Figure 1: River Torridge Bridge |
There were no glued (or epoxied) segmental bridges in the UK when
the design for the Torridge Bridge was started in the 1970s. This
was not the first glued segmental bridge to be built in the UK,
however, due to delays with changing design standards, public consultation
and public inquiry. It was still something of a pioneering project,
and the three 90-m (295-foot) river spans were the longest yet constructed
by this method in the UK (Figure 1).
The bridge was designed by MRM partnership — now the UK arm
of PB. The main contractor was Edmund Nuttall and the launching
girder was designed by Tony Gee and Partners.
The River Torridge starts among the high tors of Dartmoor and meanders
quietly northwards through the Devonshire countryside until it reaches
the historic port of Bideford where, quite suddenly, it is transformed
into a major tidal estuary. The old multi-span stone arch bridge
at Bideford is one of the very few medieval bridges in the country,
but as 700 years of scour and 20th century traffic were taking their
toll, a decision had been made to construct a new bridge one mile
downstream of the existing crossing where the estuary was 300-m
(984-feet) wide and flanked on both sides by land which flooded
at spring tides.
Factors Affecting the Choice of the Design
The town of Bideford owes much of its character to the shipping
that visits it, so it was essential that the new bridge not adversely
affect the somewhat fragile commercial viability of the port. For
this reason, a high level bridge was essential. Aesthetics were
at a premium because such a bridge would dominate the view from
the town, especially as the estuary was a site of great natural
beauty. The other main factors that affected the choice of the design
were the:
- Scour in the river bed
- 7.5-m (25-foot) tidal range
- Rock profile under the river
- Danger from collision with shipping
- Height of the approach embankments
- Railway and the roads which and relative position of the river
walls the bridge had to cross.

Figure 2: South Elevation |
After considering the usual range of options — from cable-stayed
spans to tunnels and a tidal barrage consisting of a dam across
the estuary with lock gates and a lifting or swing bridge to accommodate
shipping — it was decided that the most appropriate and elegant
solution would be a 650-m (2,133-foot) -long, eight-span bridge
that crossed the valley in a single entity of roughly equal, variable
depth spans — the three river spans each being 90-m (295-feet)
long and the approach spans reducing only slightly in length towards
the abutments (Figure 2).
Deck Design
It was clear from the outset that there were special problems involved
in building a series of large spans high above a tidal estuary that
dried out at low tide and had to be kept open to commercial shipping
at high tide. A balanced cantilevered construction offered the most
obvious solution, and the glued segmental precast technique that
had been developed in Europe appeared to be ideally suited for the
situation at Bideford.

Figure 3: Deck Sections |
The bridge was required to carry a single 9.3-m (30-foot) wide,
two-lane carriageway with 1.5-m (5-foot) -wide footpaths. The loading
was to be the British HA loading, which is a standard UK truck load,
together with the 180 tonne (198 ton) HB vehicle, which is a UK
permit load. After some preliminary work, it was found that the
best solution for the superstructure was a 6-m (20-foot) wide single-cell
spine beam varying in depth from 5.65 m (18.5 feet) at the piers
to 3 m (9.8 feet) at mid-span. The cantilever wings were each 3.65
m (12 feet). Design details are illustrated in Figure 3.
A 19/15 “compact” strand system was adopted for the
permanent prestressing because, at the time, this was considered
to be the largest tendon that could be stressed conveniently in
a structure of this nature. The tendons were generally tensioned
to 4330-kN (973-kp) force, which is 76 percent of their ultimate
tensile strength. For simplicity, it was decided to have only one
pair of anchors at the top and/or bottom of each segment. This led
to an optimum segment length of 2.575 m (8.45 feet). The segments
varied in weight from 56 metric tonnes to 80 metric tonnes (62 tons
to 88 tons) except for the segment on the pier (the “pierhead”
segment or “pier table”), which weighed 105 metric tonnes
(116 tons).
The primary moments and shears were obtained from grillage and continuous
beam theory, taking stage-by-stage construction into account. Additional
effects of warping, torsion, distortion and creep redistribution
were assessed initially using hand methods. These were subsequently
verified and adjusted using an early and somewhat primitive finite
element program.
Shear keys on the faces of the segments were designed primarily
to carry the newly erected segment before the epoxy glue had hardened.
They consist of a series of 400-mm (16-inch) serrations projecting
100-mm (4-inches) from the face of the web. The serrations are concealed
on the outer face by a masking nib so that the joint appears as
a clean vertical line on the finished structure.

