| Independent water and power projects (IWPP) represent a recent
trend in delivering the large-scale investments needed to sustain
the rapidly growing utility sector in the Middle East. Since the
first IWPP was implemented in 1998, more than half of the region’s
new capacity for power and water production has been purchased using
this model.
IWPPs rent power and water production capacity to a utility company
for a term of typically 20 years. Under such an arrangement, the
utility company does not have to raise large amounts of capital
to purchase a plant and then to operate and maintain it efficiently
throughout its life. Evaluation has shown that an IWPP can offer
tariff savings of up to 30 percent compared with a utility-owned
facility.
Modern power and water projects in the Middle East link an efficient
combined-cycle gas-turbine and steam-turbine power plant with thermal
desalination. The low-grade heat used to drive the multi-stage distillation
process used to extract fresh water from seawater is supplied as
low-pressure exhaust steam from the power plant.
Abu Dhabi, one of the United Arab Emirates, led the introduction
of IWPP. It has a successful program of such projects and at the
time of writing was evaluating bids for its fifth. PB has been involved
with each of these projects in various capacities. This article
relates particularly to the third IWPP implemented in Abu Dhabi,
the Shuweihat S1 project located about 250 km (150 miles) west of
Abu Dhabi city on the south coast of the Persian Gulf. (This project
was featured in PB’s 2003 Annual Report, page 4.)
The Shuweihat S1 IWPP has a planned capacity of 1500 MW of power
with 450,000 m3 (120 million gallons) of desalinated water per day,
the largest capacity single contract for a power and water plant
to date. The project was bid in 2000 and awarded in 2001 to a consortium
comprised of CMS Energy and International Power. Requiring a total
investment of $1,600 million, the plant is due to become fully operational
late in 2004.
PB was selected by the developers to develop their bid with the
engineer/procure/construct (EPC) contractor, a consortium of Siemens
AG of Germany and Fisia Italimpianti of Italy. Subsequently, we
acted as owners’ engineer, responsible for design review and
supervision of site construction and commissioning work.
The IWPP Developer’s Challenge
The significant difference between independent water and power
projects and utility procured projects is in the competition for
the work. Independent projects are awarded to a developer who will
not only install a plant but also operate it for a long period.
This arrangement profoundly affects the way such projects are bid
and the structure of contracts they incorporate.
To win the contract for supplying water and power, the bidders
need to convert the utility’s technical outline and commercial
definition into a detailed technical and commercial proposal offering
the capacity for the minimum tariff. As can be appreciated, this
is a complex process because the developer must select an appropriate
design, establish a price for its construction and fund the investment.
Funding is usually secured from a group of commercial investors,
usually including international banking groups.
Minimising the tariff for power and water in the Middle East, where
fuel costs are low, has conventionally been achieved by minimizing
project investment cost. This has normally meant offering a relatively
inefficient but low-cost plant that results in more wasteful use
of natural resources and higher emissions of carbon dioxide (CO2)
and other pollutants. For the Shuweihat Project, PB and the developers’
technical team proved that an alternative was possible.
The Difference with Shuweihat
The Shuweihat bid by CMS and International Power worked differently
from the start. The technical team, comprising specialists from
the developers, their contract modelling advisor and PB, explored
possible plant concepts early in the bidding process. Despite the
larger than usual group, a healthy constructively competitive team
spirit grew up committed to winning.
In this atmosphere no options were discounted until they had been
demonstrated to offer inferior financial performance, not merely
for first cost but for life cost. This open environment resulted
in the team overturning the conventional lowest first cost approach
and demonstrating that despite low fuel costs, a much more efficient
and sustainable plant offered the lowest life cost.

Figure 1: Conventional Process |

Figure 2: Improved Process |
Finding the Best Solution
As the team worked on optimising the design, a subtle but significant
thermal loss was identified between the power plant and the desalination
facility. The challenge to reduce this loss was “thrown down”
at the end of a meeting, and PB’s specialists left determined
to find a solution.
Even before we completed the two-hour return journey, a novel idea
had been conceived and rough estimates of its value computed. A
modification to existing, proven technology was involved, however.
We had to convince ourselves that the benefits were real before
taking our solution back to the team.
The mismatch between the cycles arises as the operating temperature
of the desalination process determines the temperature of the steam
condensate returned to the power cycle. This hot condensate is pumped
back to the gas turbine heat recovery steam generator (HRSG) to
be reheated and evaporated as part of the steam cycle. The high
temperature of the condensate limits the energy that can be extracted
in the HRSG, increasing cycle losses to the stack.
The PB invention combines the recovery of heat from the hot condensate
back into the desalination cycle, reducing steam consumption in
the distiller with cooling of the return condensate to the HRSG
allowing more heat to be recovered from the gas turbine exhaust
gases. The combined effect is to improve the overall power and water
production cycle thermal efficiency. The conventional and improved
processes are illustrated by Figures 1 and 2.
The hot condensate is cooled in a conventional heat exchanger with
a flow of cool distilled water from the distiller. The reheated
distilled water is then recycled into the distiller so that its
heat is recovered into the distillation process. The equipment required
for the invention is all conventional process equipment; but the
modification to the distillation process is novel and needed careful
evaluation.
Our engineers spent several days modifying analytical software
to check the impacts of the idea on the power and water cycles.
When the full analysis was completed the benefits were found, if
anything, to be larger than preliminary estimates. The concept was
scrutinised further—had a fatal flaw or adverse impact on
the distillation process been overlooked?
Finally, confident of the work, the idea was introduced to the
rest of the technical team, with us expecting serious reservations
and probable rejection. True to form, the group gave the idea a
searching examination. It was then incorporated into the bid. Eight
months later the CMS Energy International Power consortium was awarded
the project, gaining part of their competitive advantage from this,
now patented, PB innovation.
How Good is PB’s Innovation?
The new cycle modification has a number of benefits:
- Economic impact: Reduces fuel burn by up to 2 percent, and
pays back the small additional investment in a few months
- Environmental benefit: Reduces CO2 emissions by up to 2 percent,
and would avoid 3 million tons per year of CO2 emissions if applied
to 30 percent of existing power and desalination plant
- Societal Benefit: Demonstrates that sustainability can be self-financing.
Although the gains of this innovation appear small, the subsequent
award of the project has changed the way purchasers and bidders
have approached later IWPPs. The longer-term effect has been to
focus developers’ attention on valuable improvements in sustainability,
however they are achieved.
The judgment of the market on the technology is relevant here.
Few projects have been initiated since 2001 in the Middle East but
confidence has recovered recently. Further, the Shuweihat project
has now reached an advanced state of commissioning and the PB technology
has been proven to perform as predicted in 2001.
Lessons Learned
- Early involvement of specialist skills offers projects the
best improvement in sustainability.
- Contribute new or unusual ideas wherever they offer benefits.
- Keep the whole solution in view; gaps between technical areas
may hide opportunities.
- Ensure that proper evaluations of costs allow sustainability
to sell itself.
- Seek opportunities to leverage sustainability gains though
advocacy and publicity.
|