For immersed tube tunnels, proper design can significantly reduce
the services space and, hence, the submerged volumes of the immersed
tube tunnel. This was the case with the Western Harbour Crossing
(WHC) in Hong Kong, which comprises a 1.36-km (0.8-mile) long immersed
tube tunnel and 0.64-km (0.4-mile) -long cut-and-cover approach
tunnels. PB is the project designer responsible for the concept
design for the mechanical & electrical (M&E) system and
immersed tube tunnel. The tunnel ventilation system and the tunnel
services were optimized to reduce the air duct and the services
ducts inside the immersed tube tunnel. The tunnel was then re-configured
from a five-box tube to a four-box tube with integrated services
box and ballast concrete. This arrangement not only reduced the
overall dimension of the immerse tube but also reduced the seabed
preparation.

Figure 1: Stack Tunnel Arrangement-Eastern Distributor Tunnel |
Site Constraints. Sometimes it is not easy to
construct tunnels for a densely populated urban area, particularly
if they are in a soft ground and located very close to the ground
level. Under such circumstances, a stacked tunnel may resolve the
land issues. This was the case with the Eastern Distributor in Sydney,
Australia, a 6-km (3.6-mile) -long route with a new 1.7-km (1-mile)
–long main tunnel and the 600 m (2,000-foot) -long Dacey Todman
Underpass (Figure 1). PB is the tunnel ventilation designer for
the project.
The main tunnel is a double-deck, dual three-lane tunnel with entry
and exit ramps. Due to a very stringent environmental requirement
at the tunnel portals (zero portal emission), a ventilation building
is located near each of the main exit portals to extract the polluted
air from the tunnel. This air is then exhausted vertically to the
atmosphere at a high velocity. This project is one of the major
sustainable developments in Sydney as it links northern and southern
Sydney via a narrow corridor in a densely populated urban area with
minimum portal emission to maintain air quality in the neighborhoods.
Use of Construction Adits. The selection of a
suitable ventilation system and the use of construction adits can
optimize the tunnel cross-section area and shorten the construction
period with multi-face working, as was the case with Tate’s
Cairn Tunnel in Hong Kong, a 4 km (2.4-mile) long, twin bore, two-lane
structure. PB is the project designer for the M&E
system. The structural and M&E design for the winning build/operate/transfer
(BOT) tender saved 14 months in programmed construction time and
an estimated 15 percent in the construction cost. A major contribution
to these savings was the deletion of ventilation shafts and the
use of two 500-m (1,650-foot) -long construction/ventilation adits
that allowed up to twelve faces to be available at any one time
for excavation. The semi-transverse ventilation system was designed
to take advantage of the two construction adits that intersect the
main road tunnels at their quarter points.
Access/Location of Ventilation Buildings. PB is
the M&E project designer for the 3.8-km (2.3-mile) -long Tai
Lam Tunnel in Hong Kong, the longest dual three-lane tunnel in the
world. There are 24 supply axial fans and 15 exhaust axial fans
housed in two ventilation buildings, one at each portal. Semi-transverse
ventilation system is adopted with point exhaust at the first and
the third quarter points. The construction program was shortened
by 12 months and a cost-effective design was achieved by the following
features:
- Space at the “crown” above the traffic gauge created
by constructing a concrete slab was used as an air duct.
- Point exhaust at the first and the third quarter points minimized
portal emissions.
- Ventilation tunnels constructed to one-quarter of the tunnel
length from both portals eliminated the need for vertical vent
shafts, which were not permitted because the tunnel runs under
a country park, and because of the associated site formations
and access roads.
Railway Tunnels: Cost-effective Designs Generate
Energy Savings
Several factors need to be considered to make a railway tunnel
a viable option for sustainable development, including those discussed
below.
Environmental Control System. Mainly two environmental
control system concepts are used for mass transit systems in tropical
countries: closed system (CS) and platform screen door (PSD). The
PSD concept, which has been used for several projects in South East
Asia, can generate substantial energy savings because it isolates
the air-conditioned platform environment from the hot, humid air
in the tunnel, improves the train-induced ventilation for tunnel
ventilation, and reduces the air leakage into the station when the
tunnel ventilation fan is operated. The overall effects are to achieve
a sustainable design, which can reduce the costs for plant space
and M&E equipment, reduce the operating cost on the environmental
control system and tunnel ventilation system, and enhance the station
environment and safety.
Site Constraints and Use of Temporary Launching Shaft.
Similar to road tunnel projects, it is difficult to construct
tunnels and stations in a densely populated urban area. The use
of temporary construction launching shafts as permanent building
can eliminate the need of additional site formation, access roads
and building structures. As part of Quarry Bay Extension for an
existing railway line in Hong Kong, the design made use of the launching
shaft, having it become a permanent ventilation building that incorporates
vent shafts, plant rooms and evacuation staircases. Extra space
and an assess route were not required for the permanent building.
As a sub-contractor, PB served as the mechanical and electrical
designer.
Rolling Stock. Rolling stock has significant impacts
on the design of a tunnel and the associated M&E systems. In
particular, the impacts due to:
Braking Methods. Of the two types of braking
methods, rheostatic and regenerative, regenerative results in sustainable
design in that it recovers part of the generated current to power
on-board auxiliary equipment, and the remainder is available to
the current distribution for other trains operating in the vicinity
of the regenerating train or back to the station power supply system.
If the line is not receptive, the excess energy is dissipated by
on-board resister grids to the tunnel. Rheostatic braking consists
of bank of resistors to dissipate the generated electricity in the
form of heat, which then heats up the tunnel air.
Train Air Conditioning. The configuration of
the train air-conditioning (A/C) unit—underneath the train
or ceiling mounted—has significant impact on the tunnel air
temperature and, in turn, the tunnel ventilation requirements. During
a train stoppage, the heat will accumulate in the annular space
along the train and the warmer less dense air will rise and collect
along the tunnel crown.
Ceiling mounted A/C units aggravate the problem because the heat
discharged by the upstream A/C units cascades along the train in
the upper regions of the annulus and can make the condenser intake
temperature of the downstream A/C units about 7° C (12°
F) higher than the average tunnel air temperature at the same location,
even with the operation of the tunnel ventilation system. In comparison,
underneath train A/C units can reduce the airflow requirement to
ventilate the tunnel during congested operation due to the stratification
effect and, in turn, reduce the associated civil provision.
Pressure Transient. Subject to the permeability
of the trains, pressure waves that can affect passengers inside
a train or on a station platform are generated when a train enters
or exits a tunnel portal, so need to be controlled to ensure a safe
and comfortable environment. Cost effective designs to mitigate
the pressure transient includes the control of train speed at portals,
the use of pressure relief dampers or pressure relief shafts, the
use of isolation walls and the use of special portal design.
Conclusion
Tunnels can be an important component of sustainable transportation
infrastructure design. Often they can readily meet two components
of the triple bottom line—environmental and social outcomes.
It is incumbent upon engineers to develop cost-effective designs
that satisfy the third component—economic outcomes. As illustrated
by projects discussed in this article, multi-discipline knowledge/input
is essential to arrive at a cost-effect design. We need knowledgeable
and innovative engineers to come up with ideas. We also need experienced
contractors who can work with designers to help come out with a
tailor-made cost-effective design. |