Figure 4: Substructure |
Substructures
The deck is supported on two spill-through abutments and seven vertical
columns. The columns are coffin-shaped in cross section, tapering
from 2.5-m (8.2-feet) wide on the centre line to 1.7-m (5.6-feet)
wide at the edge (Figure 4). This shape has both structural and
aesthetic advantages. The narrow leading edge catches the eye and
gives the column a slender appearance and the inclined facets add
interest by reflecting different intensities of light and shadow.
Foundations
All foundations were on sandstone or mudstone. At the two abutments
and piers 1, 2 and 7, the rock was sufficiently close to the surface
for conventional spread footings to be used. For piers 5 and 6 (which
were protected from shipping impact by the river wall) large 2.1-m
(67-inch) diameter bored piles (drilled shafts) could be used.
In the middle of the bridge, however, the rock level dropped to
some 16 m (52.5 feet) below bed level, so the situation for piers
3 and 4 was radically different. These piers were vulnerable to
shipping impact, and a study of the alluvial deposits indicated
that 10-m (33-foot) deep scour holes might develop during spring
tides. It was decided, therefore, to found the two main river piers
on 18.5 m by 12.6 m by 16 m high (61 feet by 41 feet by 52 feet)
compressed air caissons that would be sunk to rock level where they
could resist shipping impact without support from any fill around
them and the foundation stratum could be inspected in the dry.
The bottom 3 m (10 feet) of the caissons were cast in Appledore
dry dock, made buoyant with compressed air, towed up the river on
spring tides and positioned on the sand of the river bed as the
tide ebbed. The contractor elected to construct the next 9 m (30
feet) of caisson at low tide without any excavation. During this
stage, scouring of the river bed caused the caissons to list alternately
to the east and west on the ebb and flow tides, but any out-of-plumb
was subsequently corrected by differential digging through cells
that had been provided in the design for this purpose, and the caissons
ended up vertical and correctly positioned. When mechanical excavation
through the cells was no longer possible, the caisson roof was cast
and sinking was continued to rock level by hand, digging under compressed
air.
Concrete fenders were cast on top of the caissons to protect the
more vulnerable columns from shipping impact. Rubber units were
used to ward off glancing blows, but when designing for head-on
impact it was found that the energy of such a blow would mainly
be absorbed by the collapse of the impacting vessel. The impact
force used for the design was therefore assessed by investigating
the structure of typical vessels that visited Bideford, using Gerrards
Empirical Design Method, which was developed to determine the crippling
strength of the frames of aircraft.
Precast Segment Construction
The deck segments were match-cast in a specially constructed casting
shed on site. Only one casting bed was provided, although the complicated
“pier table” units were cast in a separate form so that
there was no delay to the match-casting operation. The bridge required
251 segments, and a rate of one segment per day, had to be achieved
ultimately if the bridge was to be completed on program. The original
concrete mix contained Portland blast furnace cement to control
alkali-silica reaction, but difficulty was found in achieving adequate
early strength with this mix and in the end the contractor decided
to blend the blast furnace cement with low-alkali ordinary Portland
cement.
Stringent geometry control was applied to the match-casting operation
and the form for each segment was set taking into account the future
prestress, dead load and creep deflections and the accumulated errors
that had developed in casting the previous segments in the cantilever.

Figure 5: Figure 5: Photo showing the first 105 metric tonne
pier segment about to be placed. The launching girder is supported
on temporary steel towers. Once the segment was stressed to
the column, the girder was launched forward on rollers located
on top of the pier segment. |
Figure 5 shows the first 105 metric tonne (116-ton) pier segment
about to be placed. At this stage, the launching girder was supported
on temporary steel towers, but once the segment was stressed to
the column, the girder was launched forward on rollers located on
top of the pier segment.
Deck Erection
The method of erection assumed in the design was that the “pier
table” would be stressed vertically to the column so that
it could resist the eccentric effects of two segments being erected
on either side of it. Thereafter, it was assumed that outriggers
on a launching girder would be used to counteract any out of balance
moments that arose during erection.
This is what, in essence, was done, except that the contractor choose
to use an innovative launching girder weighing only about 150 metric
tonnes (165 tons). This girder was not only significantly lighter
(and cheaper) than that assumed in the design, it was also much
shorter, and every stage of the erection had to be carefully re-checked,
particularly the uplift effects on the last completed span. These
uplift effects often had to be counteracted by the strategic placing
of other precast units on the “back span” to act as
a counter-balance.
The units were delivered to the launching girder by a low-loader
reversing over the completed section of deck and, at one critical
stage, it was even necessary to instruct the low-loader to park
overnight at a specified location on the bridge to counteract the
adverse differential temperature stresses which would develop at
night. The uplift problems were compounded by the fact that the
program did not allow for any delay while the previous in-situ mid-span
closure pour reached strength, and a temporary steel hinge was used
to connect the ends of the penultimate two cantilevers.

Figure 6: Deck Erection |
Dywidag post-tensioning bars were used as temporary stressing to
allow two pairs of precast units to be erected ahead of the permanent
prestressing. These were left stressed in the completed cantilever
to help control the tensions across the joints when the next balanced
cantilever was under construction.
The deck was erected in eight months. Figure 6 shows construction
in progress. Note the low-tide dry riverbed.
Accolades for the Completed Bridge
The bridge was formally opened in May 1987 and received many accolades.
It won the “Concrete Society Award — 1988” together
with a commendation from the Institute of Structural Engineers,
and it was short-listed for the prestigious British Construction
Industry Award the same year. Perhaps, though, the most satisfying
accolade came from some of those who had vociferously opposed the
scheme in the early days, who said (after the bridge was completed):
“If we’d known what we were going to get, we would never
have objected to the scheme in the first place”! |