| PB Energy Storage Services constructed the U.S.'s first CAES facility for peak-shaving in Alabama's McIntosh salt
dome, where a 20-million cubic foot cavern supports a 26-hour, 110 MW power generation
plant.
KBB constructed the world's first CAES salt dome
storage cavern project at Huntorf, Germany, where two 10-million cubic foot caverns
support a 2-hour, 290 MW power plant.
|

Cavern wellhead for the first CAES plant in the U.S.
|