In the pre-privatisation days, management of British Rail’s
supply functions was much like any other railway’s in that
requirements planning, procurement and material control activities
were managed and controlled on a day-to-day basis by railway staff.
While the organisation’s approach and efficiency varied from
time to time, the railway’s direct involvement in management
of supply activities was a given, as it was in most businesses at
that time.
Post-privatisation, the supply management landscape within the
rail industry changed completely. The British Rail organisation
was broken into seemingly logical business units and privatised
(or sold). The former supply management entity became several privately
owned and separate business entities. Along with the sale of the
supply unit went the inventory, historical data on usage and supply
systems used by British Rail to manage its supply activities.
At the time, this divestiture did not pose a problem because Railtrack
had made a conscious business decision to outsource its maintenance
activities. Infrastructure maintenance and up-grade contracts required
the contractor to manage, along with other things, the supply of
material, resources and plant required for their contractual maintenance
obligations. It all seemed pretty simple at the time.
Supply Chain Management Issues Surface
Over time, Railtrack embarked on a series of large infrastructure
upgrade programmes. The West Coast Route Modernisation (WCRM) is
one of these and the largest. This programme activity was on the
heel of decades of under-investment in rail infrastructure maintenance
or upgrade. The under-investment continued until the mid 1990s and
the WCRM was developed without anyone realising the impact that
such a large initiative would have on the capability of the rail
industry’s market (including the privatised companies) to
support it.
During the years of under-investment, critical labour and professional
skills migrated to other areas of endeavour, training programmes
ceased, material supply companies either went out of business or
shifted to other markets, and specialised plant and equipment grew
old and unreliable. Consequently, as the WCRM programme activity
ramped up, the rail industry market was not prepared to support
it.
During 1999, Railtrack began to realise that successful delivery
of its programme activity might be put at risk by the market’s
inability to support the volume of work. An ancillary issue was
the inefficiency generated by fragmentation of market demand for
rail industry materials and resources that resulted from independent
infrastructure maintenance planning activities. Railtrack commissioned
a study of the current supply chain environment within certain rail
industry market segments.
At approximately the same time, Railtrack started requiring firms
to tender for their programme management contracts and to demonstrate
their capability in supply chain management. PB was able to do this,
and was awarded the contract to programme manage the WCRM. We served
in that capacity from September, 1999 through February, 2002, and
continue to serve as the programme supply chain lead.
Determining Our Strategy
Initially, we spent a good deal of time clarifying our understanding
of the present state of the programme and determining what had to
be done to set it right. Part of the initial analysis dealt with
identifying existing supply chain management tools within Railtrack
and the various project teams. We identified a number of supply
management issues that had to be addressed to enhance Railtrack’s
ability to successfully deliver the WCRM programme, including the
following:
- There was no consistency of requirements across the various
projects.
- The different companies involved had solutions that ranged
from out-dated manual methods to sophisticated system solutions,
with the former being more prevalent.
- Planning horizons were three to four months at their best,
and more likely shorter.
Development of a comprehensive strategy to deal with these issues
meant dealing with each of the facets of supply that could adversely
impact programme delivery. Separate but coordinated solutions to
dealing with the supply of required materials, people and equipment
had to be developed, prioritised and aligned to mitigate the higher
risk supply issues.
Our early work had led us to the determination that critical skill
shortages were at the top of the risk register, followed by material
supply and, lastly, equipment. We developed a three-pronged WCRM
supply chain strategy that dealt with these issues through a rationalised
approach to managing the unique requirements of each. This strategy
was submitted to and approved by the programme’s general manager.
The basic premise of the strategy centred on re-development of
an aggregated, forward looking programme-wide information data base
that would allow for implementation of efficient supply processes
and mitigation strategies for each of the areas of concern. Development
of aggregated requirements plans meant that substantial data mining
efforts had to be undertaken by the supply chain team. Requirements
plans for critically skilled people, materials and equipment had
to be developed and aggregated across the programme. This was no
easy task because although some of the project teams’ planning
capabilities were reasonably good, others were non-existent.
Critical Skills
Our team set about quantifying WCRM requirements for signalling
designers, signalling testers, and people capable of performing
the design and installation of the overhead line electrification
(OLE) up-grade work. This effort was done on an eighteen-month forward-looking
horizon. The team also quantified the number of people with each
type of skill who were currently assigned or committed to work on
each project. At the same time, we also quantified the requirements
of all other major Railtrack projects for the same skills and the
total UK market capacity to satisfy those requirements.
The resulting picture indicated that acute shortages of staff skilled
in OLE installation and signalling testing would occur during various
times over the eighteen-month horizon. Armed with that knowledge,
the supply chain team began a successful search for additional non-domestic
sources of qualified people to offset the projected OLE shortages.
German and Swedish OLE installation workers were brought in to work
on two separate projects during the summer of 2000; thus enabling
the successful completion of the work.
