| PB has developed a sustainable energy solution for Midlothian
Council1 in order to meet the needs of the new town of Shawfair,
where some 4,000 homes are planned for construction. The town will
grow up on the site of the old Monktonhall colliery (a coal mine
and its facilities), which ceased production in the early 1990s.
The mine is continuously dewatered to prevent groundwater rebound
and the water is discharged to a local watercourse.
Midlothian Council intended that Shawfair be a model of sustainable
development, and supplying the town's energy from a sustainable
source was a key element in delivering this objective. The Council
proposed to use the low-grade geothermal energy resource available
in the minewater as an energy source for a district heating network
supplying the new town.
The proliferation of abandoned mine workings in the central belt
of Scotland and the associated minewater disposal issues are of
environmental concern due to the pollution risks. Minewater is generally
warmer than normal ground temperatures, however, so if it were possible
to use it as a heat source for community energy projects, an environmental
liability could be turned into a sustainable energy source.
Assessing the Opportunities
Midlothian Council appointed PB to develop the energy strategy
and outline design for the new town. We considered the technical,
environmental, economic and legal issues pertaining to a minewater
energy solution for Shawfair, and compared it to more conventional
energy supply approaches and other more innovative solutions, including
combined heat and power (CHP). The energy provision options considered
were:
- Individual (decentralised) gas fired boilers in the homes and
packaged boilers in the offices, schools and retail areas.
- Electrically driven minewater heat pumps with centralised gas
boilers feeding a community heating network
- Various combinations of interlinking CHP with minewater heat
pumps to feed a community heating network
- CHP and centralised boilers feeding a community heating network
with no minewater usage.
Technical Issues. The minewater options depended on the technical
viability of the geothermal energy source, which were evaluated
based upon on satisfying the following three criteria:
- The water source had to be hot enough to provide useful energy.
- There had to be sufficient water available for the life of
the project.
- It had to be possible to abstract the water at a rate sufficient
to provide the net power required by the project.
PB showed that these three criteria could be satisfied. The minewater
would not be used directly in the district heating network but as
a heat source for large heat pumps that would be capable of producing
hot water at 60° C (140° F). Boiler plant and/or a CHP engine
could then be used to raise the temperature to 80° C (176°
F) for distribution in the district heating. CHP units would also
generate electricity for supply to the town via a private wire electrical
network. Technically, the cooled minewater could be discharged at
the surface to the existing water treatment facility (reed beds)
or discharged back down into the coal workings at return points
away from the abstraction shaft.
Cooling for the office buildings in the centre of the town would
be provided by conventional means. Free cooling from the discharge
of the heat pump is still under consideration.
The community energy solutions considered included PB’s best
practise designs of using large temperature differences across the
flow and return pipework to reduce the network costs. Selecting
a large temperature difference means that PB could suggest innovative
design solutions to combine the characteristics of the heat pumps
and gas engine CHP systems as shown in Figure 1.

Figure 1. Sustainable Energy Solution Using Minewater |
Defining and Selecting the “Best”
Solution
We also evaluated the anticipated environmental and economic performances
of the energy provision options.
Environmental Issues. Interestingly the greatest emission saving
option depended on the carbon value attributed to electricity in
the UK. There are currently two schools of thought in the UK:
- For each kWh of electricity consumed in the UK, 430 g of CO2
are produced. This view is based upon an overall average of emissions
factors from all the grid generators in the UK, known as grid
mix.
- Distributed generation, like that discussed in this instance,
would be operating during times of peak demand and, therefore,
would prevent the marginal plant from being called on line to
meet that demand. In the UK, marginal plant is considered to be
predominantly coal-fired generation and, therefore, has a much
higher carbon emissions factor of 664 g CO2/kWh.
Option 2 consumes electricity whereas the CHP options generate
electricity, so Option 2 was ruled out from further consideration.
The greatest emissions savings option for Shawfair Town (4,000t
CO2 per annum by year 15) was Option 3 if the emissions
factor attributed to electricity is 430g CO2/kWh. Based
on an emissions factor attributed to electricity of 664 g CO2/kWh,
however, Option 4 yielded the greatest emissions savings (8,000t
CO2 per annum by year 15).
Economic Issues. An important aspect of the appraisal was to investigate
the availability of and quantify grant support for the different
options. The sources considered were INTERREG IIIB from the European
Union (EU) structural fund, and various UK-based funding programmes.
A prerequisite for INTERREG funding was project innovation, something
Option 3 met but Option 4 did not.
The economic analysis was conducted using a whole life costing
methodology as is prescribed for public spending in the UK by the
Treasury guidance, Appraisal and Evaluation in Central Government.
The enhanced funding opportunities open to the minewater options
meant that, economically, Option 4 did not compare favourably.
The inclusion of a private wire network for direct electricity
generation sales to the community and capital grant funding meant
that Option 3 would deliver the least net, present-cost solution
over 25 years. In addition, if the minewater were not used, the
perceived social benefit would be lost. Therefore, Option 3, the
minewater heat pump with CHP solution, was selected as the preferred
option on a balance of economic, environmental and social considerations.
Leading the Way Forward
We developed business plans for the project and submitted all grant
funding applications on Midlothian Council’s behalf under
budget and within all project deadlines, and eagerly anticipate
the next phase of the project. Midlothian is awaiting notification
of grant funding support and hopes to be in a position to continue
forward soon. We are particularly satisfied that this approach will
be taken into account for a client’s new build project, which
historically have tended to adopt solutions with the lowest capital
cost.
The development work for the Shawfair project has been complemented
by a national minewater energy potential study for Scotland, conducted
by PB and funded by the Scottish Executive. This study was based
on existing geothermal surveys and identified the availability of
minewater across Scotland in correlation to the density of heat
demand. The purpose of the study was to highlight areas where geothermal
district heating should be considered in more detail as part of
local sustainable energy plans. The study showed that minewater
projects could meet up to three percent of Scotland’s heat
load. |