| Rehabilitation of the Bulimba Creek Oxbow, and associated floodplain,
as part of the Port of Brisbane Motorway project (PoBM) has proven
that environmentalists and industry can work together to achieve
an outcome that is beneficial to all. The rehabilitation strategy
they came to support has significantly raised the benchmark for
water quality treatment and environmental management on major road
projects in Queensland. Water management strategies included the
adoption of treatment devices not normally associated with motorway
stormwater systems. These devices are now recycling motorway runoff,
which is providing a valuable inflow, rejuvenating the existing
wetland, and enhancing an ecosystem that supports native flora,
fauna and migratory birds. In addition, sustainable water quality
treatments and environmental management strategies were applied
to the entire length of the project.
Background
Three years in the making, the first stage of the PoBM was opened
in December 2002—well ahead of time and under budget, and
with minimal disruption to the community and environment. The project
was a massive undertaking that resulted in 5 km (3 miles) of motorway,
12 major new bridges and Queensland’s first tri-level interchange.
The design and construction was delivered by the PoBM Alliance,
which was made up of Queensland Motorways Limited, Leighton Contractors,
PB, and Coffey Geosciences. PB led the design team responsible for
many of the breakthrough outcomes that allowed the Alliance to achieve
its goals, and was responsible for environment, community consultation,
permits and approvals and technical site supervision. We recognised
and embraced the fact that sustainable development was vital to
the achievement of excellent engineering outcomes.
Community Concerns about the Bulimba Creek Oxbow
The Bulimba Creek Oxbow is bound on three sides by Bulimba Creek
and is adjacent to Doboy wetland and the village of Hemmant. Past
industrial use and the construction of rail embankment and public
utility services altered the area’s flood regime and subsequently
reduced the effectiveness of its filtering process. Embankments
had been constructed that separated the Oxbow waterway system from
the natural tidal flows, and areas of the system have been used
as waste treatment ponds for organic waste products from abattoir
(slaughterhouse) operations.
Despite this degradation, the local community, and Brisbane City
Council, and catchment groups, such as the Bulimba Creek Catchment
Coordinating Committee (B4C) and Brisbane Region Environment Committee
(BREC), recognised the potential for the floodplain and the function
it provides in the protection of the Moreton Bay area. These groups
raised concerns that the impacts from the PoBM would cause further
degradation to the area, knowing that stormwater runoff from highways
contains high concentrations of pollutants that are harmful to receiving
watercourses, and that the PoBM crossed or passed near a number
of waterways that form a unique matrix of freshwater, brackish and
estuarine habitats, including Bulimba Creek and its oxbow (Figure
1). In response, the alliance identified the opportunities and constraints
for the oxbow and developed a rehabilitation strategy to ”bring
back to life” the degraded habitat.

Figure 1: Port of Brisbane Motorway Crossing the Bulimba Creek Floodplain and Oxbow |
Rehabilitation Strategy
The rehabilitation strategy was driven by a project commitment
to rehabilitate off-road areas, including the oxbow, to a point
where there was zero negative impact. Our investigations identified
the existing natural and physical environment in the study area
and provided the following recommendations for rehabilitation:
- Remove existing bunds (embankments) and re-open the Oxbow,
returning it to a tidal system similar to its natural river flow
regime and allowing natural processes to flush accumulated sediments
- Remove dumped gravel within the Oxbow
- Remove surrounding landfill that promotes weed growth
- Maintain existing freshwater flows and increase flows where
possible during flood events to help flush salts from the tidal
zone of the floodplain. Additional freshwater flows through the
wetland will be achieved by “recycling” stormwater
run-off from the Port of Brisbane Motorway. A series of stormwater
treatment devices, such as wetlands, buffer strips and sedimentation
basins, will reduce pollutants in the run-off before it enters
the natural wetland system.
While the first three measures were straight forward, the fourth
one was not. In addition, there was a requirement to not increase
flood levels in the Bulimba Creek flood plain as a result of the
project. Typical treatment levels that have been adopted on similar
projects would not meet the high water quality objectives set for
the PoBM project, or could not be achieved at the minimal additional
cost we were limited to, so the design team had to approach stormwater
management in new and innovative ways.
Common Ground: Stakeholder Involvement
During the early design phase of the motorway, PB’s team
expanded negotiations with stakeholders to include the Oxbow. The
most successful (and valuable) aspect of the consultation process
was the involvement of B4C and BREC in the flood modeling design
meetings. The detailed two-dimensional hydraulic model with easily
interpretable graphical output provided the basis for meaningful
consultation between the Department of Main Roads (DMR), the B4C,
the BREC and the PBM Alliance. The final modeling indicated enhancement
to the freshwater wetland area by encouraging freshwater flood flows
to pass through the wetland. Increased flushing will improve the
health of the wetland. The final design represented a break through
in being a cost -effective solution that met environmental and hydraulic
objectives, and also the zero allowable flood afflux limits.
Some examples of innovative stormwater treatments our team specified
for the PoBM include:
- Providing water quality treatment devices that will capture
a 20,000 litres (5,200 gallons) of spill along the entire length
of the motorway, thereby preventing the discharge of major chemical
spills into the natural environment.
- Using linear, permanently inundated wetlands that collect pavement
runoff and transport it to receiving waterways via underflow weirs,
thereby reducing maintenance problems in low-lying, flat channels.
- Replacing grass with rock mulch (riprap) in most vegetated
swales, thereby providing a physical barrier that prevented scouring
of the channel, minimised maintenance and improved the water quality
by filtering during low-flow events.
Safeguarding and Enhancing Environmental Quality
The water quality treatment practises PB designed for this project
have been recognised by Brisbane City Council as Best Practice,
and either PB or the project were awarded the following:
- 2002 Queensland Stormwater Industry Association Award in the
Design and Planning Category (PB)
- Ministers Grand prize in the Healthy Waterways Awards 2002
(project)
- National winner in the 2003 Case Earth Awards for Environment
(project).
|
| Dave Rankin is the major projects executive
in Brisbane. He was the design manager for the Port Brisbane Motorway
project, and has 19 years’ experience in all facets of motorway
planning and design.
Fern Dorricott is an environmental engineer with the Planning and Environmental Assessment Group in Brisbane . She was the environmental representative for the Port Brisbane Motorway project, and has more than 5 years' experience in motorway environmental assessment, management and design.
Kiri Henry is a former PB employee.
Ed. Note: This article is based a presentation made at annual combined
REEA and ARRB Transport Research conference June 2003, Cairns Australia.
This paper is a result of Leisa Proses’ poster session she
presented at the Technical Exchange Program.
1 For more information about the Port of Brisbane Motorway alliance, see “Project Alliancing for Motorways” by Mike Wilke, Greg Steele and Dave Rankin, PB Network Issue No. 56, July 2003, pp.6-8. |