The use of unlicensed or unqualified signal testing personnel was
not allowed due to UK regulation, so the option of using non-domestic
help was not possible in the short term due to the requirement for
assessing individual qualifications. Instead, the information that
our team developed about the signalling resource needs was presented
to executives within Railtrack Plc who, after consideration of the
data, implemented processes that created a platform for prioritisation
and deferment of work to smooth demand during peak periods.
These critical skills databases are maintained on eighteen-month
moving horizons and have been expanded to include critical skills
outside the signalling and OLE areas. They have been adopted as
a tool for management of personnel requirements within Railtrack,
including project prioritisation and personnel allocation, when
necessary. A Web-based tool for gathering personnel resource information
is underway through PB’s ProjectSolve application and is being
taken forward by Company 39.1
Our team also conducted a worldwide search for additional licensed
professionals in the signalling field. This search resulted in identification
of pools of qualified and licensed people in the British Commonwealth
countries, such as India, Australia and South Africa. Pools of non-domestic
OLE and unlicensed signalling personnel have also been identified
in the U.S., France, Romania and Switzerland, as well as in the
commonwealth countries.
Initiatives have been implemented to develop these pools of resources
through mentorship programmes being established with UK-based companies.
It is envisaged that these mentorship programmes, which are aimed
at leading to qualification and licensing, will allow for a substantial
increase in the resource capacity within the UK to take forward
various rail upgrade programmes, such as WCRM. To date, they have
increased the capacity of signal designers within the industry by
approximately 10 percent.
Material Supply
Material supply chain rationalisation presented a much different
challenge. For example, nomenclature used in conjunction with the
critical skills area was reasonably consistent, but that was not
the case with the various materials used on the projects. Each project
team had different nomenclature and processes and, other than materials
such as rail, ballast and sleepers, none of the material requirements
were being planned or leveraged on a programme-wide basis. A different
approach was needed, one that would standardize nomenclature and
procedures, and introduce the opportunity to gain supply chain efficiencies
on WCRM.
Internal development of the required materials management tools
was not considered a feasible option because it would require substantial
investments in time and money. This situation led the development
of a strategy that would bring the requisite tools to the programme
through a third party provider.
Major contract logistics players were identified and preliminary
discussions undertaken. In parallel, notices were posted in the
appropriate journals to inform the market of the WCRM’s interest
in pursuing third party logistics support. As a result, we identified
several players who could provide the systems and infrastructure
needed to provide enhanced material requirements planning capability,
warehousing and distribution support, inventory management and aggregated
material procurement/contract management services.
The third party logistics initiative is well underway, having begun
its implementation on 1 November 2001. It is bringing to the programme
necessary support in e-commerce capability, requirements planning
and forecasting, nomenclature standardisation, inventory management/distribution
and logistics planning. The initiative is also bringing significant
cost savings to the programme as a result of improved material requirements
plans, pass through supplier of production efficiencies, procurement
leverage and reduction in work disruption caused by material supply
problems.
This initiative has also generated interest within Railtrack outside
the WCRM to the point where Railtrack is currently in the process
of tendering for professional services agreements to carry forward
similar strategies on future Railtrack programme work. PB is partnering
with Unipart Rail Logistics in connection with this current tender
activity and we have been informed recently that we will be included
in the short list of tenderers.
Equipment
The last cog of the three-pronged strategy deals with an improved
approach to the supply and management of specialised on-track equipment
(plant) required to carry out the work.
Most of the strategic plant (i.e. ballast cleaners, tampers) is
provided through the contractors as either contractor owned and
operated plant or hire-plant. Railtrack has funded the acquisition
of certain major strategic plant through the contractor with the
proviso that Railtrack takes ownership at programme end. Consequently,
the supply strategy developed in relation to plant was focused on:
- Developing a view of the available plant in the UK
- Looking for opportunities to improve plant-hire mechanisms
- Developing a process to improve plant utilisation between contractors
to improve efficiency and reduce cost.
Efforts to implement this facet of the overall strategy have been
underway for several months. They are, however, still in the early
stages of development.
Results
Although implementation of the overall strategy is relatively recent,
a number of successes have already been realised:
- Three projects with significant resource problems were successfully
resourced.
- The WCRM resource management strategy has been adopted as a
Railtrack management tool.
- Resource mentorship programmes have begun.
- Seven programme-wide material framework agreements have been
tendered and are nearing award and two potential industry capacity
problems have been identified and are being addressed.
- Cross programme requirements planning forums are meeting on
a regular basis, and the importance of strategic supply planning
has been recognised and is now becoming a mainstream activity
within Railtrack.
Through our activities on WCRM, we have helped to place supply
chain management in the forefront of Railtrack’s strategic
planning. By demonstrating our capability to improve the success
of managing Railtrack’s supply chain activities, chances for
programme success have been enhanced. Railtrack now recognises the
value of determining the impact of its plans on the marketplace
and facilitating improvement in supply chain processes. |