| Highway infrastructure lends itself to meeting sustainability
goals through the use of recycled material from highway components
removed from service and from other sources. In the U.S., state
specifications stipulate requirements for materials that can be
used in all state and federal-aid highway construction projects.
These specifications vary from state to state, depending on availability
of local materials and the perception of their suitability for engineering
application.
Indiana Department of Transportation’s (INDOT’s) standard
specifications permit considerable use of recycled materials. Indiana
has a number of steel manufacturers and heavy industries and, hence,
an abundance of byproducts, such as slag aggregates and fly ash,
that are suitable for highway/bridge construction.
Indiana’s Material Requirements
The amount of recycled material INDOT allows in each major construction
components is described below. The percentages cited are by weight.
Concrete Structures. As much as 77 percent recycled
materials is allowed for most concrete structures, and 50 percent
for concrete bridge decks. This can be achieved by partial replacement
of cement with fly ash and ground granulated blast furnace slag,
the use of air cooled (ACBF) or granulated (GBF) blast furnace slag
as coarse aggregate, and fine aggregate from foundry sand in decks
and ACBF in other components.
Steel. The steel industry currently utilizes steel
scrap at the rate of 95 percent to make structural shapes and plates
and at the rate of 47.5 percent to make steel reinforcing bars.
INDOT uses these rates.and does not have additional requirements.
Pavement. INDOT permits a maximum of approximately
50 percent recycled materials for Portland cement concrete pavement.
Bituminous pavement can comprise as much as 93 percent recycled
materials through the use of reclaimed asphalt and asphalt roof
shingles, ACBF or GBF coarse aggregates and ACBF fine aggregate.
Steel furnace slag may be used in HMA surface mixtures. Compacted
aggregate base may be 100 percent ACBF. INDOT specifications also
permit rubblization of the existing concrete pavement for use as
the base for a new Portland cement concrete pavement.
Earthwork. INDOT requires that the removed and
excavated materials, including soil and existing structures that
have suitable engineering properties, be used within the project.
If the materials are not suitable, the balance has to be borrowed
from sources outside the project and may consist of air-cooled or
granulated blast furnace slag, or crushed concrete, masonry, or
stone removed from an old structure or pavement.
Case Study
The project selected for the case study is a bridge replacement
and road realignment in a rural-suburban setting. The new bridge
is a 63-m (208-foot) -long prestressed concrete structure and the
road is a 1.45-km (0.87-mile) –long segment of a two-lane
collector roadway. They were designed to serve approximately 9,000
vehicles per day.
The client was interested in the use of recycled materials for
the project due to a potential unique funding opportunity. I took
the opportunity to develop a project-specific specification that
required the use of recycled materials based on the existing INDOT
framework. At the end of this brief research, I and everyone who
learned of the findings were surprised by how much recycled material
could be used potentially in highway construction.
Table 1:
Construction Materials for
the Case Study Project.  |
The breakdown of major construction materials for this project
is shown in Table 1. The maximum utilization of recycled materials
as sources of the construction materials as permitted by INDOT specifications
is also tabulated. It can be seen that as much as 97 percent of
the materials by weight could potentially be recovered materials.
Also, the optimal use of recycled materials in this project would
result in the net reduction of materials that would otherwise enter
the waste stream. This case study demonstrates that a highway construction
project can be an environmentally friendly endeavor.
Hurdles Remain
The funding opportunity, unfortunately, never materialized and
the project was constructed with typical federal-aid funds. As with
most highway projects, the lowest bidder used recycled material
in this project only when it is the most economically advantage.
The construction specifications and material availability already
existed for the potential significant use of recycled materials
in highway construction. The remaining hurdle for the use of recycled
materials is a thorough understanding of their short- and long-term
benefits and costs (environmental, societal, and economics). |